Description
IGF::OT::IGF P000017 - BOND FEE ADJUSTMENT FOR MODIFICATIONS ON THE 3 EAST CONSTRUCTION PROJECT AT THE OSCAR G JOHNSON VA MEDICAL CENTER, IRON MOUNTAIN, MI
Base award description: IGF::OT::IGF RENOVATE 3 EAST FOR SPECIALTY CLINICS - CONSTRUCTION CONTRACT FOR THE RENOVATION OF THE 3RD FLOOR TO ACCOMMODATE THE SPECIALTY CLINIC EXPANSION AT THE OSCAR G JOHNSON VA MEDICAL CENTER IN IRON MOUNTAIN, MI
Modification chain · 18 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2016-07-22+$5,344,281= $5,344,281
- Mod P000012016-09-09+$2,117= $5,346,398
- Mod P000022016-09-21+$3,001= $5,349,399
- Mod P000032016-09-29+$1,534= $5,350,933
- Mod P000042016-10-24+$21,739= $5,372,672
- Mod P000052016-11-30+$13,426= $5,386,098
- Mod P000062017-01-13+$2,286= $5,388,383
- Mod P000072017-04-10+$60,125= $5,448,508
- Mod P000082017-05-17+$18,483= $5,466,991
- Mod P000092017-07-05+$58,474= $5,525,465
- Mod P000102017-08-14+$22,404= $5,547,869
- Mod P000112017-09-28+$13,538= $5,561,407
- Mod P000122017-11-07+$7,378= $5,568,785
- Mod P000132018-01-09+$61,728= $5,630,513
- Mod P000142018-03-13+$21,114= $5,651,626
- Mod P000152018-06-04+$67,568= $5,719,194
- Mod P000162018-10-19+$4,417= $5,723,611
- Mod P000172018-11-30+$2,249= $5,725,860
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2016-07-22 | +$5,344,281 | $5,344,281 | IGF::OT::IGF RENOVATE 3 EAST FOR SPECIALTY CLINICS - CONSTRUCTION CONTRACT FOR THE RENOVATION OF THE 3RD FLOOR… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-09 | +$2,117 | $5,346,398 | IGF::OT::IGF P00001 - CHANGES TO THE DEPTH OF THE FOOTINGS FROM 12" TO 19" DUE TO A/E OVERSIGHT. COSTS ARE TO… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-21 | +$3,001 | $5,349,399 | IGF::OT::IGF DEMOLISH EXISTING PIPE RISER WALLS, REMOVE THE EXISTING PIPE, PERFORM ASBESTOS ABATEMENT AND REBU… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-29 | +$1,534 | $5,350,933 | IGF::OT::IGF P00003 - CB-04 - REROUTE FIRE SPRINKLER DRAIN TO SANITARY STACK LOCATED IN ROOM B003 AS SHOWN ON… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-24 | +$21,739 | $5,372,672 | IGF::OT::IGF P00004 - CB-02 - UPDATE CORRIDOR DOORS TO PROVIDE MECHANICAL ASSIST AND FIRE SECURITY FUNTIONALIT… |
| Mod P00005· CHANGE ORDER | 2016-11-30 | +$13,426 | $5,386,098 | IGF::OT::IGF P00005 - CB-05 - NEW DATA DROP IN CANTEEN AND RE-ROUTING OF THE POWER/ELECTRICAL. $13,425.64 AND… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-01-13 | +$2,286 | $5,388,383 | IGF::OT::IGF P00006 - CB-06 - INCLUDES; EXISTING VENT REPAIR, REPLACEMENT OF THE VAV FAN WHICH DOES NOT MEET T… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-04-10 | +$60,125 | $5,448,508 | IGF::OT::IGF P00007 - PER CB-07, 08,&09: THESE CHANGES ARE DUE TO AN UNFORESEEN SIGHT CONDITION NOT ADDRESSED… |
| Mod P00008· CHANGE ORDER | 2017-05-17 | +$18,483 | $5,466,991 | IGF::OT::IGF P00008 - CB10&11 - CB10: ELECTRICAL FEEDS IN DEMOLITION DO NOT PROVIDE A REPLACEMENT TO FEED OFFI… |
| Mod P00009· CHANGE ORDER | 2017-07-05 | +$58,474 | $5,525,465 | IGF::OT::IGF P00009 - PER CB12 - INCREASE THICKNESS IN OLD COOLER AREAS, LAMINATE EXISTING WALL BY ELEVATION,… |
| Mod P00010· CHANGE ORDER | 2017-08-14 | +$22,404 | $5,547,869 | IGF::OT::IGF P00010 - CB'S 13, 14&15: WORK RELATED TO THE CANTEEN KITCHEN, INCLUDING ELECTRICAL, HVAC, PLUMBIN… |
| Mod P00011· CHANGE ORDER | 2017-09-28 | +$13,538 | $5,561,407 | IGF::OT::IGF P00011 - CB-16 - ADDRESSES THE UNSPECIFIED WALL TILE, RESINOUS FLOOR AND HARD TILE CEILING WHICH… |
| Mod P00012· CHANGE ORDER | 2017-11-07 | +$7,378 | $5,568,785 | IGF::OT::IGF P00012 - CB-17 - CHANGE OUT THE LIGHTING IN THE CAFETERIA TO MEET THE VA LIGHTING STANDARDS. |
| Mod P00013· CHANGE ORDER | 2018-01-09 | +$61,728 | $5,630,513 | IGF::OT::IGF P000013 - INCORPORATES CONSTRUCTION BULLETINS 18, 19, 20,&21 TO THE 3 EAST CONSTRUCTION PROJECT… |
| Mod P00014· CHANGE ORDER | 2018-03-13 | +$21,114 | $5,651,626 | IGF::OT::IGF P000014 - INCORPORATES CONSTRUCTION BULLETIN 22 TO THE 3 EAST CONSTRUCTION PROJECT AT THE OSCAR… |
| Mod P00015· CHANGE ORDER | 2018-06-04 | +$67,568 | $5,719,194 | IGF::OT::IGF P000015 - INCORPORATES CONSTRUCTION BULLETIN 23 TO THE 3 EAST CONSTRUCTION PROJECT AT THE OSCAR… |
| Mod P00016· CHANGE ORDER | 2018-10-19 | +$4,417 | $5,723,611 | IGF::OT::IGF P000016 - INCORPORATES CONSTRUCTION BULLETIN 24 TO THE 3 EAST CONSTRUCTION PROJECT AT THE OSCAR… |
| Mod P00017· CHANGE ORDER | 2018-11-30 | +$2,249 | $5,725,860 | IGF::OT::IGF P000017 - BOND FEE ADJUSTMENT FOR MODIFICATIONS ON THE 3 EAST CONSTRUCTION PROJECT AT THE OSCAR… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI H8KMD811NZE3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C77626C0066 | PCAC (36C776) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $361,268 | FY2026 |
| 36C25226N0389 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $2,247,449 | FY2026 |
| 36C25226N0390 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $734,500 | FY2026 |
| 36C25226N0400 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $152,603 | FY2026 |
| 36C25226C0022 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $2,044,778 | FY2026 |
| 36C25026C0044 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS | $11,999,679 | FY2026 |
Other recipients under Z1DA from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25226C0042 | JV6 CONTRACTING V2 LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $4,403,098 | FY2026 |
| 36C25226N0493 | PROGRESSIVE CONSTRUCTION SERVICES LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $976,400 | FY2026 |
| 36C25226N0509 | RHI LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $111,799 | FY2026 |
| 36C25226C0036 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $131,843 | FY2026 |
| 36C25226P0501 | PRO FIRE AND WATER RESTORATION COMPANY | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $558,024 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69D16C0197_3600_-NONE-_-NONE- · retrieved 2026-09-26.