Description
IGF::OT::IGF MOD P00004 - INCORPORATE SURETY TAKEOVER AGREEMENT INTO CONTRACT DUE TO ISSUANCE OF TERMINATION FOR DEFAULT TO CANNON MANAGEMENT GROUP ON PROJECT # 537-14-109 OGDEN SUMP PUMP AND PIT INSTALLATION PROJECT AT JESSE BROWN VAMC, CHICAGO, ILLINOIS. SURETY COMPANY WILL COMPLETE OUTSTANDING WORK.
Base award description: IGF::OT::IGF OGDEN SUMP PUMP AND PIT INSTALLATION AT JESSE BROWN VAMC, CHICAGO, ILLINOIS
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2015-05-19+$89,089= $89,089
- Mod P000012015-09-21-$3,080= $86,009
- Mod P000022016-05-26+$4,822= $90,832
- Mod P000032017-01-12+$0= $90,832
- Mod P000042017-04-19+$0= $90,832
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2015-05-19 | +$89,089 | $89,089 | IGF::OT::IGF OGDEN SUMP PUMP AND PIT INSTALLATION AT JESSE BROWN VAMC, CHICAGO, ILLINOIS |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-21 | −$3,080 | $86,009 | IGF::OT::IGF MOD P00001 - PCO # 1 - REVISED DEMO PLAN AND REVISED LAYOUT OF FLOOR DRAINS AND PCO # 2 - REVISED… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-05-26 | +$4,822 | $90,832 | IGF::OT::IGF MOD P00002 - MOVE NORTH SUMP DUE TO UNFORESEEN CONDITION FOR OGDEN SUMP PUMP AND PIT INSTALLATION… |
| Mod P00003· TERMINATE FOR DEFAULT (COMPLETE OR PARTIAL) | 2017-01-12 | +$0 | $90,832 | IGF::OT::IGF MOD P00003 - TERMINATION FOR DEFAULT FOR OGDEN SUMP PUMP AND PIT INSTALLATION PROJECT AT JESSE BR… |
| Mod P00004· UNIQUE ENTITY ID OR LEGAL BUSINESS NAME CHANGE - NON-NOVATION | 2017-04-19 | +$0 | $90,832 | IGF::OT::IGF MOD P00004 - INCORPORATE SURETY TAKEOVER AGREEMENT INTO CONTRACT DUE TO ISSUANCE OF TERMINATION F… |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI HC6TJFZY4YS6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24514C0098 | 245-NETWORK CONTRACT OFFICE 5 (36C245) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $5,104,708 | FY2014 |
Other recipients under Z1DZ from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25226N0557 | U.S. VET GENERAL CONTRACTING, LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $192,487 | FY2026 |
| 36C25226N0474 | AUTOMATIC DOORS INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $472,256 | FY2026 |
| 36C25226C0032 | BLUE YONDER INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $5,868,000 | FY2026 |
| 36C25226C0018 | MOONLITE CONSTRUCTION | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $323,641 | FY2026 |
| 36C25226N0400 | INDUSTRIAL MAINTENANCE SERVICES INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $152,603 | FY2026 |