Description
IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00013: RFP-120 RFP-120; STAIRWELL JOINT SEALANT&CIP WASH CRACKS INCREASE: $6,780.00.
Base award description: IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2015-06-18+$7,721,750= $7,721,750
- Mod P000012015-09-25+$142,722= $7,864,472
- Mod P000022015-10-08+$89,231= $7,953,703
- Mod P000032015-10-13+$46,909= $8,000,612
- Mod P000042015-10-29+$68,064= $8,068,676
- Mod P000052016-02-24+$94,710= $8,163,386
- Mod P000062016-04-14-$4,543= $8,158,843
- Mod P000072016-04-29+$54,530= $8,213,373
- Mod P000082016-06-29+$138,889= $8,352,262
- Mod P000092016-06-30+$16,284= $8,368,546
- Mod P000102016-10-06+$13,964= $8,382,510
- Mod P000112016-11-15+$39,974= $8,422,485
- Mod P000122016-11-22+$0= $8,422,485
- Mod P000132017-02-01+$6,780= $8,429,265
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2015-06-18 | +$7,721,750 | $7,721,750 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4 |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-25 | +$142,722 | $7,864,472 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P0001 INCORPORATES RFPS 101:HOLE-LESS ELEVATOR, RFP 102: SOILS… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-08 | +$89,231 | $7,953,703 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00002-RFP-105; CHANGE FOR ALL SOIL DISPOSAL TO WM LANDFILL SI… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-13 | +$46,909 | $8,000,612 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00003-RFP 104/CB-02-RFP 104R1: ELEVATOR EQUIP ROOM, LIGHT POL… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-29 | +$68,064 | $8,068,676 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00004: RFP 106/CB-03: TELESCOPING HOLED HYDRAULIC ELEVATORS… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-02-24 | +$94,710 | $8,163,386 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00005:RFP 108; DELAY CLAIM INCREASE: $94,710.15 |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-14 | −$4,543 | $8,158,843 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00006:RFP 107; REMOVE FA SYSTEM&DEVICES AND RFP-109:ELEVATOR… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-04-29 | +$54,530 | $8,213,373 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00007:INCORPORATES RFP 111/CB-08: DRAIN TILE MODIFICATIONS,RF… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-29 | +$138,889 | $8,352,262 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00008: WINTER CONDITIONS $138,889.02 |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-30 | +$16,284 | $8,368,546 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00009: INCORPORATES RFP-114/CB-12 WATER METER AND ELEVATOR R… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-10-06 | +$13,964 | $8,382,510 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00010: INCORPORATES RFP-117 BIOSWALE, PARK STRIPING, STAIR IN… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-11-15 | +$39,974 | $8,422,485 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00011: RFP-119 ELEVATOR EMERGENCY POWER. INCREASE: $39,974.18 |
| Mod P00012· CHANGE ORDER | 2016-11-22 | +$0 | $8,422,485 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00012: RFP-119 ELEVATOR EMERGENCY POWER. NO COST TIME EXTENSI… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-02-01 | +$6,780 | $8,429,265 | IGF::OT::IGF CONSTRUCT PARKING STRUCTURE, LOT 4-P00013: RFP-120 RFP-120; STAIRWELL JOINT SEALANT&CIP WASH CRAC… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI KSWVYZ1M7WZ3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25226N0493 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $976,400 | FY2026 |
| 36C25226N0355 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $382,900 | FY2026 |
| 36C25226N0349 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $559,900 | FY2026 |
| 36C25226N0346 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $5,237,900 | FY2026 |
| 36C25226C0017 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $4,393,000 | FY2026 |
| 36C25226N0323 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $2,248,000 | FY2026 |
Other recipients under Y1DZ from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25226C0043 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $3,464,800 | FY2026 |
| 36C25226C0006 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $3,353,007 | FY2026 |
| 36C25225C0056 | BLUE YONDER INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $0 | FY2025 |
| 36C25225C0052 | AMERITECH CONTRACTING LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $2,094,000 | FY2025 |
| 36C25225C0028 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $331,124 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69D15C0177_3600_-NONE-_-NONE- · retrieved 2026-09-26.