Description
IGF::OT::IGF BUILDING 41 FACADE CONSTRUCTION-P00006, RFP-105; STAINED GLASS WINDOW REPLACEMENT $9,023.00
Base award description: IGF::OT::IGF BUILDING 41 FACADE CONSTRUCTION
Modification chain · 7 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-07-31+$733,440= $733,440
- Mod P000012014-11-10+$0= $733,440
- Mod P000022015-03-04+$0= $733,440
- Mod P000032015-09-24+$2,847= $736,287
- Mod P000042015-10-28+$10,361= $746,648
- Mod P000052015-11-24+$1,852= $748,500
- Mod P000062016-01-08+$9,023= $757,523
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-07-31 | +$733,440 | $733,440 | IGF::OT::IGF BUILDING 41 FACADE CONSTRUCTION |
| Mod P00001· CHANGE ORDER | 2014-11-10 | +$0 | $733,440 | IGF::OT::IGF BUILDING 41 FACADE CONSTRUCTION-P00001: SUSPEND WORK ORDER |
| Mod P00002· CHANGE ORDER | 2015-03-04 | +$0 | $733,440 | IGF::OT::IGF BUILDING 41 FACADE CONSTRUCTION-P00002: SUSPEND WORK ORDER |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-24 | +$2,847 | $736,287 | IGF::OT::IGF BUILDING 41 FACADE CONSTRUCTION-P00003: PORCH SUPPORT RE-SUPPORT $2,847.00 |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-28 | +$10,361 | $746,648 | IGF::OT::IGF BUILDING 41 FACADE CONSTRUCTION-P00004:RFP-102; UNFORESEEN SITE CONDITIONS, RFP-103; PORCH REBUIL… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-24 | +$1,852 | $748,500 | IGF::OT::IGF BUILDING 41 FACADE CONSTRUCTION-P00005, RFP-104; REPLACE BEAM-INCREASE $1,852.00 |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-08 | +$9,023 | $757,523 | IGF::OT::IGF BUILDING 41 FACADE CONSTRUCTION-P00006, RFP-105; STAINED GLASS WINDOW REPLACEMENT $9,023.00 |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ZJE3GTWE6D36)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA69D16J6000 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $104,449 | FY2016 |
| VA69D16C0293 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $510,740 | FY2016 |
| VA69D16J5225 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $533,186 | FY2016 |
| VA69D16J4507 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $920,504 | FY2016 |
| VA69D16J3602 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $339,641 | FY2016 |
| VA69D16D0157 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $0 | FY2016 |
Other recipients under Z1DA from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA69D16P2374 | DAHME MECHANICAL INDUSTRIES INC | 69D-NETWORK CONTRACT OFFICE 12 | $61,000 | FY2016 |
| VA69D16D0094 | OPCON, INC. | 69D-NETWORK CONTRACT OFFICE 12 | $0 | FY2016 |
| VA69D16J1442 | P & M CONTRACTORS, INC. | 69D-NETWORK CONTRACT OFFICE 12 | $38,688 | FY2016 |
| VA69D16J1370 | P & M CONTRACTORS, INC. | 69D-NETWORK CONTRACT OFFICE 12 | $51,722 | FY2016 |
| VA69D16P1801 | TROPICAL ENVIRONMENTAL INC | 69D-NETWORK CONTRACT OFFICE 12 | $3,460 | FY2016 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69D14C0301_3600_-NONE-_-NONE- · retrieved 2026-09-26.