Award recordCONTRACT

PROGRESSIVE CONSTRUCTION SERVICES LLC

PIID VA69D14C0208· VHA· 69D-NETWORK CONTRACT OFFICE 12· Y1LB · CONSTRUCTION OF HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS· FY2014· $2,013,687 net obligations· UEI KSWVYZ1M7WZ3· WI

Description

IGF::OT::IGF - SITE S.E. AREA PARKING LOT - CONSTRUCT NEW PARKING LOT AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE WI P00003-INCORPORATES THE FOLLOWING RFP: RFP109R1-CONCRETE MODS AND WIRE UPSIZING

Base award description: IGF::OT::IGF - SITE S.E. AREA PARKING LOT - CONSTRUCT NEW PARKING LOT AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE WI

First action · last action
2014-05-08 · 2015-02-17
Transactions
4
First transaction's obligation
$1,843,000
Base + all options value (sum of deltas)
$2,013,687
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
6
SDVOSB flag on record
Yes (self-representation)
NAICS
237310 · HIGHWAY, STREET, AND BRIDGE CONSTRUCTION

Modification chain · 4 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$2,013,687$0Base award · 2014-05-08 · this action $1,843,000 · running total $1,843,000Modification P00001 · 2015-01-15 · this action $93,855 · running total $1,936,855Modification P00002 · 2015-01-20 · this action $67,190 · running total $2,004,045Modification P00003 · 2015-02-17 · this action $9,642 · running total $2,013,687
  • Base2014-05-08+$1,843,000= $1,843,000
  • Mod P000012015-01-15+$93,855= $1,936,855
  • Mod P000022015-01-20+$67,190= $2,004,045
  • Mod P000032015-02-17+$9,642= $2,013,687
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2014-05-08+$1,843,000$1,843,000IGF::OT::IGF - SITE S.E. AREA PARKING LOT - CONSTRUCT NEW PARKING LOT AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE W…
Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-15+$93,855$1,936,855IGF::OT::IGF - SITE S.E. AREA PARKING LOT - CONSTRUCT NEW PARKING LOT AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE W…
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-01-20+$67,190$2,004,045IGF::OT::IGF - SITE S.E. AREA PARKING LOT - CONSTRUCT NEW PARKING LOT AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE W…
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2015-02-17+$9,642$2,013,687IGF::OT::IGF - SITE S.E. AREA PARKING LOT - CONSTRUCT NEW PARKING LOT AT CLEMENT J. ZABLOCKI VAMC, MILWAUKEE W…

Related awards · 6

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI KSWVYZ1M7WZ3)

AwardOffice · PSC / listingNet obligationsFY
36C25226N0493252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$976,400FY2026
36C25226N0355252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$382,900FY2026
36C25226N0349252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$559,900FY2026
36C25226N0346252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$5,237,900FY2026
36C25226C0017252-NETWORK CONTRACT OFFICE 12 (36C252) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES$4,393,000FY2026
36C25226N0323252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$2,248,000FY2026

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69D14C0208_3600_-NONE-_-NONE- · retrieved 2026-09-26.