Description
IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTENDENCE, MATERIALS, TOOLS, EQUIPMENT, TRANSPORTATION, LICENSES, INSURANCE, TEMPORARY PROTECTION, MINOR DEMOLITION, GENERAL CONSTRUCTION, MECHANICAL AND ELECTRICAL WORK, PREPARATION, WORK FOR EQUIPMENT, UTILITY SYSTEMS AND OTHER ITEMS REQUIRED UNDER THE PROVISIONS OF THIS CONTRACT. THE NEW FACILITY SHALL BE A STAND-ALONE THREE (3) STORY BUILDING, APPROXIMATELY 30,000 GROSS SQUARE FEET FOR 75 PATIENT BEDS. THIS PROJECT SHALL ALSO INCLUDE A 50 FOOT LONG, ENCLOSED CORRIDOR TO CONNECT THE NEW BUILDING WITH EXISTING BUILDING 404. AWARDED CONTRACT IS FOR BID ITEM 3, WHEREBY PARTIAL DEDUCTS FOR THE INTERIOR BUILD-OUT OF THE 1ST AND 2ND FLOORS SHALL BE APPLIED. MOD-P0016 INCORPORATES FINAL SETTLEMENT FOR TWO CONTRACTOR CLAIMS AND THREE CREDITS DUE TO THE VA RELATED TO REVISED PRECAST&CABINETRY AND CREDITS FOR ADDITIONAL HEATING, GROUT ALTERNATE AND ELEVATOR FINISH ALTERNATE. MOD-P00017 IS A DEDUCT FOR PAVEMENT STRIPING NO LONGER REQUIRED.
Base award description: IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTENDENCE, MATERIALS, TOOLS, EQUIPMENT, TRANSPORTATION, LICENSES, INSURANCE, TEMPORARY PROTECTION, MINOR DEMOLITION, GENERAL CONSTRUCTION, MECHANICAL AND ELECTRICAL WORK, PREPARATION, WORK FOR EQUIPMENT, UTILITY SYSTEMS AND OTHER ITEMS REQUIRED UNDER THE PROVISIONS OF THIS CONTRACT. THE NEW FACILITY SHALL BE A STAND-ALONE THREE (3) STORY BUILDING, APPROXIMATELY 30,000 GROSS SQUARE FEET FOR 75 PATIENT BEDS. THIS PROJECT SHALL ALSO INCLUDE A 50 FOOT LONG, ENCLOSED CORRIDOR TO CONNECT THE NEW BUILDING WITH EXISTING BUILDING 404. AWARDED CONTRACT IS FOR BID ITEM 3, WHEREBY PARTIAL DEDUCTS FOR THE INTERIOR BUILD-OUT OF THE 1ST AND 2ND FLOORS SHALL BE APPLIED.
Modification chain · 17 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-05-22+$7,257,351= $7,257,351
- Mod P000012014-12-10+$14,387= $7,271,738
- Mod P000022015-03-19+$12,812= $7,284,550
- Mod P000042015-06-04+$18,326= $7,302,876
- Mod P000052015-06-08+$90,224= $7,393,100
- Mod P000062015-07-30+$14,864= $7,407,964
- Mod P000072016-01-08+$0= $7,407,964
- Mod P000082016-02-05+$0= $7,407,964
- Mod P000092016-03-28+$227,487= $7,635,451
- Mod P000102016-05-05+$82,921= $7,718,372
- Mod P000112016-06-21+$37= $7,718,409
- Mod P000122016-07-15+$4,694= $7,723,103
- Mod P000132016-07-27+$0= $7,723,103
- Mod P000142016-09-07+$9,517= $7,732,620
- Mod P000152017-03-24-$4,163= $7,728,457
- Mod P000162017-03-24+$200,000= $7,928,457
- Mod P000172017-05-22-$1,000= $7,927,457
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-05-22 | +$7,257,351 | $7,257,351 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-10 | +$14,387 | $7,271,738 | IGF::OT::IGF - PROJECT 676-3222 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINT… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-19 | +$12,812 | $7,284,550 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-06-04 | +$18,326 | $7,302,876 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-06-08 | +$90,224 | $7,393,100 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-07-30 | +$14,864 | $7,407,964 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00007· CHANGE ORDER | 2016-01-08 | +$0 | $7,407,964 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-02-05 | +$0 | $7,407,964 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-03-28 | +$227,487 | $7,635,451 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-05-05 | +$82,921 | $7,718,372 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-06-21 | +$37 | $7,718,409 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-07-15 | +$4,694 | $7,723,103 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00013· CHANGE ORDER | 2016-07-27 | +$0 | $7,723,103 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-09-07 | +$9,517 | $7,732,620 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-24 | −$4,163 | $7,728,457 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-03-24 | +$200,000 | $7,928,457 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-05-22 | −$1,000 | $7,927,457 | IGF::OT::IGF - PROJECT 676-322 CONSTRUCT B405 FOR 75 MHRRTP BEDS: PROVIDE FOR AND FURNISH ALL LABOR, SUPERINTE… |
Related awards · 8
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI QJKNRML5QTN6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA101F17D3107 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1AA · CONSTRUCTION OF OFFICE BUILDINGS | $0 | FY2017 |
| VA69D17C0195 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $145,644 | FY2017 |
| VA69D13C0131 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $8,214,698 | FY2013 |
Other recipients under Y1DA from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25225C0027 | TL SERVICES, INC. | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $12,399 | FY2025 |
| 36C25225C0004 | VORTEX INDUSTRIES LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $24,581 | FY2025 |
| 36C25222N0327 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $1,457,672 | FY2022 |
| 36C25222C0023 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $4,205,450 | FY2022 |
| 36C25222N0123 | RICHARD GROUP LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $4,726,328 | FY2022 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69D14C0190_3600_-NONE-_-NONE- · retrieved 2026-09-26.