Description
IGF::OT::IGF - P00011 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI.
Base award description: IGF::OT::IGF - CONSOLIDATE ICU'S AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI.
Modification chain · 12 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-05-05+$7,634,790= $7,634,790
- Mod P000012014-07-24+$0= $7,634,790
- Mod P000022014-08-18+$20,588= $7,655,378
- Mod P000032014-12-01+$39,726= $7,695,104
- Mod P000042015-03-18+$56,967= $7,752,071
- Mod P000052015-05-19+$66,153= $7,818,224
- Mod P000062015-06-10+$77,976= $7,896,200
- Mod P000072015-07-23+$35,219= $7,931,419
- Mod P000082015-08-18+$52,558= $7,983,977
- Mod P000092015-10-27+$78,599= $8,062,576
- Mod P000102015-12-10+$79,244= $8,141,820
- Mod P000112016-02-26+$17,548= $8,159,368
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-05-05 | +$7,634,790 | $7,634,790 | IGF::OT::IGF - CONSOLIDATE ICU'S AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-24 | +$0 | $7,634,790 | IGF::OT::IGF - P00001 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-18 | +$20,588 | $7,655,378 | IGF::OT::IGF - P00002 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-01 | +$39,726 | $7,695,104 | IGF::OT::IGF - P00003 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-18 | +$56,967 | $7,752,071 | IGF::OT::IGF - P00004 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-05-19 | +$66,153 | $7,818,224 | IGF::OT::IGF - P00005 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-06-10 | +$77,976 | $7,896,200 | IGF::OT::IGF - P00006 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-07-23 | +$35,219 | $7,931,419 | IGF::OT::IGF - P00007 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-18 | +$52,558 | $7,983,977 | IGF::OT::IGF - P00008 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-27 | +$78,599 | $8,062,576 | IGF::OT::IGF - P00009 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-12-10 | +$79,244 | $8,141,820 | IGF::OT::IGF - P00010 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-02-26 | +$17,548 | $8,159,368 | IGF::OT::IGF - P00011 FOR THE CONSOLIDATE ICU'S PROJECT AT THE WM S. MIDDLETON VA HOSPITAL MADISON WI. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI NTT5F9DDYJW4)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25221C0020 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $4,939,549 | FY2021 |
| 36C25221C0010 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $3,887,833 | FY2021 |
| 36C25220C0120 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $5,642,897 | FY2020 |
| 36C25218C0040 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $6,108,490 | FY2018 |
| VA69D17C0302 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $7,476,959 | FY2017 |
| VA69D16C0191 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $3,874,195 | FY2016 |
Other recipients under Z1DZ from 69D-NETWORK CONTRACT OFFICE 12 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA69D16J2920 | RHI LLC | 69D-NETWORK CONTRACT OFFICE 12 | $6,200 | FY2016 |
| VA69D16J1763 | C3T, INC. | 69D-NETWORK CONTRACT OFFICE 12 | $4,206 | FY2016 |
| VA69D15J5623 | OPCON, INC. | 69D-NETWORK CONTRACT OFFICE 12 | $178,450 | FY2015 |
| VA69D15J4736 | C3T, INC. | 69D-NETWORK CONTRACT OFFICE 12 | $71,959 | FY2015 |
| VA69D15J4695 | C3T, INC. | 69D-NETWORK CONTRACT OFFICE 12 | $32,463 | FY2015 |