Description
IGF::OT::IGF - MODIFICATION P00015 ESTABLISHES THAT THE CONTRACTOR AND VA BOTH AGREE ON A SETTLEMENT AMOUNT OF $99,998.00 FOR REA 001 FOR CONTRACT VA69D-13-C-0209, PROJECT 695-13-131, AT THE MILWAUKEE VAMC.
Base award description: IGF::OT::IGF - 102 111 EXPAND SUPPLY PROCESSING SERVICES (SPS)
Modification chain · 16 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2013-06-28+$8,820,000= $8,820,000
- Mod P000012013-12-06+$17,757= $8,837,757
- Mod P000022014-03-31+$65,849= $8,903,606
- Mod P000032014-06-02+$81,770= $8,985,376
- Mod P000042014-08-04+$99,644= $9,085,020
- Mod P000052014-10-17+$91,802= $9,176,822
- Mod P000062014-11-14+$77,498= $9,254,320
- Mod P000072014-12-11+$48,788= $9,303,108
- Mod P000082015-02-05+$69,294= $9,372,402
- Mod P000092015-03-12+$4,880= $9,377,282
- Mod P000102015-03-23+$0= $9,377,282
- Mod P000112015-04-27-$242,344= $9,134,938
- Mod P000122015-06-24+$29,905= $9,164,843
- Mod P000132015-07-28+$77,027= $9,241,870
- Mod P000142015-10-27+$15,702= $9,257,572
- Mod P000152017-02-15+$99,998= $9,357,570
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2013-06-28 | +$8,820,000 | $8,820,000 | IGF::OT::IGF - 102 111 EXPAND SUPPLY PROCESSING SERVICES (SPS) |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-06 | +$17,757 | $8,837,757 | IGF::OT::IGF - 102 111 EXPAND SUPPLY PROCESSING SERVICES (SPS)P00001-RFP-101: CB-01: RTU 166A CHANGES |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-03-31 | +$65,849 | $8,903,606 | IGF::OT::IGF - 102 111 EXPAND SUPPLY PROCESSING SERVICES (SPS)P00002-RFPS 104, 106, AND 107 |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-06-02 | +$81,770 | $8,985,376 | IGF::OT::IGF - P00003-RFPS 105, 108, AND 110 - 102 111 EXPAND SUPPLY PROCESSING SERVICES (SPS) |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-08-04 | +$99,644 | $9,085,020 | IGF::OT::IGF - MODIFICATION P00004 INCORPORATES RFPS RFP 109, 111, AND 112 FOR CONTRACT VA69D-13-C-0209, 102 1… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-10-17 | +$91,802 | $9,176,822 | IGF::OT::IGF - P00003-RFPS 105, 108, AND 110 - 102 111 EXPAND SUPPLY PROCESSING SERVICES (SPS) |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-11-14 | +$77,498 | $9,254,320 | IGF::OT::IGF - MOD P00006, RFP 118R1 GENERATOR REVISIONS FOR 102 111 EXPAND SUPPLY PROCESSING SERVICES (SPS) |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-12-11 | +$48,788 | $9,303,108 | IGF::OT::IGF - MOD P00007 WHICH INCLUDES RFPS 115 (CB-11 LOADING DOCK REMOVE CEILING), 116 (CB-08R2 HARD-LID C… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-02-05 | +$69,294 | $9,372,402 | IGF::OT::IGF - MOD P00008 WHICH INCLUDES RFPS 115 (CB-11 LOADING DOCK REMOVE CEILING), 116 (CB-08R2 HARD-LID C… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-12 | +$4,880 | $9,377,282 | IGF::OT::IGF - MOD P00009 WHICH INCORPORATES RFP 122, BLDG. 102 DOOR POSITION SWITCH AND BLDG. 111 DOCK COMPRE… |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-23 | +$0 | $9,377,282 | IGF::OT::IGF - MOD P00010 IS A SUSPENSION OF WORK FOR CONTRACT VA69D-13-C-0209, PROJECT 695-13-131. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-04-27 | −$242,344 | $9,134,938 | IGF::OT::IGF - MOD P00009 WHICH INCORPORATES RFP 122, BLDG. 102 DOOR POSITION SWITCH AND BLDG. 111 DOCK COMPRE… |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-06-24 | +$29,905 | $9,164,843 | IGF::OT::IGF - MOD P00012 INCORPORATES RFP 126 (CB 13 POWER FOR STEAM HUMIDIFIER, DAMPER MOTORS&FIRE ALARM BEL… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-07-28 | +$77,027 | $9,241,870 | IGF::OT::IGF - MOD P00009 WHICH INCORPORATES RFP 122, BLDG. 102 DOOR POSITION SWITCH AND BLDG. 111 DOCK COMPRE… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-10-27 | +$15,702 | $9,257,572 | IGF::OT::IGF - MOD P00014 WHICH INCORPORATES RFP 134, POWER TO CART WASHERS, UNDER CONTRACT VA69D-13-C-0209, P… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-02-15 | +$99,998 | $9,357,570 | IGF::OT::IGF - MODIFICATION P00015 ESTABLISHES THAT THE CONTRACTOR AND VA BOTH AGREE ON A SETTLEMENT AMOUNT OF… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ZJE3GTWE6D36)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA69D16J6000 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $104,449 | FY2016 |
| VA69D16C0293 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $510,740 | FY2016 |
| VA69D16J5225 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $533,186 | FY2016 |
| VA69D16J4507 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $920,504 | FY2016 |
| VA69D16J3602 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $339,641 | FY2016 |
| VA69D16D0157 | 252-NETWORK CONTRACT OFFICE 12 (36C252) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $0 | FY2016 |
Other recipients under Z1DA from 252-NETWORK CONTRACT OFFICE 12 (36C252) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25226C0042 | JV6 CONTRACTING V2 LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $4,403,098 | FY2026 |
| 36C25226N0493 | PROGRESSIVE CONSTRUCTION SERVICES LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $976,400 | FY2026 |
| 36C25226N0509 | RHI LLC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $111,799 | FY2026 |
| 36C25226C0036 | TROOP CONTRACTING INC | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $131,843 | FY2026 |
| 36C25226P0501 | PRO FIRE AND WATER RESTORATION COMPANY | 252-NETWORK CONTRACT OFFICE 12 (36C252) | $558,024 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA69D13C0209_3600_-NONE-_-NONE- · retrieved 2026-09-26.