Description
DEOBLIGATION MOD
Base award description: DESIGN - CHILLER PLANT UPDATES
Modification chain · 2 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-12-16+$53,483= $53,483
- Mod AM12010-08-31-$231= $53,252
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-12-16 | +$53,483 | $53,483 | DESIGN - CHILLER PLANT UPDATES |
| Mod AM1· FUNDING ONLY ACTION | 2010-08-31 | −$231 | $53,252 | DEOBLIGATION MOD |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI KX6BMSE3TEF8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA25813J0828 | 258-NETWORK CONTRACT OFFICE 18 · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $122,109 | FY2013 |
| VA25812J1277 | 258-NETWORK CONTRACT OFFICE 18 · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $20,107 | FY2012 |
| VA25812J1101 | 258-NETWORK CONTRACT OFFICE 18 · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $15,045 | FY2012 |
| VA25812J1067 | 644-PHOENIX · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $17,045 | FY2012 |
| VA25812J0387 | 678-TUCSON · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $96,463 | FY2012 |
| VA25812J0170 | 257-NETWORK CONTRACT OFFICE 17 (36C257) · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $977,762 | FY2012 |
Other recipients under C211 from 678-TUCSON (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA678C10395 | GLHN ARCHITECTS & ENGINEERS INC | 678-TUCSON | $66,582 | FY2011 |
| V678C70385 | WESTLAKE, REED, LESKOSKY, LTD. | 678-TUCSON | -$12,008 | FY2011 |
| VA678C00391 | GLHN ARCHITECTS & ENGINEERS INC | 678-TUCSON | $193,329 | FY2010 |
| V678C70319 | GLHN ARCHITECTS & ENGINEERS INC | 678-TUCSON | -$3,212 | FY2010 |
| V678C50445 | LIZARD ROCK DESIGNS LLC | 678-TUCSON | -$12,021 | FY2010 |