Description
DECREASE OF EXPIRING FY07 FUNDS.
Base award description: TAKEOVER AGREEMENT WITH THE SURETY FOR COMPLETION OF PUNCH LIST ITEMS.
Modification chain · 2 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-03-30+$0= $0
- Mod P000022012-09-11-$10,725= -$10,725
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-30 | +$0 | $0 | TAKEOVER AGREEMENT WITH THE SURETY FOR COMPLETION OF PUNCH LIST ITEMS. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-11 | −$10,725 | -$10,725 | DECREASE OF EXPIRING FY07 FUNDS. |
Related awards · 9
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI NGH3RD9F5QK5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| V672C90273 | 672S-SAN JUAN SMALL PURHCASE · J041 · MAINT-REP OF REFRIGERATION - AC EQ | $6,382 | FY2009 |
| VA672C0045 | 248-NETWORK CONTRACT OFFICE 8 · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $25,151 | FY2008 |
| VA672C0016 | 672-SAN JUAN · Y242 · CONSTRUCT/HEATING & COOLING PLANTS | $35,500 | FY2008 |
| VA672C0030 | 672-SAN JUAN · Y111 · CONSTRUCTION OF OFFICE BUILDINGS | $9,035 | FY2008 |
Other recipients under Z141 from 248-NETWORK CONTRACT OFFICE 8 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA248C0168 | JWD ENGINEERING CORP | 248-NETWORK CONTRACT OFFICE 8 | $38,391 | FY2012 |
| VA248C18660001 | BLUE CORD DESIGN AND CONSTRUCTION, LLC | 248-NETWORK CONTRACT OFFICE 8 | $5,456,912 | FY2011 |
| VA248C1866 | BLUE CORD DESIGN AND CONSTRUCTION, LLC | 248-NETWORK CONTRACT OFFICE 8 | $0 | FY2011 |
| VA248C1887 | AYE AYE CONSTRUCTION, LLC | 248-NETWORK CONTRACT OFFICE 8 | $137,705 | FY2011 |
| VA248C1969 | ACRO CONSTRUCTION, LLC | 248-NETWORK CONTRACT OFFICE 8 | $88,685 | FY2011 |