Description
OF 649-11-101 STEAM LINE DESIGN
Base award description: 649-11-101 CAMPUS STEAM TUNNEL REPAIRS
Modification chain · 2 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-06-12+$64,711= $64,711
- Mod P000012012-11-13-$4,761= $59,950
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-06-12 | +$64,711 | $64,711 | 649-11-101 CAMPUS STEAM TUNNEL REPAIRS |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-13 | −$4,761 | $59,950 | OF 649-11-101 STEAM LINE DESIGN |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI GQMAJ174UHM5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA25813J1321 | 258-NETWORK CNTRCT OFF 22G (36C258) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $505,719 | FY2013 |
| VA25813J1328 | 258-NETWORK CNTRCT OFF 22G (36C258) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $104,478 | FY2013 |
| VA25813J0970 | 258-NETWORK CNTRCT OFF 22G (36C258) · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $1,298,207 | FY2013 |
| VA25813J0563 | 258-NETWORK CONTRACT OFFICE 18 · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $219,258 | FY2013 |
| VA25813J0776 | 258-NETWORK CONTRACT OFFICE 18 · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $99,871 | FY2013 |
| VA25812J1351 | 258-NETWORK CNTRCT OFF 22G (36C258) · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $196,413 | FY2013 |
Other recipients under C215 from 644-PHOENIX (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA644Z100002 | DURRANT GROUP INC, THE | 644-PHOENIX | $442,218 | FY2011 |
| VA644X100001 | SMITHGROUP, INC. | 644-PHOENIX | $210,374 | FY2011 |
| VA644C01267 | DURRANT GROUP INC, THE | 644-PHOENIX | $22,386 | FY2010 |
| VA644C01268 | SMITHGROUP, INC. | 644-PHOENIX | $179,234 | FY2010 |
| VA649C00123 | NTD ARCHITECTS | 644-PHOENIX | $112,050 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA649C90159_3600_VA258P0204_3600 · retrieved 2026-09-26.