Award recordCONTRACT

STV-ELLERBE BECKET JV

PIID VA620C10381· VHA· 243-NTWRK CNTNG FUND OFC 03(00243· C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING· FY2011· $172,740 net obligations· UEI N9DLZHTQLWM5· NY

Description

THE IS MODIFICATION IS TO DESCOPE REMAINING WORK AND DEOBLIGATE REMAINING BALANCE FOR CLOSE OUT.

Base award description: ARCHITECT AND ENGINEERING SERVICES FOR VISN 3. PROJECT 620-11-105 REPAIR SEWER LINES AT HUDSON VALLEY VA, MONTROSE CAMPUS.

First action · last action
2011-09-29 · 2016-04-15
Transactions
3
First transaction's obligation
$262,484
Base + all options value (sum of deltas)
$172,740
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
30
SDVOSB flag on record
No
Parent IDV
VA243P0234
NAICS
541310 · ARCHITECTURAL SERVICES

Modification chain · 3 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$262,484$0Base award · 2011-09-29 · this action $262,484 · running total $262,484Modification P00001 · 2013-03-26 · this action -$42,868 · running total $219,617Modification P00002 · 2016-04-15 · this action -$46,877 · running total $172,740
  • Base2011-09-29+$262,484= $262,484
  • Mod P000012013-03-26-$42,868= $219,617
  • Mod P000022016-04-15-$46,877= $172,740
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2011-09-29+$262,484$262,484ARCHITECT AND ENGINEERING SERVICES FOR VISN 3. PROJECT 620-11-105 REPAIR SEWER LINES AT HUDSON VALLEY VA, MONT…
Mod P00001· CHANGE ORDER2013-03-26−$42,868$219,617THE IS MODIFICATION IS FOR ADDITIONAL ENVIRONMENTAL WORK AS WELL A REDUCTION IN SCOPE.
Mod P00002· CLOSE OUT2016-04-15−$46,877$172,740THE IS MODIFICATION IS TO DESCOPE REMAINING WORK AND DEOBLIGATE REMAINING BALANCE FOR CLOSE OUT.

Related awards · 6

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI N9DLZHTQLWM5)

AwardOffice · PSC / listingNet obligationsFY
36C24218C0053242-NETWORK CONTRACT OFFICE 02 (36C242) · C1DZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER HOSPITAL BUILDINGS$88,020FY2018
VA24313J0084243-NETWORK CONTRACTING OFFICE 03 · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER$250,696FY2012
VA24312J2517243-NETWORK CONTRACTING OFFICE 03 · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING$24,290FY2012
VA24312J2504243-NETWORK CONTRACTING OFFICE 03 · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING$83,288FY2012
VA526C20441243-NETWORK CONTRACTING OFFICE 03 · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING$382,498FY2012
VA24312J1780242-NETWORK CONTRACT OFFICE 02 (36C242) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES$460,549FY2012

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA620C10381_3600_VA243P0234_3600 · retrieved 2026-09-26.