Description
THE WORK CONSISTS OF ALL LABOR, EQUIPMENT, MATERIALS, TOOLS, ACCESSORIES, SUPERVISION AND ALL OPERATIONS REQUIRED TO CONSTRUCT 8,050 LINEAR FEET OF NEW FENCE. WORK TO INCLUDE BUT NOT LIMITED TO CLEARING/REMOVING BRUSH ,TREES , VEGETATION, AN AREA OF BOULDERS, A SECTION OF CONCRETE SLAB, CONCRETE FOOTING OF OLD GREEN HOUSE, NEW 6 FOOT HIGH PVC COATED CHAIN LINK FENCE WITH TOP RAIL, BOTTOM WIRE , ACCESSORIES AND GATES AS SHOWN ON DRAWINGS. CONCRETE FOOTINGS FOR FENCE POST, LOCATED IN DENSE SOIL, ROCK AND WET AREAS, LOCATION AND MARKOUT OF UNDERGROUND UTILITIES WITHIN 40 PARAMETER OF FENCE LINE (20 FEET EACH SIDE OF FENCE LINE).PERFORM WORK SPECIFIED HEREIN AND COMPLY WITH VA SPECIFICATIONS AND VA REGULATIONS, PROCEDURES AND CONDITIONS FOR WORK AT THE MEDICAL CENTER AND ANY APPLICABLE CODES AS PER REQUIREMENTS OF ALL GOVERNING AGENCIES AND OTHER RELATED AND ANCILLARY WORK. CONTRACTOR SHALL DISPOSE OF WOOD AND CHIPPED MATERIALS SPREAD IN LEVEL BLANKET OVER THE PATH WIDTH FOR A DRIVING SURFACE. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR, PRIOR TO BIDDING THIS JOB, TO INSPECT THE WORK SITE, DETERMINE THE QUANTITY OF WORK INVOLVED, CHECK DIMENSIONS, COMPARE THE SPECIFICATIONS WITH THE WORK TO BE DONE, AND INFORM THEMSELVES AS TO ALL EXISTING SITE CONDITIONS. FAILURE TO DO SO WILL IN NO WAY RELIEVE THE SUCCESSFUL CONTRACTOR FROM WORK THAT MAY BE REQUIRED TO CARRY OUT THE TERMS OF THIS CONTRACT IN ACCORDANCE WITH THE TRUE INTENT AND MEANING OF THE PLANS, WITHOUT ADDITIONAL COST TO THE OWNER.
Modification chain · 1 transaction
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-05-06+$495,000= $495,000
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-05-06 | +$495,000 | $495,000 | THE WORK CONSISTS OF ALL LABOR, EQUIPMENT, MATERIALS, TOOLS, ACCESSORIES, SUPERVISION AND ALL OPERATIONS REQUI… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI M6DYB8PSFFY5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA25116J0006 | 550-DANVILLE(00550) · S222 · HOUSEKEEPING- WASTE TREATMENT/STORAGE | $60,187 | FY2016 |
| VA25114J2769 | 550-DANVILLE · S222 · HOUSEKEEPING- WASTE TREATMENT/STORAGE | $119,441 | FY2015 |
| VA25114J3572 | 550-DANVILLE · S222 · HOUSEKEEPING- WASTE TREATMENT/STORAGE | $112,323 | FY2014 |
| VA25112J2779 | 550-DANVILLE · S222 · HOUSEKEEPING- WASTE TREATMENT/STORAGE | $123,829 | FY2013 |
| VA550C27009 | 550-DANVILLE · S222 · HOUSEKEEPING- WASTE TREATMENT/STORAGE | $65,936 | FY2012 |
| VA620C10300 | 243-NETWORK CONTRACTING OFFICE 03 · C114 · HOSPITAL BUILDINGS | $25,439 | FY2011 |
Other recipients under Y111 from 243-NETWORK CONTRACTING OFFICE 03 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA630C11394 | CONCENTRIC GROUP, LLC | 243-NETWORK CONTRACTING OFFICE 03 | $190,666 | FY2011 |
| VA243C1207 | CONCENTRIC GROUP, LLC | 243-NETWORK CONTRACTING OFFICE 03 | $7,761,181 | FY2011 |
| VA243C1186 | GCC ENTERPRISES INC. | 243-NETWORK CONTRACTING OFFICE 03 | $2,497,000 | FY2011 |
| VA630C11413 | REGIMENT CONSTRUCTION CORP | 243-NETWORK CONTRACTING OFFICE 03 | $70,260 | FY2011 |
| VA630C11414 | REGIMENT CONSTRUCTION CORP | 243-NETWORK CONTRACTING OFFICE 03 | $31,500 | FY2011 |