Award recordCONTRACT

ADCO COMPANIES, LTD.

PIID VA619C95261· VHA· 619-CENTRAL ALABAMA· J099 · MAINT-REP OF MISC EQ· FY2009· $9,744 net obligations· UEI L114LNJ4UQP7· AL

Description

138BPT: 1 VENDOR WILL FURNISH ALL MATERIAL AND LABOR TO REPAIR #3 BOILER AT 2400 HOSPITAL ROAD, TUSKEGEE, AL. SCOPE OF WORK - 1. VENDOR WILL PATCH MAIN FURNACE REFRACTORY FRONT, REAR, LEFT AND RIGHT SIDES. 2. VENDOR WILL REMOVE AND REPLACE FIRST TWO BRICK COURSES FROM THE FURNACE WALL, INCLUDING ARCH BRICK. 3. REPLACE THE TWO COURSES OF HIGH DUTY BRICK IN ADDITION TO THE ACCESS DOOR ARCH. 4. REPAIR GENERATIANG BANK REFRACTORY BAFFLE. 5. REPAIR BURNER THROAT REFRACTORY. 6. REPAIR HOLES IN BRICK WALL. 7. OTHER VENDORS JASON KUHN 704-562-1794, CORN SERVICE 704-864-7707. 8. VENDOR MUST PROVIDE SAFETY MAN TO WATCH BOILER ENTRANCE HOLE AND MONITOR FOR GAS. 1

First action · last action
2009-03-10 · 2009-03-10
Transactions
1
First transaction's obligation
$9,744
Base + all options value (sum of deltas)
$9,744
Extent competed
COMPETED UNDER SAP
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
3
SDVOSB flag on record
No

Modification chain · 1 transaction

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$9,744$0Base award · 2009-03-10 · this action $9,744 · running total $9,744
  • Base2009-03-10+$9,744= $9,744
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2009-03-10+$9,744$9,744138BPT: 1 VENDOR WILL FURNISH ALL MATERIAL AND LABOR TO REPAIR #3 BOILER AT 2400…

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI L114LNJ4UQP7)

AwardOffice · PSC / listingNet obligationsFY
36C24726P0319247-NETWORK CONTRACT OFFICE 7 (36C247) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS$21,726FY2026
36C24724P1044247-NETWORK CONTRACT OFFICE 7 (36C247) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS$0FY2024
36C24724P0044247-NETWORK CONTRACT OFFICE 7 (36C247) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT$416,528FY2024
36C24724P0055247-NETWORK CONTRACT OFFICE 7 (36C247) · J044 · MAINT/REPAIR/REBUILD OF EQUIPMENT- FURNACE, STEAM PLANT, AND DRYING EQUIPMENT; NUCLEAR REACTORS$544,144FY2024
36C25623P0896256-NETWORK CONTRACT OFFICE 16 (36C256) · J049 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MAINTENANCE AND REPAIR SHOP EQUIPMENT$0FY2023
36C24723P0697247-NETWORK CONTRACT OFFICE 7 (36C247) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT$36,187FY2023

Other recipients under J099 from 619-CENTRAL ALABAMA (most recent first)

AwardRecipientOfficeNet obligationsFY
VA619C15254DAD'S ENTERPRISES, INC.619-CENTRAL ALABAMA$34,412FY2011
VA619C15268JOHNSON CONTROLS, INC619-CENTRAL ALABAMA$18,740FY2011
VA619C15255PARTSSOURCE INC619-CENTRAL ALABAMA$3,198FY2011
VA619C15230BOB'S ELITE BUILDERS, LLC619-CENTRAL ALABAMA$3,189FY2011
VA619C05143SENTINEL CLEANING INC619-CENTRAL ALABAMA$6,800FY2010

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA619C95261_3600_-NONE-_-NONE- · retrieved 2026-09-26.