Description
END OF OPT YR 4, EXERCISING 52.217-8 THROUGH 3/30/16
Base award description: TURNKEY DESIGN AND CONSTRUCTION SERVICES TO COMPLETE SITE PREP, BUILDOUT AND LEASE OF A 20,000 SF MODULAR BUILDING.
Modification chain · 9 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-09-30+$1,213,871= $1,213,871
- Mod 12011-02-14+$99,885= $1,313,756
- Mod 22011-09-19+$58,139= $1,371,895
- Mod 32011-09-26-$67,483= $1,304,412
- Mod 42011-10-03+$256,976= $1,561,388
- Mod P000052012-10-01+$256,976= $1,818,363
- Mod P000062013-10-01+$256,976= $2,075,339
- Mod P000072014-10-01+$256,976= $2,332,314
- Mod P000082015-10-01+$128,488= $2,460,802
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-09-30 | +$1,213,871 | $1,213,871 | TURNKEY DESIGN AND CONSTRUCTION SERVICES TO COMPLETE SITE PREP, BUILDOUT AND LEASE OF A 20,000 SF MODULAR BUIL… |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-14 | +$99,885 | $1,313,756 | TURNKEY DESIGN AND CONSTRUCTION SERVICES TO COMPLETE SITE PREP, BUILDOUT AND LEASE OF A 20,000 SF MODULAR BUIL… |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-19 | +$58,139 | $1,371,895 | TURNKEY DESIGN AND CONSTRUCTION SERVICES TO COMPLETE SITE PREP, BUILDOUT AND LEASE OF A 20,000 SF MODULAR BUIL… |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-26 | −$67,483 | $1,304,412 | TURNKEY DESIGN AND CONSTRUCTION SERVICES TO COMPLETE SITE PREP, BUILDOUT AND LEASE OF A 20,000 SF MODULAR BUIL… |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-10-03 | +$256,976 | $1,561,388 | TURNKEY DESIGN AND CONSTRUCTION SERVICES TO COMPLETE SITE PREP, BUILDOUT AND LEASE OF A 20,000 SF MODULAR BUIL… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-01 | +$256,976 | $1,818,363 | TURNKEY DESIGN AND CONSTRUCTION SERVICES TO COMPLETE SITE PREP, BUILDOUT AND LEASE OF A 20,000 SF MODULAR BUIL… |
| Mod P00006· EXERCISE AN OPTION | 2013-10-01 | +$256,976 | $2,075,339 | TURNKEY DESIGN AND CONSTRUCTION SERVICES TO COMPLETE SITE PREP, BUILDOUT AND LEASE OF A 20,000 SF MODULAR BUIL… |
| Mod P00007· EXERCISE AN OPTION | 2014-10-01 | +$256,976 | $2,332,314 | OPTION YR 4 OF FSS MODULAR BLDG ORDER |
| Mod P00008· EXERCISE AN OPTION | 2015-10-01 | +$128,488 | $2,460,802 | END OF OPT YR 4, EXERCISING 52.217-8 THROUGH 3/30/16 |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI JRWNS9LNFMK1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25520F0026 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · 5410 · PREFABRICATED AND PORTABLE BUILDINGS | $400,943 | FY2020 |
| 36C25519F0023 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · 5410 · PREFABRICATED AND PORTABLE BUILDINGS | $84,480 | FY2019 |
| VA25616P0647 | 256-NETWORK CONTRACT OFFICE 16 · 5410 · PREFABRICATED AND PORTABLE BUILDINGS | $807,036 | FY2016 |
| VA25516F0629 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · 5410 · PREFABRICATED AND PORTABLE BUILDINGS | $253,440 | FY2016 |
| VA25615F0876 | 256-NETWORK CONTRACT OFFICE 16 · 5410 · PREFABRICATED AND PORTABLE BUILDINGS | $96,897 | FY2015 |
| VA119A14C0037 | SAC FREDERICK (36C10X) · X1CZ · LEASE/RENTAL OF OTHER EDUCATIONAL BUILDINGS | $368,891 | FY2014 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA580C00609_3600_GS07F0358J_4730 · retrieved 2026-09-26.