Description
SA P00002 ADDS WITHIN SCOPE DESIGN CHANGES TO REMEDY CAVITATION PROBLEMS AT CONDENSATION TOWER WATER PUMPS.
Base award description: 2. THE MAJOR SCOPE ITEMS FOR THIS PROJECT INCLUDES: A. DESIGN FOR THE INSTALLATION OF A NEW 1200 TON CHILLER AND COOLING TOWER TO INCLUDE EVALUATION OF ENERGY CONSERVING APPLICATION ALTERNATIVES INCLUDING A HEAT PUMP CHILLER SYSTEM. B. DESIGN FOR THE INSTALLATION OF A NEW 2000 KW GENERATOR AND SWITCHGEAR. C. DESIGN FOR THE INSTALLATION OF CONNECTING ANY REMAINING CANDIDATE STAND-ALONE OR MEDICAL EQUIPMENT COOLING PROCESS LOADS TO THE EXISTING DEDICATED PROCESS COOLING WATER LOOP.
Modification chain · 3 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-03-31+$350,720= $350,720
- Mod 12011-04-20+$126,292= $477,012
- Mod P000022012-12-12+$12,451= $489,463
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-03-31 | +$350,720 | $350,720 | 2. THE MAJOR SCOPE ITEMS FOR THIS PROJECT INCLUDES: A. DESIGN FOR THE INSTALLATION OF A NEW 1200 TON CHILLER A… |
| Mod 1· CHANGE ORDER | 2011-04-20 | +$126,292 | $477,012 | 2. THE MAJOR SCOPE ITEMS FOR THIS PROJECT INCLUDES: A. DESIGN FOR THE INSTALLATION OF A NEW 1200 TON CHILLER A… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-12 | +$12,451 | $489,463 | SA P00002 ADDS WITHIN SCOPE DESIGN CHANGES TO REMEDY CAVITATION PROBLEMS AT CONDENSATION TOWER WATER PUMPS. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI NLSDASB6NFV6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25019N0778 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $23,150 | FY2019 |
| 36C25019N0347 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $489,434 | FY2019 |
| 36C25018N3580 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $69,761 | FY2018 |
| 36C25018N3265 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $83,257 | FY2018 |
| 36C25018N1422 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $167,000 | FY2018 |
| VA25017J4969 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $285,020 | FY2017 |
Other recipients under C211 from 541-BRECKSVILLE (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA25014J3053 | CHAMPLIN/HAUPT ARCHITECTS INC | 541-BRECKSVILLE | $19,400 | FY2014 |
| VA25013J2108 | CBLH DESIGN INC | 541-BRECKSVILLE | $0 | FY2013 |
| VA25013P1537 | MAKOVICH & PUSTI ARCHITECTS INC | 541-BRECKSVILLE | $22,857 | FY2013 |
| VA25014J0547 | CHAMPLIN/HAUPT ARCHITECTS INC | 541-BRECKSVILLE | $0 | FY2013 |
| VA25013J1472 | CHAMPLIN/HAUPT ARCHITECTS INC | 541-BRECKSVILLE | $86,200 | FY2013 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA541C02022_3600_VA250P0475_3600 · retrieved 2026-09-26.