SINK REPLACEMENT AND MODIFICATION AND REMOVAL OF CEMENT
Base award description: RENOVATION OF DENTAL CLINIC TO INCLUDE THE INSTALLATION OF THREE (3) NEW DENTAL CHAIRS. ALSO INCLUDES THE RELOCATION OF THE BLOOD DRAW LAB.
Modification chain · 4 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-09-15+$303,372= $303,372
- Mod 12008-12-10+$16,204= $319,576
- Mod 22009-04-24+$16,702= $336,277
- Mod 32009-10-06+$6,655= $342,932
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2008-09-15 | +$303,372 | $303,372 | RENOVATION OF DENTAL CLINIC TO INCLUDE THE INSTALLATION OF THREE (3) NEW DENTAL CHAIRS. ALSO INCLUDES THE RELO… |
| Mod 1· OTHER ADMINISTRATIVE ACTION | 2008-12-10 | +$16,204 | $319,576 | INCORPORATION OF REVISED DAVIS BACON WAGE DETERMINATION (MONROE COUNTY VERSUS ONTARIO COUNTY). |
| Mod 2· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-04-24 | +$16,702 | $336,277 | ADDITIONAL SOUNDPROOFING AND SANITARY DRAIN WORK UNDER DIFFERING SITE CONDITIONS. |
| Mod 3· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-10-06 | +$6,655 | $342,932 | SINK REPLACEMENT AND MODIFICATION AND REMOVAL OF CEMENT |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI R34MRBPK3E94)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA24216J1957 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $2,000 | FY2016 |
| VA78616P0792 | NATIONAL CEMETERY ADMIN (36C786) · Y1QA · CONSTRUCTION OF RESTORATION OF REAL PROPERTY (PUBLIC OR PRIVATE) | $11,500 | FY2016 |
| VA52815J1361 | 242-NETWORK CONTRACT OFFICE 02 · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $2,000 | FY2015 |
| VA52814D0067 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $0 | FY2014 |
| VA52814C0033 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $944,835 | FY2014 |
| VA52814P0057 | 242-NETWORK CONTRACT OFFICE 02 · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $80,943 | FY2014 |
Other recipients under Z141 from 242-NETWORK CONTRACT OFFICE 02 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA528C0946 | LOZIER ENVIRONMENTAL CONSULTING, INC | 242-NETWORK CONTRACT OFFICE 02 | $17,190 | FY2011 |
| VA5280952 | WELCH CONSTRUCTION INC. | 242-NETWORK CONTRACT OFFICE 02 | $156,000 | FY2011 |
| VA528C0951 | MONUMENT CONSTRUCTION LLC | 242-NETWORK CONTRACT OFFICE 02 | $2,275,471 | FY2011 |
| VA528C15300 | ST. JOSEPH'S HEALTH SYSTEMS INC | 242-NETWORK CONTRACT OFFICE 02 | $4,600 | FY2011 |
| VA528C0950 | WELCH CONSTRUCTION INC. | 242-NETWORK CONTRACT OFFICE 02 | $459,025 | FY2011 |