Description
TAS::36 0158::TAS PROJECT 568-09-101 CONSISTS OF TOTAL RENOVATION OF APPROXIMATELY 1,600 SF OF EXISTING SPACE WITHIN BUILDING 148 TO PROVIDE NEW ADMINISTRATIVE OFFICE SPACE. WORK INVOLVES DEMOLITION AND REPLACEMENT OF EXISTING WALLS, FINISHES, MECHANICAL AND ELECTRICAL SYSTEMS WITHIN THE PROJECT AREA. WORK ALSO INVOLVES REPLACEMENT OF AN EXTERIOR WINDOW WALL WITH NEW BRICK FA ADE, WINDOWS, AND EXIT DOOR.
Base award description: TAS::36 0158 000::TAS PROJECT 568-09-101 CONSISTS OF TOTAL RENOVATION OF APPROXIMATELY 1,600 SF OF EXISTING SPACE WITHIN BUILDING 148 TO PROVIDE NEW ADMINISTRATIVE OFFICE SPACE. WORK INVOLVES DEMOLITION AND REPLACEMENT OF EXISTING WALLS, FINISHES, MECHANICAL AND ELECTRICAL SYSTEMS WITHIN THE PROJECT AREA. WORK ALSO INVOLVES REPLACEMENT OF AN EXTERIOR WINDOW WALL WITH NEW BRICK FA ADE, WINDOWS, AND EXIT DOOR.
Modification chain · 5 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-04-10+$252,347= $252,347
- Mod 12009-09-16+$1,958= $254,305
- Mod 22009-11-04+$6,919= $261,224
- Mod 32009-11-12+$1,407= $262,632
- Mod 42010-01-25+$0= $262,632
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-04-10 | +$252,347 | $252,347 | TAS::36 0158 000::TAS PROJECT 568-09-101 CONSISTS OF TOTAL RENOVATION OF APPROXIMATELY 1,600 SF OF EXISTING SP… |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-16 | +$1,958 | $254,305 | TAS::36 0158::TAS PROJECT 568-09-101 CONSISTS OF TOTAL RENOVATION OF APPROXIMATELY 1,600 SF OF EXISTING SPACE… |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-04 | +$6,919 | $261,224 | TAS::36 0158::TAS PROJECT 568-09-101 CONSISTS OF TOTAL RENOVATION OF APPROXIMATELY 1,600 SF OF EXISTING SPACE… |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-12 | +$1,407 | $262,632 | TAS::36 0158::TAS PROJECT 568-09-101 CONSISTS OF TOTAL RENOVATION OF APPROXIMATELY 1,600 SF OF EXISTING SPACE… |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-25 | +$0 | $262,632 | TAS::36 0158::TAS PROJECT 568-09-101 CONSISTS OF TOTAL RENOVATION OF APPROXIMATELY 1,600 SF OF EXISTING SPACE… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI TWDTCRDNY5G7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA263C0670 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $50,271 | FY2009 |
| VA263C0634 | 568-VA BLACK HILLS HEALTH CARE SYSTEM · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $403,991 | FY2009 |
| V568C90587 | 568S-VA BLACK HILLS HEALTH CARE SYSTEM · Z199 · MAINT-REP-ALT/MISC BLDGS | $3,795 | FY2009 |
| V568C90564 | 568S-VA BLACK HILLS HEALTH CARE SYSTEM · Z199 · MAINT-REP-ALT/MISC BLDGS | $16,594 | FY2009 |
| V568C90513 | 568S-VA BLACK HILLS HEALTH CARE SYSTEM · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | $4,225 | FY2009 |
| V568P95655 | 568S-VA BLACK HILLS HEALTH CARE SYSTEM · 9999 · MISCELLANEOUS ITEMS | $4,097 | FY2009 |
Other recipients under Z141 from 568-VA BLACK HILLS HEALTH CARE SYSTEM (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA263C1373 | JOURNEY CONSTRUCTION, INC. | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $259,712 | FY2011 |
| VA263C1350 | GCH CONSTRUCTION COMPANY | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $89,400 | FY2011 |
| VA263C1331 | GCH CONSTRUCTION COMPANY | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $126,517 | FY2011 |
| VA263C1311 | BOULDER HILL CONSTRUCTION LLC | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $8,504 | FY2011 |
| VA263C1235 | GCH CONSTRUCTION COMPANY | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $105,332 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA263RA0635_3600_-NONE-_-NONE- · retrieved 2026-09-26.