Description
PROJECT 636-11-828, CONSTRUCT ADA SIDEWALK AND SOUTH STEPS FOR MODULAR BUILDING D AT THE NEBRASKA-WESTERN IOWA HEALTH CARE SYSTEM, OMAHA (NE) VA MEDICAL CENTER.
Modification chain · 2 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-05-02+$9,347= $9,347
- Mod 12011-06-30+$3,171= $12,518
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-05-02 | +$9,347 | $9,347 | PROJECT 636-11-828, CONSTRUCT ADA SIDEWALK AND SOUTH STEPS FOR MODULAR BUILDING D AT THE NEBRASKA-WESTERN IOWA… |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-30 | +$3,171 | $12,518 | PROJECT 636-11-828, CONSTRUCT ADA SIDEWALK AND SOUTH STEPS FOR MODULAR BUILDING D AT THE NEBRASKA-WESTERN IOWA… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI NJFASMLTSRR5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26312P1615 | 636-NEBRASKA WESTERN-IOWA · J043 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PUMPS AND COMPRESSORS | $4,335 | FY2012 |
| VA26312C0086 | 636-NEBRASKA WESTERN-IOWA · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $17,065 | FY2012 |
| VA263C1303 | 636-NEBRASKA WESTERN-IOWA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $5,804 | FY2011 |
| V636SM1679 | 636-NEBRASKA WESTERN-IOWA · J099 · MAINT-REP OF MISC EQ | $9,845 | FY2011 |
| V636SL1043 | 636-NEBRASKA WESTERN-IOWA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $9,975 | FY2011 |
| V636SM1534 | 636-NEBRASKA WESTERN-IOWA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $18,894 | FY2011 |
Other recipients under Z141 from 636-NEBRASKA WESTERN-IOWA (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA263C1357 | COVENANT CONSTRUCTION SERVICES LLC | 636-NEBRASKA WESTERN-IOWA | $70,046 | FY2011 |
| VA263C1341 | L & J BUILDING COMPANY LLC | 636-NEBRASKA WESTERN-IOWA | $139,951 | FY2011 |
| VA263C1343 | MIDWEST CONTRACTING, INC. | 636-NEBRASKA WESTERN-IOWA | $447,481 | FY2011 |
| VA263C1342 | KOZIOL UPHOLSTERING & CONCRETE | 636-NEBRASKA WESTERN-IOWA | $9,075 | FY2011 |
| VA263C1338 | WINN CONSTRUCTION COMPANY | 636-NEBRASKA WESTERN-IOWA | $462,062 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA263C1238_3600_-NONE-_-NONE- · retrieved 2026-09-26.