Description
CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRINGS, SD
Modification chain · 29 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-09-23+$625,800= $625,800
- Mod SA12011-02-15+$8,499= $634,299
- Mod SA22011-03-10+$3,871= $638,170
- Mod SA32011-03-10+$6,307= $644,477
- Mod SA42011-04-12+$1,505= $645,983
- Mod SA52011-04-20+$7,660= $653,642
- Mod SA62011-04-28+$2,614= $656,256
- Mod SA72011-05-24+$5,301= $661,557
- Mod SA82011-06-17+$8,364= $669,921
- Mod SA92011-06-21+$520= $670,441
- Mod SA102011-07-12+$8,148= $678,589
- Mod SA112011-07-13+$740= $679,329
- Mod SA122011-07-19+$10,512= $689,840
- Mod SA132011-08-17+$9,544= $699,384
- Mod SA142011-08-28+$1,420= $700,804
- Mod SA152011-09-11+$9,943= $710,747
- Mod SA162011-11-10+$2,239= $712,986
- Mod SA172011-12-29+$2,894= $715,880
- Mod SA182012-04-13+$4,274= $720,154
- Mod SA192012-04-25+$25,354= $745,508
- Mod P00012012-06-25+$1,469= $746,978
- Mod P000022012-08-14+$6,503= $753,481
- Mod P000032012-10-05+$2,237= $755,718
- Mod P000042012-10-31+$37,571= $793,289
- Mod P000052012-10-31+$4,355= $797,644
- Mod P000062012-10-31+$11,395= $809,040
- Mod P000072012-10-31-$37,571= $771,468
- Mod P000082012-10-31+$110= $771,578
- Mod P000102012-10-31+$3,534= $775,112
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-09-23 | +$625,800 | $625,800 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA1· CHANGE ORDER | 2011-02-15 | +$8,499 | $634,299 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA2· CHANGE ORDER | 2011-03-10 | +$3,871 | $638,170 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA3· CHANGE ORDER | 2011-03-10 | +$6,307 | $644,477 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-12 | +$1,505 | $645,983 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-20 | +$7,660 | $653,642 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-28 | +$2,614 | $656,256 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-24 | +$5,301 | $661,557 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-17 | +$8,364 | $669,921 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-21 | +$520 | $670,441 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-12 | +$8,148 | $678,589 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-13 | +$740 | $679,329 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-07-19 | +$10,512 | $689,840 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-17 | +$9,544 | $699,384 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-08-28 | +$1,420 | $700,804 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA15· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-11 | +$9,943 | $710,747 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA16· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-10 | +$2,239 | $712,986 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-29 | +$2,894 | $715,880 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA18· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-13 | +$4,274 | $720,154 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod SA19· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-25 | +$25,354 | $745,508 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod P0001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-25 | +$1,469 | $746,978 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-08-14 | +$6,503 | $753,481 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-05 | +$2,237 | $755,718 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-31 | +$37,571 | $793,289 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-31 | +$4,355 | $797,644 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-31 | +$11,395 | $809,040 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-31 | −$37,571 | $771,468 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod P00008· FUNDING ONLY ACTION | 2012-10-31 | +$110 | $771,578 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
| Mod P00010· FUNDING ONLY ACTION | 2012-10-31 | +$3,534 | $775,112 | CONTRACTOR TO COMPLETE PROJECT 568-10-201, EXPAND DIALYSIS AT THE VA BLACK HILLS HEALTH CARE SYSTEM. HOT SPRIN… |
Related awards · 7
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI F7JVEZDEMLM1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25021P0374 | 250-NETWORK CONTRACT OFFICE 10 (36C250) · 6640 · LABORATORY EQUIPMENT AND SUPPLIES | $184,500 | FY2021 |
| 36C25621P0314 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · 6515 · MEDICAL AND SURGICAL INSTRUMENTS, EQUIPMENT, AND SUPPLIES | $12,654 | FY2021 |
| 36C25521P0086 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · 7125 · CABINETS, LOCKERS, BINS, AND SHELVING | $54,585 | FY2021 |
| 36C24221P0146 | 242-NETWORK CONTRACT OFFICE 02 (36C242) · 6640 · LABORATORY EQUIPMENT AND SUPPLIES | $171,462 | FY2021 |
| 36C25921P0009 | NETWORK CONTRACT OFFICE 19 (36C259) · H163 · QUALITY CONTROL- ALARM, SIGNAL, AND SECURITY DETECTION SYSTEMS | $59,835 | FY2021 |
| 36C24821N0074 | 248-NETWORK CONTRACT OFFICE 8 (36C248) · 6640 · LABORATORY EQUIPMENT AND SUPPLIES | $80,265 | FY2021 |
Other recipients under Z111 from 568-VA BLACK HILLS HEALTH CARE SYSTEM (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA568C00612 | TARRAF CONSTRUCTION, INC. | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $49,343 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA263C1069_3600_-NONE-_-NONE- · retrieved 2026-09-26.