Description
PROJECT 636-13-103, AE DESIGN SERVICES FOR REPLACE BOILERS AT THE GRAND ISLAND DIVISION OF THE NEBRASKA-WESTERN IOWA HEALTH CARE SYSTEM. IGF::CT::IGF MODIFICATION TO REMOVE THE CONSTRUCTION PERIOD SERVICES.
Base award description: PROJECT 636-13-103, AE DESIGN SERVICES FOR REPLACE BOILERS AT THE GRAND ISLAND DIVISION OF THE NEBRASKA-WESTERN IOWA HEALTH CARE SYSTEM. IGF::CT::IGF
Modification chain · 2 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-12-21+$156,624= $156,624
- Mod P000012015-05-11-$44,418= $112,206
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-12-21 | +$156,624 | $156,624 | PROJECT 636-13-103, AE DESIGN SERVICES FOR REPLACE BOILERS AT THE GRAND ISLAND DIVISION OF THE NEBRASKA-WESTER… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-05-11 | −$44,418 | $112,206 | PROJECT 636-13-103, AE DESIGN SERVICES FOR REPLACE BOILERS AT THE GRAND ISLAND DIVISION OF THE NEBRASKA-WESTER… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI MSBTMNAYAW55)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26326C0059 | NETWORK CONTRACT OFFICE 23 (36C263) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $268,349 | FY2026 |
| 36C25626N0722 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $677,940 | FY2026 |
| 36C25626N0581 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $454,704 | FY2026 |
| 36C25526C0027 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $368,543 | FY2026 |
| 36C25526C0019 | 255-NETWORK CONTRACT OFFICE 15 (36C255) · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $349,066 | FY2026 |
| 36C25626N0223 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $1,159,344 | FY2026 |
Other recipients under C212 from 636-NEBRASKA WESTERN-IOWA (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA263BO0123 | LEO A. DALY LLC | 636-NEBRASKA WESTERN-IOWA | $0 | FY2010 |
| VA636SD0467 | LEO A. DALY LLC | 636-NEBRASKA WESTERN-IOWA | $83,843 | FY2010 |
| V636A6P1923 | LEO A. DALY LLC | 636-NEBRASKA WESTERN-IOWA | $0 | FY2010 |
| VA636SD0308 | LEO A. DALY LLC | 636-NEBRASKA WESTERN-IOWA | $19,494 | FY2010 |
| V636SD0284 | GREEN COMPANIES, INC. | 636-NEBRASKA WESTERN-IOWA | $16,670 | FY2010 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA26313J0569_3600_VA263P1064_3600 · retrieved 2026-09-26.