Award recordCONTRACT

COVENANT CONSTRUCTION SERVICES LLC

PIID VA26313C0188· VHA· NETWORK CONTRACT OFFICE 23 (36C263)· Y1NB · CONSTRUCTION OF HEATING AND COOLING PLANTS· FY2013· $10,462,421 net obligations· UEI P3CTJ2KMB3J8· IA

Description

BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 014&016 636A6-11-916 IGF::OT::IGF

Base award description: BOILER PLANT CONSTRUCTION PROJECT 636A6-11-916 IGF::OT::IGF

First action · last action
2013-06-28 · 2019-06-10
Transactions
18
First transaction's obligation
$9,479,815
Base + all options value (sum of deltas)
$10,462,421
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
1
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION

Modification chain · 18 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$10,462,421$0Base award · 2013-06-28 · this action $9,479,815 · running total $9,479,815Modification P00001 · 2013-09-27 · this action $5,806 · running total $9,485,621Modification P00002 · 2014-04-04 · this action $142,714 · running total $9,628,335Modification P00003 · 2014-05-11 · this action $0 · running total $9,628,335Modification P00005 · 2014-06-05 · this action $88,413 · running total $9,716,748Modification P00006 · 2014-10-20 · this action $1,046 · running total $9,717,794Modification P00007 · 2015-03-05 · this action $54,646 · running total $9,772,440Modification P00008 · 2015-03-30 · this action -$4,863 · running total $9,767,577Modification P00009 · 2015-04-01 · this action $8,248 · running total $9,775,825Modification P00010 · 2015-09-21 · this action $14,920 · running total $9,790,745Modification P00011 · 2016-06-24 · this action $37,359 · running total $9,828,104Modification P00012 · 2017-05-12 · this action $43,605 · running total $9,871,709Modification P00013 · 2017-06-26 · this action $50,429 · running total $9,922,138Modification P00014 · 2017-06-26 · this action $54,014 · running total $9,976,152Modification P00015 · 2018-07-08 · this action $443,746 · running total $10,419,898Modification P00016 · 2018-08-24 · this action $6,000 · running total $10,425,898Modification P00017 · 2018-10-01 · this action $0 · running total $10,425,898Modification P00018 · 2019-06-10 · this action $36,523 · running total $10,462,421
  • Base2013-06-28+$9,479,815= $9,479,815
  • Mod P000012013-09-27+$5,806= $9,485,621
  • Mod P000022014-04-04+$142,714= $9,628,335
  • Mod P000032014-05-11+$0= $9,628,335
  • Mod P000052014-06-05+$88,413= $9,716,748
  • Mod P000062014-10-20+$1,046= $9,717,794
  • Mod P000072015-03-05+$54,646= $9,772,440
  • Mod P000082015-03-30-$4,863= $9,767,577
  • Mod P000092015-04-01+$8,248= $9,775,825
  • Mod P000102015-09-21+$14,920= $9,790,745
  • Mod P000112016-06-24+$37,359= $9,828,104
  • Mod P000122017-05-12+$43,605= $9,871,709
  • Mod P000132017-06-26+$50,429= $9,922,138
  • Mod P000142017-06-26+$54,014= $9,976,152
  • Mod P000152018-07-08+$443,746= $10,419,898
  • Mod P000162018-08-24+$6,000= $10,425,898
  • Mod P000172018-10-01+$0= $10,425,898
  • Mod P000182019-06-10+$36,523= $10,462,421
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2013-06-28+$9,479,815$9,479,815BOILER PLANT CONSTRUCTION PROJECT 636A6-11-916 IGF::OT::IGF
Mod P00001· CHANGE ORDER2013-09-27+$5,806$9,485,621BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 001 636A6-11-916 IGF::OT::IGF
Mod P00002· CHANGE ORDER2014-04-04+$142,714$9,628,335BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 001 636A6-11-916 IGF::OT::IGF
Mod P00003· CHANGE ORDER2014-05-11+$0$9,628,335BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 001 636A6-11-916 IGF::OT::IGF
Mod P00005· CHANGE ORDER2014-06-05+$88,413$9,716,748BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 001 636A6-11-916 IGF::OT::IGF
Mod P00006· CHANGE ORDER2014-10-20+$1,046$9,717,794BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 001 636A6-11-916 IGF::OT::IGF
Mod P00007· CHANGE ORDER2015-03-05+$54,646$9,772,440BOILER PLANT CONSTRUCTION PROJECT, MOD P00007 FOR COR 7,8,9 636A6-11-916 IGF::OT::IGF
Mod P00008· CHANGE ORDER2015-03-30−$4,863$9,767,577BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 001 636A6-11-916 IGF::OT::IGF
Mod P00009· CHANGE ORDER2015-04-01+$8,248$9,775,825BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 001 636A6-11-916 IGF::OT::IGF
Mod P00010· CHANGE ORDER2015-09-21+$14,920$9,790,745BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 001 636A6-11-916 IGF::OT::IGF
Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2016-06-24+$37,359$9,828,104BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 014&016 636A6-11-916 IGF::OT::IGF
Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-05-12+$43,605$9,871,709BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 014&016 636A6-11-916 IGF::OT::IGF
Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-06-26+$50,429$9,922,138BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 014&016 636A6-11-916 IGF::OT::IGF
Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2017-06-26+$54,014$9,976,152BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 014&016 636A6-11-916 IGF::OT::IGF
Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-07-08+$443,746$10,419,898BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 014&016 636A6-11-916 IGF::OT::IGF
Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2018-08-24+$6,000$10,425,898BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 014&016 636A6-11-916 IGF::OT::IGF
Mod P00017· OTHER ADMINISTRATIVE ACTION2018-10-01+$0$10,425,898BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 014&016 636A6-11-916 IGF::OT::IGF
Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-06-10+$36,523$10,462,421BOILER PLANT CONSTRUCTION PROJECT, CHANGE ORDER 014&016 636A6-11-916 IGF::OT::IGF

Related awards · 7

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI P3CTJ2KMB3J8)

AwardOffice · PSC / listingNet obligationsFY
36C26326C0031NETWORK CONTRACT OFFICE 23 (36C263) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$3,071,800FY2026
36C77625C0121PCAC (36C776) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$19,181,217FY2025
36C77625C0102PCAC (36C776) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS$11,091,002FY2025
36C26324C0085NETWORK CONTRACT OFFICE 23 (36C263) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS$2,271,222FY2024
36C77624C0093PCAC (36C776) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES$10,069,728FY2024
36C77624C0117PCAC (36C776) · Y1LZ · CONSTRUCTION OF PARKING FACILITIES$2,755,965FY2024

Other recipients under Y1NB from NETWORK CONTRACT OFFICE 23 (36C263) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C26325C0059SAW GREENLAND, LLCNETWORK CONTRACT OFFICE 23 (36C263)$34,638,080FY2025

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA26313C0188_3600_-NONE-_-NONE- · retrieved 2026-09-25.