Description
CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE VA BLACK HILLS HEALTH CARE SYSTEM, HOT SPRINGS, SD.IGF::CT::IGF
Base award description: CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE VA BLACK HILLS HEALTH CARE SYSTEM, HOT SPRINGS, SD. IGF::CT::IGF
Modification chain · 12 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-03-13+$542,400= $542,400
- Mod SA12012-04-03-$49,573= $492,827
- Mod SA22012-04-03+$40,330= $533,157
- Mod P00012012-06-21+$7,466= $540,623
- Mod P000022012-09-21+$24,218= $564,841
- Mod P000032012-09-27+$1,752= $566,593
- Mod P000042012-10-05+$37,571= $604,164
- Mod P000052012-12-20+$2,166= $606,330
- Mod P000062013-02-04+$1,358= $607,689
- Mod P000072013-03-06+$92,491= $700,180
- Mod P000082013-05-17+$3,501= $703,681
- Mod P000092013-08-05+$3,210= $706,892
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-03-13 | +$542,400 | $542,400 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod SA1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-03 | −$49,573 | $492,827 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod SA2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-03 | +$40,330 | $533,157 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod P0001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-06-21 | +$7,466 | $540,623 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-21 | +$24,218 | $564,841 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-09-27 | +$1,752 | $566,593 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-10-05 | +$37,571 | $604,164 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-20 | +$2,166 | $606,330 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod P00006· FUNDING ONLY ACTION | 2013-02-04 | +$1,358 | $607,689 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod P00007· FUNDING ONLY ACTION | 2013-03-06 | +$92,491 | $700,180 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-17 | +$3,501 | $703,681 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-05 | +$3,210 | $706,892 | CONTRACTOR TO PROVIDE ALL LABOR AND MATERIALS TO COMPLETE PROJECT 568-12-201 REPLACE FLOORING PHASE 1 AT THE V… |
Related awards · 7
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI RZDNMLWD95E5)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25926C0021 | NETWORK CONTRACT OFFICE 19 (36C259) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $12,516 | FY2026 |
| 36C25926N0124 | NETWORK CONTRACT OFFICE 19 (36C259) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $297,242 | FY2026 |
| 36C25925N0375 | NETWORK CONTRACT OFFICE 19 (36C259) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $467,940 | FY2025 |
| 36C78625P50360 | NATIONAL CEMETERY ADMIN (36C786) · S208 · HOUSEKEEPING- LANDSCAPING/GROUNDSKEEPING | $32,426 | FY2025 |
| 36C25925N0397 | NETWORK CONTRACT OFFICE 19 (36C259) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $98,407 | FY2025 |
| 36C25925C0083 | NETWORK CONTRACT OFFICE 19 (36C259) · Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS | $18,153 | FY2025 |
Other recipients under Z1DZ from 568-VA BLACK HILLS HEALTH CARE SYSTEM (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA26312C0037 | JE HURLEY INC. | 568-VA BLACK HILLS HEALTH CARE SYSTEM | $583,924 | FY2012 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA26312C0089_3600_-NONE-_-NONE- · retrieved 2026-09-26.