Description
PREVENTIVE MAINTENANCE OF REVERSE OSMOSIS WATER SYSTEM
Modification chain · 6 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2007-10-01+$15,492= $15,492
- Mod 32009-03-18+$7,295= $22,787
- Mod 42009-03-18+$0= $22,787
- Mod 52009-11-13+$7,295= $30,082
- Mod 12009-11-30+$0= $30,082
- Mod 62010-10-04+$7,295= $37,376
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base· EXERCISE AN OPTION | 2007-10-01 | +$15,492 | $15,492 | PREVENTIVE MAINTENANCE OF REVERSE OSMOSIS WATER SYSTEM |
| Mod 3· EXERCISE AN OPTION | 2009-03-18 | +$7,295 | $22,787 | PREVENTATIVE MAINTENANCE REVERSE OSMOSIS WATER SYSTEM |
| Mod 4· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2009-03-18 | +$0 | $22,787 | PREVENTATIVE MAINTENANCE REVERSE OSMOSIS WATER SYSTEM |
| Mod 5· EXERCISE AN OPTION | 2009-11-13 | +$7,295 | $30,082 | PREVENTIVE MAINTENANCE OF RO SYSTERM- DIALYSIS RM4-G115 |
| Mod 1· CHANGE ORDER | 2009-11-30 | +$0 | $30,082 | PREVENTIVE MAINTENANCE OF REVERSE OSMOSIS WATER SYSTEM |
| Mod 6· EXERCISE AN OPTION | 2010-10-04 | +$7,295 | $37,376 | PREVENTIVE MAINTENANCE OF REVERSE OSMOSIS WATER SYSTEM |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ERBBBLNRSK87)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26114P3354 | 261-NETWORK CONTRACT OFFICE 21 · 4940 · MISCELLANEOUS MAINTENANCE AND REPAIR SHOP SPECIALIZED EQUIPMENT | $5,786 | FY2014 |
| VA26113C0041 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · J046 · MAINT/REPAIR/REBUILD OF EQUIPMENT- WATER PURIFICATION AND SEWAGE TREATMENT EQUIPMENT | $70,270 | FY2013 |
| VA26112P0056 | 261-NETWORK CONTRACT OFFICE 21 · F103 · ENVIRONMENTAL SYSTEMS PROTECTION- WATER QUALITY SUPPORT | $10,729 | FY2012 |
| VA459A10030 | 261-NETWORK CONTRACT OFFICE 21 · 6640 · LABORATORY EQUIPMENT AND SUPPLIES | $4,803 | FY2011 |
| V459P00349 | 459S-HONOLULU SMALL PURCHASE · 4310 · COMPRESSORS AND VACUUM PUMPS | $6,742 | FY2010 |
| VA459P00095 | 459-HONOLULU · 6520 · DENTAL INSTRUMENTS EQ & SUPPLIES | $3,385 | FY2010 |
Other recipients under J046 from 261-NETWORK CONTRACT OFFICE 21 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA26116P0059 | DAVID A. MENDEZ | 261-NETWORK CONTRACT OFFICE 21 | $7,720 | FY2016 |
| VA26115J2835 | PATRIOT CONSTRUCTION INC | 261-NETWORK CONTRACT OFFICE 21 | $0 | FY2015 |
| VA26115P1913 | HALBERT CONSTRUCTION COMPANY, INC. | 261-NETWORK CONTRACT OFFICE 21 | $12,189 | FY2015 |
| VA26112F0138 | INTERNATIONAL CHEMTEX CORP | 261-NETWORK CONTRACT OFFICE 21 | $24,988 | FY2012 |
| VA640C19314 | ALTON BUILDERS, INC. | 261-NETWORK CONTRACT OFFICE 21 | $23,100 | FY2012 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA261P0070_3600_-NONE-_-NONE- · retrieved 2026-09-26.