Description
COMPLETE LOBBY CONCRETE FLOOR REPAIRS AND FINAL POLISHING.
Base award description: CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER.
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-09-30+$7,100,000= $7,100,000
- Mod 12012-03-16+$1,072= $7,101,072
- Mod 22012-04-10+$2,323= $7,103,395
- Mod P000032012-11-28+$24,951= $7,128,346
- Mod P000042012-12-10+$4,124= $7,132,470
- Mod P000052013-03-28+$18,185= $7,150,655
- Mod P000062013-04-09+$41,053= $7,191,708
- Mod P000072013-05-17+$35,305= $7,227,014
- Mod P000092013-07-15+$0= $7,227,014
- Mod P000082013-08-07+$240,737= $7,467,751
- Mod P000102013-08-19+$28,770= $7,496,521
- Mod P000112013-08-21+$38,054= $7,534,575
- Mod P000122014-02-03+$9,068= $7,543,643
- Mod P000132014-07-15+$2,449= $7,546,092
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-09-30 | +$7,100,000 | $7,100,000 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-16 | +$1,072 | $7,101,072 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-04-10 | +$2,323 | $7,103,395 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-28 | +$24,951 | $7,128,346 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-10 | +$4,124 | $7,132,470 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-28 | +$18,185 | $7,150,655 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-09 | +$41,053 | $7,191,708 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-17 | +$35,305 | $7,227,014 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-15 | +$0 | $7,227,014 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-07 | +$240,737 | $7,467,751 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-19 | +$28,770 | $7,496,521 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-21 | +$38,054 | $7,534,575 | CONSTRUCTION OF A NEW ADMINISTRATION BUILDING AT MOUNTAIN VIEW CENTER. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-03 | +$9,068 | $7,543,643 | MODIFY CONSTRUCTION REQUIREMENTS TO FACILITATE 6 FOOT HIGH RAILING AND REMOVE AT&T SPLICE VAULT. |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-07-15 | +$2,449 | $7,546,092 | COMPLETE LOBBY CONCRETE FLOOR REPAIRS AND FINAL POLISHING. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI SCM2PEG3V1C9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26021P0264 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $191,322 | FY2021 |
| 36C26021P0263 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $154,434 | FY2021 |
| 36C26021N0139 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $1,551,890 | FY2021 |
| 36C26021N0119 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $587,926 | FY2021 |
| 36C26020N0639 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $72,058 | FY2020 |
| 36C26120N0687 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $2,000 | FY2020 |
Other recipients under Y119 from 261-NETWORK CONTRACT OFFICE 21 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA662C14439 | SALINAS AND FARIAS & ASSOCIATES | 261-NETWORK CONTRACT OFFICE 21 | $80,061 | FY2011 |
| VA261C1027 | ELLERY GROUP & RATTO CONSTRUCTION COMPANY, INC., THE | 261-NETWORK CONTRACT OFFICE 21 | $972,915 | FY2011 |
| VA640C09314 | D. E. ERHARD CONSTRUCTION INC. | 261-NETWORK CONTRACT OFFICE 21 | $147,461 | FY2010 |
| VA654C99091 | FALCON BUILDERS & DEVELOPERS INC. | 261-NETWORK CONTRACT OFFICE 21 | $29,981 | FY2009 |
| VA654C99092 | FALCON BUILDERS & DEVELOPERS INC. | 261-NETWORK CONTRACT OFFICE 21 | $196,865 | FY2009 |