Description
RENOVATE BLDG. 324 - MENLO PARK DIVISION - PROJECT NO. 640A0-10-118M - CHANGE ORDER #2 TO INCLUDE ADDITIONAL POWER OUTLETS
Base award description: RENOVATE BLDG. 324 - MENLO PARK DIVISION - PROJECT NO. 640A0-10-118M
Modification chain · 3 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-07-28+$1,399,892= $1,399,892
- Mod 12010-12-28+$44,114= $1,444,006
- Mod 22011-03-02+$29,800= $1,473,806
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-07-28 | +$1,399,892 | $1,399,892 | RENOVATE BLDG. 324 - MENLO PARK DIVISION - PROJECT NO. 640A0-10-118M |
| Mod 1· CHANGE ORDER | 2010-12-28 | +$44,114 | $1,444,006 | RENOVATE BLDG. 324 - MENLO PARK DIVISION - PROJECT NO. 640A0-10-118M - CHANGE ORDER #1 TO INCLUDE ADDITIONAL… |
| Mod 2· CHANGE ORDER | 2011-03-02 | +$29,800 | $1,473,806 | RENOVATE BLDG. 324 - MENLO PARK DIVISION - PROJECT NO. 640A0-10-118M - CHANGE ORDER #2 TO INCLUDE ADDITIONAL… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI KG67MXSQN6H3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| V654C09143 | 654-RENO · H156 · QUALITY CONT SV/CONTRUCT MATERIAL | $49,990 | FY2010 |
| VA261C0658 | 261-NETWORK CONTRACT OFFICE 21 · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $2,747,140 | FY2010 |
| VA261C0812 | 640-PALO ALTO · Y199 · CONSTRUCT/MISC BLDGS | $1,499,500 | FY2010 |
| VA261RA0716 | 261-NETWORK CONTRACT OFFICE 21 · Y199 · CONSTRUCT/MISC BLDGS | $743,309 | FY2009 |
| V662Q94914 | 261P-NETWORK CONTRACT OFFICE 21 · N056 · INSTALL OF CONTRUCT MATERIAL | $3,900 | FY2009 |
| V662C94620 | 662S-SAN FRANCISCO SMALL PURCHASE · Z299 · MAINT, REP/ALTER/ALL OTHER | $7,690 | FY2009 |
Other recipients under Y111 from 261-NETWORK CONTRACT OFFICE 21 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA654C19184 | GLEN/MAR CONSTRUCTION, INC. | 261-NETWORK CONTRACT OFFICE 21 | $2,387 | FY2011 |
| VA640C19354 | IME-ACC INC. | 261-NETWORK CONTRACT OFFICE 21 | $55,426 | FY2011 |
| VA612C19259 | HERRERA CORPORATION | 261-NETWORK CONTRACT OFFICE 21 | $7,560 | FY2011 |
| VA640Z10004 | IME-ACC INC. | 261-NETWORK CONTRACT OFFICE 21 | $437,479 | FY2011 |
| VA662C14443 | HUBZONE, CORP. | 261-NETWORK CONTRACT OFFICE 21 | $404,687 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA261C0881_3600_-NONE-_-NONE- · retrieved 2026-09-26.