Description
DEMOLITION OF BUILDING 23 AND ASSOCIATED SITE UTILITIES.
Modification chain · 8 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-07-21+$631,521= $631,521
- Mod 22010-03-03+$121,154= $752,675
- Mod SA22010-04-02+$56,286= $808,961
- Mod SA32010-07-19+$258,565= $1,067,526
- Mod SA42010-07-19+$38,215= $1,105,741
- Mod 12010-09-10+$0= $1,105,741
- Mod 32010-09-10+$0= $1,105,741
- Mod 42010-09-10+$0= $1,105,741
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-07-21 | +$631,521 | $631,521 | DEMOLITION OF BUILDING 23 AND ASSOCIATED SITE UTILITIES. |
| Mod 2· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2010-03-03 | +$121,154 | $752,675 | DEMOLITION OF BUILDING 23 AND ASSOCIATED SITE UTILITIES. |
| Mod SA2· CHANGE ORDER | 2010-04-02 | +$56,286 | $808,961 | DEMOLITION OF BUILDING 23 AND ASSOCIATED SITE UTILITIES. |
| Mod SA3· CHANGE ORDER | 2010-07-19 | +$258,565 | $1,067,526 | DEMOLITION OF BUILDING 23 AND ASSOCIATED SITE UTILITIES. |
| Mod SA4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-07-19 | +$38,215 | $1,105,741 | DEMOLITION OF BUILDING 23 AND ASSOCIATED SITE UTILITIES. |
| Mod 1· ADDITIONAL WORK (NEW AGREEMENT,FAR PART 6 APPLI | 2010-09-10 | +$0 | $1,105,741 | DEMOLITION OF BUILDING 23 AND ASSOCIATED SITE UTILITIES. |
| Mod 3· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2010-09-10 | +$0 | $1,105,741 | DEMOLITION OF BUILDING 23 AND ASSOCIATED SITE UTILITIES. |
| Mod 4· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2010-09-10 | +$0 | $1,105,741 | DEMOLITION OF BUILDING 23 AND ASSOCIATED SITE UTILITIES. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI T5HAA9MUMDU4)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26117J3257 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $196,915 | FY2017 |
| VA26217P5008 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · N071 · INSTALLATION OF EQUIPMENT- FURNITURE | $21,533 | FY2017 |
| VA101F17C2862 | OFFICE OF CONSTRUCTION & FACILITIES MGMT (36C10F) · Y1AZ · CONSTRUCTION OF OTHER ADMINISTRATIVE FACILITIES AND SERVICE BUILDINGS | $2,169,218 | FY2017 |
| VA26216C0223 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $2,154,790 | FY2016 |
| VA26216J7442 | 262-NETWORK CONTRACT OFFICE 22 (36C262) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $999,920 | FY2016 |
| VA26116J2886 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $32,459 | FY2016 |
Other recipients under Z141 from 261-NETWORK CONTRACT OFFICE 21 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA654C19169 | GLEN/MAR CONSTRUCTION, INC. | 261-NETWORK CONTRACT OFFICE 21 | $20,770 | FY2011 |
| VA261C1067 | HERRERA CORPORATION | 261-NETWORK CONTRACT OFFICE 21 | $1,592,341 | FY2011 |
| VA261C1115 | HERMAN CONSTRUCTION GROUP, INC. | 261-NETWORK CONTRACT OFFICE 21 | $482,000 | FY2011 |
| VA261C1113 | IME-ACC INC. | 261-NETWORK CONTRACT OFFICE 21 | $579,413 | FY2011 |
| VA261C0981 | HERRERA CORPORATION | 261-NETWORK CONTRACT OFFICE 21 | $59,386 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA261C0661_3600_-NONE-_-NONE- · retrieved 2026-09-26.