MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS.
Base award description: CONSTRUCTION, EMERGENCY ROOM EXPANSION AND RENOVATION, MAIN HOSPITAL CAMPUS, DEPT OF VETERANS AFFAIRS, CENTRAL CALIFORNIA HEALTH CARE SYSTEM, FRESNO, CA
Modification chain · 15 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-09-24+$4,310,872= $4,310,872
- Mod 12009-01-20+$0= $4,310,872
- Mod 22009-04-28+$7,185= $4,318,057
- Mod 32009-05-01+$9,439= $4,327,496
- Mod 42009-05-22+$4,667= $4,332,163
- Mod 52009-06-09+$2,089= $4,334,252
- Mod 62009-06-15+$5,427= $4,339,679
- Mod 72009-08-05+$48,833= $4,388,512
- Mod 92009-10-04+$128,953= $4,517,465
- Mod 82009-11-09+$83,858= $4,601,323
- Mod 102010-01-08+$6,079= $4,607,402
- Mod 112010-01-08+$69,270= $4,676,672
- Mod 122010-01-13+$29,850= $4,706,522
- Mod 132010-03-14+$14,866= $4,721,388
- Mod 142010-05-21+$11,634= $4,733,022
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2008-09-24 | +$4,310,872 | $4,310,872 | CONSTRUCTION, EMERGENCY ROOM EXPANSION AND RENOVATION, MAIN HOSPITAL CAMPUS, DEPT OF VETERANS AFFAIRS, CENTRAL… |
| Mod 1· OTHER ADMINISTRATIVE ACTION | 2009-01-20 | +$0 | $4,310,872 | — |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-04-28 | +$7,185 | $4,318,057 | MODIFICATION TO RELOCATE FIRE SPRINKLER. |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-05-01 | +$9,439 | $4,327,496 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-05-22 | +$4,667 | $4,332,163 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
| Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-06-09 | +$2,089 | $4,334,252 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
| Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-06-15 | +$5,427 | $4,339,679 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-08-05 | +$48,833 | $4,388,512 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-10-04 | +$128,953 | $4,517,465 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-09 | +$83,858 | $4,601,323 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-08 | +$6,079 | $4,607,402 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
| Mod 11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-08 | +$69,270 | $4,676,672 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
| Mod 12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-13 | +$29,850 | $4,706,522 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. REMODEL OF EMERGENCY ROOM. |
| Mod 13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-03-14 | +$14,866 | $4,721,388 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. EMERGENCY ROOM REMODEL. |
| Mod 14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-05-21 | +$11,634 | $4,733,022 | MODIFICATION DUE TO UNFORSEEN SITE CONDITIONS. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI NLLKV94M2BP3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA673C00487 | 673-TAMPA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $19,873 | FY2010 |
| VA673C00187 | 673-TAMPA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $19,873 | FY2010 |
| VA101CFMC0137 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $0 | FY2009 |
| VA248C0629 | 673-TAMPA · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $865,000 | FY2009 |
| VA0002 | 261-NETWORK CONTRACT OFFICE 21 · Y249 · CONSTRUCTION OF OTHER UTILITIES | $397,410 | FY2009 |
| VA0001 | 261-NETWORK CONTRACT OFFICE 21 · Z299 · MAINT, REP/ALTER/ALL OTHER | $430,716 | FY2008 |
Other recipients under Z149 from 261-NETWORK CONTRACT OFFICE 21 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA570C19206 | SALINAS AND FARIAS & ASSOCIATES | 261-NETWORK CONTRACT OFFICE 21 | $238,689 | FY2011 |
| VA570C19207 | SALINAS AND FARIAS & ASSOCIATES | 261-NETWORK CONTRACT OFFICE 21 | $500,852 | FY2011 |
| VA261C1059 | VANDAHL ENGINEERING & SALES LTD | 261-NETWORK CONTRACT OFFICE 21 | $331,371 | FY2011 |
| VA261C1101 | ELLERY GROUP & RATTO CONSTRUCTION COMPANY, INC., THE | 261-NETWORK CONTRACT OFFICE 21 | $1,051,304 | FY2011 |
| VA612C19263 | FALCON BUILDERS & DEVELOPERS INC. | 261-NETWORK CONTRACT OFFICE 21 | $103,621 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA261C0480_3600_-NONE-_-NONE- · retrieved 2026-09-26.