Description
PROVIDE FOR HVAC AND ELECTRICAL NEEDS FOR PHARMACY AND ADDITIONAL TESTING FOR USP 797 COMPLIANCE.
Base award description: IGF::OT::IGF PROVIDE FOR CONSTRUCTION FOR NEW PHARMACY AND EXPAND PTSD AT VA MENLO PARK.
Modification chain · 22 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2016-08-31+$6,625,000= $6,625,000
- Mod P000012017-01-14+$0= $6,625,000
- Mod P000022017-04-01+$51,180= $6,676,180
- Mod P000032017-04-21+$233,823= $6,910,003
- Mod P000052017-05-18+$4,197= $6,914,200
- Mod P000062017-06-05+$9,147= $6,923,348
- Mod P000072017-06-14+$11,808= $6,935,156
- Mod P000082017-07-13+$52,254= $6,987,410
- Mod P000092017-08-03+$2,762= $6,990,172
- Mod P000102017-08-04+$149,454= $7,139,627
- Mod P000112017-08-25+$45,474= $7,185,101
- Mod P000122017-10-25+$268,432= $7,453,532
- Mod P000132018-01-04+$76,175= $7,529,708
- Mod P000142018-03-08+$736,452= $8,266,159
- Mod P000152018-06-22+$138,000= $8,404,159
- Mod P000162018-09-25+$10,192= $8,414,351
- Mod P000172018-11-09+$26,758= $8,441,109
- Mod P000182019-01-15+$91,603= $8,532,712
- Mod P000192019-02-27+$29,790= $8,562,502
- Mod P000202019-03-26+$78,065= $8,640,567
- Mod P000212019-05-22+$77,740= $8,718,307
- Mod P000222019-11-07+$82,906= $8,801,213
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2016-08-31 | +$6,625,000 | $6,625,000 | IGF::OT::IGF PROVIDE FOR CONSTRUCTION FOR NEW PHARMACY AND EXPAND PTSD AT VA MENLO PARK. |
| Mod P00001· OTHER ADMINISTRATIVE ACTION | 2017-01-14 | +$0 | $6,625,000 | IGF::OT::IGF PROVIDE FOR INCORPORATION OF UPDATED SPECIFICATIONS AND DRAWINGS. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-04-01 | +$51,180 | $6,676,180 | IGF::OT::IGF PROVIDE FOR ADDED UNDERGROUND UTILITIES. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-04-21 | +$233,823 | $6,910,003 | IGF::OT::IGF PROVIDE FOR ADDED INFECTION CONTROL REQUIREMENTS DURING DEMOLITION AND CONSTRUCTION OF THIS PROJE… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-05-18 | +$4,197 | $6,914,200 | IGF::OT::IGF PROVIDE FOR ASBESTOS PIPE REMOVAL AND CHANGED THICKNESS OF CONCRETE SLAB. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-06-05 | +$9,147 | $6,923,348 | IGF::OT::IGF PROVIDE FOR SAW CUTTING OF EXISTING BUILDING 360 FOUNDATION CONCRETE OVERPOUR. |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-06-14 | +$11,808 | $6,935,156 | IGF::OT::IGF PROVIDE FOR COMPLETE FIRE SUPPRESSION SURVEY OF BUILDING 334 AND CAP LINES AT CONSTRUCTION ZONE. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-07-13 | +$52,254 | $6,987,410 | IGF::OT::IGF PROVIDE FOR COMPLETE REPLACEMENT OF HYRDONIC PIPING FOR 2ND FLOOR OF BUILDING 334 CONSTRUCTION ZO… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-08-03 | +$2,762 | $6,990,172 | IGF::OT::IGF PROVIDE FOR SMOKE BARRIER TO MEET NFPA REQUIREMENTS. |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-08-04 | +$149,454 | $7,139,627 | IGF::OT::IGF PROVIDE FOR HVAC BOILER AND ASSOCIATED COMPONENTS AND CHANGED LANDSCPAING AND IRRIGATION REQUIREM… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-08-25 | +$45,474 | $7,185,101 | IGF::OT::IGF PROVIDE FOR LEED SILVER CERTIFICATION OF BUILDING 360-J, NEW PHARMACY AT VA MENLO PARK CAMPUS. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-10-25 | +$268,432 | $7,453,532 | IGF::OT::IGF PROVIDE FOR INCORPORATION OF BULLETIN #2 CONSTRUCTION CHANGES AS ISSUED BY ARCHITECH&ENGINEER FIR… |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-01-04 | +$76,175 | $7,529,708 | IGF::OT::IGF PROVIDE FOR INCORPORATION OF BULLETIN #4, AE ISSUED CHANGES FOR PTSD WALLS, PIPING, PLUMBING, AND… |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-03-08 | +$736,452 | $8,266,159 | IGF::OT::IGF PROVIDE FOR MANUFACTURE AND DELIVERY OF 808 LINEAR FEET OF CUSTOM DESIGNED DEMOUNTABLE PARTITIONS… |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-06-22 | +$138,000 | $8,404,159 | IGF::OT::IGF PROVIDE FOR ENHANCED SECURITY AND ELECTRICAL UPGRADES FOR NEW PHARMACY AND ADDS CARD READERS, DIS… |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-09-25 | +$10,192 | $8,414,351 | IGF::OT::IGF PROVIDE FOR ELECTRIC STRIKES, CHILLER INSULATION AND LIGHT RELOCATION. |
| Mod P00017· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-11-09 | +$26,758 | $8,441,109 | IGF::OT::IGF PROVIDE FOR VA DIRECTED CHANGES RELATED TO NEW PHARMACY STANDARDS AND CHANGES TO PTSD RENOVATION. |
| Mod P00018· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-01-15 | +$91,603 | $8,532,712 | IGF::OT::IGF PROVIDE FOR EXTENDED GENERAL CONDITIONS, ADD OIT REQUIREMENT FOR PTSD, CHANGE NEW PHARMACY DOOR O… |
| Mod P00019· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-02-27 | +$29,790 | $8,562,502 | IGF::OT::IGF PROVIDE FOR EXTENDED GENERAL CONDITIONS. |
| Mod P00020· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-03-26 | +$78,065 | $8,640,567 | IGF::OT::IGF PROVIDE FOR EXTENDED GENERAL CONDITIONS AND CORRECT UNFORSEEN CONDITIONS IN TRAINING CENTER RENOV… |
| Mod P00021· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-05-22 | +$77,740 | $8,718,307 | IGF::OT::IGF PROVIDE FOR HVAC AND ELECTRICAL NEEDS FOR PHARMACY AND ADDITIONAL TESTING FOR USP 797 COMPLIANCE. |
| Mod P00022· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-11-07 | +$82,906 | $8,801,213 | PROVIDE FOR HVAC AND ELECTRICAL NEEDS FOR PHARMACY AND ADDITIONAL TESTING FOR USP 797 COMPLIANCE. |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Y1DZ from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26126N0163 | SERGENTS MECHANICAL SYSTEMS INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $1,507,236 | FY2026 |
| 36C26125N0684 | PATRIOT CONSTRUCTION INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $39,600 | FY2025 |
| 36C26125N0417 | HAWK CONTRACTING GROUP LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $36,023 | FY2025 |
| 36C26124N0657 | D SQUARE CONSTRUCTION LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $359,342 | FY2024 |
| 36C26124N0343 | STRATEGIC INDUSTRY INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $497,845 | FY2024 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA26116C0047_3600_-NONE-_-NONE- · retrieved 2026-09-26.