MOD P00015 POP TIME EXTENSION ADDITIONAL CONSTRUCTION PERIOD SERVICES
Base award description: IGF::OT::IGF PROVIDE A/E DESIGN SERVICES FOR EMERGENCY POWER UPGRADE FOR BUILDING 100 AND 101 AT VA PALO ALTO.
Modification chain · 15 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2015-09-17+$715,346= $715,346
- Mod P000012016-01-05+$68,207= $783,553
- Mod P000022017-04-18+$292,182= $1,075,735
- Mod P000032018-03-13+$59,813= $1,135,548
- Mod P000042019-04-17+$72,473= $1,208,021
- Mod P000052020-03-17+$33,228= $1,241,249
- Mod P000062020-09-22+$59,760= $1,301,009
- Mod P000072021-03-26+$57,901= $1,358,910
- Mod P000092021-09-29-$0= $1,358,910
- Mod P000102022-03-16+$244,335= $1,603,245
- Mod P000112024-08-07+$26,300= $1,629,545
- Mod P000122025-03-25+$25,000= $1,654,545
- Mod P000132026-02-06+$28,433= $1,682,978
- Mod P000142026-06-10+$30,670= $1,713,648
- Mod P000152026-07-22+$0= $1,713,648
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2015-09-17 | +$715,346 | $715,346 | IGF::OT::IGF PROVIDE A/E DESIGN SERVICES FOR EMERGENCY POWER UPGRADE FOR BUILDING 100 AND 101 AT VA PALO ALTO. |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2016-01-05 | +$68,207 | $783,553 | IGF::OT::IGF ADD SERVICES FOR ANALYSIS OF ALTERNATIVES FOR AUGMENTING BUILDING 103 EMERGENCY POWER GENERATOR S… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-04-18 | +$292,182 | $1,075,735 | IGF::OT::IGF ADD SERVICES FOR ADDITIONAL DESIGN WORK AT THE 65% DESIGN REVIEW. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-03-13 | +$59,813 | $1,135,548 | IGF::OT::IGF ADD SERVICES FOR ENVIRONMENTAL ASSESSMENT. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2019-04-17 | +$72,473 | $1,208,021 | IGF::OT::IGF ADD SERVICES FOR EXTENDED CONSTRUCTION PERIOD SERVICES AND SITE VISITS. |
| Mod P00005· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2020-03-17 | +$33,228 | $1,241,249 | ADD SERVICES FOR CONCEPTUAL REDESIGN. |
| Mod P00006· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2020-09-22 | +$59,760 | $1,301,009 | ADD CONSTRUCTION PERIOD SERVICES DUE TO DELAYS. |
| Mod P00007· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2021-03-26 | +$57,901 | $1,358,910 | MOD P00007 TO ADD ROAD DESIGN WORK. |
| Mod P00009· FUNDING ONLY ACTION | 2021-09-29 | −$0 | $1,358,910 | MOD P00007 TO ADD ROAD DESIGN WORK. |
| Mod P00010· ADDITIONAL WORK (NEW AGREEMENT, JUSTIFICATION REQUIRED) | 2022-03-16 | +$244,335 | $1,603,245 | MOD P00007 TO ADD ROAD DESIGN WORK. |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-08-07 | +$26,300 | $1,629,545 | MOD P00011 POP TIME EXTENSION ADD SITE VISITS |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-03-25 | +$25,000 | $1,654,545 | MOD P00011 POP TIME EXTENSION ADD SITE VISITS |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-02-06 | +$28,433 | $1,682,978 | MOD P00013 POP TIME EXTENSION ADDITIONAL CONSTRUCTION PERIOD SERVICES |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-06-10 | +$30,670 | $1,713,648 | MOD P00014 POP TIME EXTENSION ADDITIONAL CONSTRUCTION PERIOD SERVICES |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2026-07-22 | +$0 | $1,713,648 | MOD P00015 POP TIME EXTENSION ADDITIONAL CONSTRUCTION PERIOD SERVICES |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI MD35Q8AARJ54)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26116J2708 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · C1LB · ARCHITECT AND ENGINEERING- CONSTRUCTION: HIGHWAYS, ROADS, STREETS, BRIDGES, AND RAILWAYS | $10,095 | FY2016 |
| VA26116J1522 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $128,767 | FY2016 |
| VA26116J0895 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · C1DB · ARCHITECT AND ENGINEERING- CONSTRUCTION: LABORATORIES AND CLINICS | $741,519 | FY2016 |
| VA26116J0133 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · C1DA · ARCHITECT AND ENGINEERING- CONSTRUCTION: HOSPITALS AND INFIRMARIES | $434,545 | FY2016 |
| VA26115J2508 | 261-NETWORK CONTRACT OFFICE 21 · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $854,040 | FY2015 |
| VA26115D0049 | 261-NETWORK CONTRACT OFFICE 21 · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $0 | FY2015 |
Other recipients under C1DA from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26126N0649 | GDM-AE, INC. | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $4,451,252 | FY2026 |
| 36C26126N0595 | GDM-AE, INC. | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $198,807 | FY2026 |
| 36C26126N0575 | TRIPLE C-THE A & E GROUP LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $394,340 | FY2026 |
| 36C26126N0603 | AWEN SOLUTIONS GROUP, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $630,025 | FY2026 |
| 36C26126N0551 | APOGEE CONSULTING GROUP, P.A. | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $209,175 | FY2026 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA26115J2807_3600_VA26115D0310_3600 · retrieved 2026-09-26.