Description
IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT COMPLETION DATE BY FORTY TWO (42) CALENDAR DAYS AT NO ADDITIONAL COST TO THE GOVERNMENT. THE VA REVIEW COMMENTS HAVE BEEN PROVIDED TO THE CONTRACTOR. THE ADDITIONAL TIME WILL ALLOW THE CONTRACTOR AND VA TO FINALIZE THE DEFICIENCY REPORT AND FINAL REPORT PER VA STANDARDS. THE CONTRACT END DATE IS HEREBY MODIFIED FROM 11/11/2015 TO 12/23/2015.
Base award description: IGF::OT::IGF AE MASTER PLANNING TASK ORDER FOR MASTER PLANNING FOR FACILITY EXTRIOR AT VAMC FRESNO
Modification chain · 10 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2014-06-30+$201,289= $201,289
- Mod P000012014-09-30+$0= $201,289
- Mod P000022014-11-28+$0= $201,289
- Mod P000032015-01-22+$0= $201,289
- Mod P000042015-03-24+$0= $201,289
- Mod P000052015-05-15+$0= $201,289
- Mod P000062015-07-13+$0= $201,289
- Mod P000072015-08-25+$0= $201,289
- Mod P000082015-09-29+$0= $201,289
- Mod P000092015-11-10+$0= $201,289
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2014-06-30 | +$201,289 | $201,289 | IGF::OT::IGF AE MASTER PLANNING TASK ORDER FOR MASTER PLANNING FOR FACILITY EXTRIOR AT VAMC FRESNO |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-09-30 | +$0 | $201,289 | IGF::OT::IGF AE MASTER PLANNING TASK ORDER FOR MASTER PLANNING FOR FACILITY EXTRIOR AT VAMC FRESNO |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-11-28 | +$0 | $201,289 | IGF::OT::IGF MODIFICATION TO EXTEND CONTRACT POP BY 59 CALENDAR DAYS FROM 11/28/2014 TO 1/26/2015 AT NO COST T… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-01-22 | +$0 | $201,289 | IGF::OT::IGF MODIFICATION TO EXTEND CONTRACT POP BY 59 CALENDAR DAYS FROM 1/26/2015 TO MARCH 26, 2015 AT NO CO… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-24 | +$0 | $201,289 | IGF::OT::IGF MODIFICATION TO EXTEND CONTRACT POP BY 50 CALENDAR DAYS FROM 3/26/2015 TO 5/15/2015 AT NO COST TO… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-05-15 | +$0 | $201,289 | IGF::OT::IGF MODIFICATION TO EXTEND CONTRACT POP BY 59 CALENDAR DAYS FROM 5/15/2015 TO 7/13/2015 AT NO COST TO… |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-07-13 | +$0 | $201,289 | IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT PERIOD OF PERFORMANCE BY FORTY THREE (… |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-08-25 | +$0 | $201,289 | IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT PERIOD OF PERFORMANCE BY THIRTY SIX (3… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-29 | +$0 | $201,289 | IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT PERIOD OF PERFORMANCE BY FORTY TWO (42… |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-11-10 | +$0 | $201,289 | IGF::OT::IGF THE PURPOSE OF THIS MODIFICATION IS TO EXTEND THE CONTRACT COMPLETION DATE BY FORTY TWO (42) CALE… |
Related awards · 8
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI XJWBMEXTFPU1)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26116J0001 | 261-NETWORK CONTRACT OFFICE 21 · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $64,943 | FY2016 |
| VA26114J2208 | 261-NETWORK CONTRACT OFFICE 21 · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $45,842 | FY2014 |
| VA26113D0450 | 261-NETWORK CONTRACT OFFICE 21 · C211 · ARCHITECT AND ENGINEERING- GENERAL: LANDSCAPING, INTERIOR LAYOUT, AND DESIGNING | $0 | FY2014 |
Other recipients under C211 from 261-NETWORK CONTRACT OFFICE 21 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA26116J1321 | ROMANYK CONSULTING CORPORATION | 261-NETWORK CONTRACT OFFICE 21 | $44,704 | FY2016 |
| VA26116J0472 | MEI ARCHITECTS | 261-NETWORK CONTRACT OFFICE 21 | $11,717 | FY2016 |
| VA26116J0570 | JOSEPH CHOW & ASSOCIATES, INC | 261-NETWORK CONTRACT OFFICE 21 | $56,469 | FY2016 |
| VA26115J2508 | ADVANCE DESIGN CONSULTANTS, INC. | 261-NETWORK CONTRACT OFFICE 21 | $854,040 | FY2015 |
| VA26115J2760 | JOSEPH CHOW & ASSOCIATES, INC | 261-NETWORK CONTRACT OFFICE 21 | $100,811 | FY2015 |