Description
MODIFICATION TO DESCOPE AND SUPPORT CONTRACT CLOSE OUT.
Base award description: IGF::OT::IGF THE PURCHASE OF AN AE IDIQ TO PREPARE A SCHEMATIC EVALUATION, DESIGN DEVELOPMENT DRAWINGS, CONSTRUCTION DOCUMENTS, SPECIFICATIONS, AND A COST ESTIMATE TO REMODEL AND EXPAND THE COMMUNITY LIVING CENTER IN FRESNO, CA.
Modification chain · 12 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-09-24+$971,987= $971,987
- Mod P000012013-05-09+$0= $971,987
- Mod P000022013-08-30+$0= $971,987
- Mod P000032013-11-08+$15,088= $987,075
- Mod P000042014-02-12+$0= $987,075
- Mod P000052014-04-21+$0= $987,075
- Mod P000062014-05-12+$0= $987,075
- Mod P000072015-09-04+$5,306= $992,381
- Mod P000082015-09-04+$46,120= $1,038,501
- Mod P000092015-09-22+$13,700= $1,052,201
- Mod P000112025-02-26-$3,364= $1,048,837
- Mod P000122025-08-04+$15,385= $1,064,222
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-09-24 | +$971,987 | $971,987 | IGF::OT::IGF THE PURCHASE OF AN AE IDIQ TO PREPARE A SCHEMATIC EVALUATION, DESIGN DEVELOPMENT DRAWINGS, CONST… |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-05-09 | +$0 | $971,987 | IGF::OT::IGF MODIFICATION FOR NO COST TIME EXTENSION TO THE DESIGN CONTRACT. |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-30 | +$0 | $971,987 | IGF::OT::IGF MODIFICATION FOR NO COST TIME EXTENSION TO THE DESIGN CONTRACT. |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-08 | +$15,088 | $987,075 | IGF::OT::IGF MODIFICATION FOR INCREASE TO THE SIZE OF THE PATIENT ROOMS AND LIVING SPACE. |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-02-12 | +$0 | $987,075 | IGF::OT::IGF MODIFICATION FOR ADDITIONAL TIME REQUIRED DUE TO PROGRAMMING QUESTIONS. |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-04-21 | +$0 | $987,075 | IGF::OT::IGF MODIFICATION FOR ADDITIONAL TIME DUE TO SUSPENSION OF WORK. |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-05-12 | +$0 | $987,075 | IGF::OT::IGF MODIFICATION FOR ADDITIONAL TIME DUE TO PROGRAMMING DECISIONS. |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-04 | +$5,306 | $992,381 | IGF::OT::IGF MODIFICATION FOR CHANGE TO POINT OF CONNECTION FOR DOMESTIC WATER LINE. |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-04 | +$46,120 | $1,038,501 | IGF::OT::IGF MODIFICATION FOR ADDITIONAL DESIGN - LANDSCAPING AND SECURITY ALONG ANGUS AVENUE. |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-09-22 | +$13,700 | $1,052,201 | MODIFICATION TO COMPLETE TRANSFER OF PROPERTY FROM CITY OF FRESNO BACK TO VA CENTRAL CALIFORNIA HEALTH CARE SY… |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-02-26 | −$3,364 | $1,048,837 | MODIFICATION TO DESCOPE AND SUPPORT CONTRACT CLOSE OUT. |
| Mod P00012· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2025-08-04 | +$15,385 | $1,064,222 | MODIFICATION TO DESCOPE AND SUPPORT CONTRACT CLOSE OUT. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI HUFCAXQBHLQ8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26116J3174 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $2,500 | FY2016 |
| VA26115D0057 | 261-NETWORK CONTRACT OFFICE 21 · C214 · ARCHITECT AND ENGINEERING- GENERAL: MANAGEMENT ENGINEERING | $0 | FY2015 |
| VA26115J0962 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · C219 · ARCHITECT AND ENGINEERING- GENERAL: OTHER | $708,461 | FY2015 |
| VA26114J2679 | 261-NETWORK CONTRACT OFFICE 21 · C1NZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER UTILITIES | $996,591 | FY2014 |
| VA26114J2380 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · C1EB · ARCHITECT AND ENGINEERING- CONSTRUCTION: MAINTENANCE BUILDINGS | $443,139 | FY2014 |
| VA26114J1982 | 261-NETWORK CONTRACT OFFICE 21 · C1DZ · ARCHITECT AND ENGINEERING- CONSTRUCTION: OTHER HOSPITAL BUILDINGS | $964,323 | FY2014 |
Other recipients under C219 from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26120N0779 | APOGEE CONSULTING GROUP, P.A. | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $169,439 | FY2020 |
| 36C26120N0132 | AESUS DESIGN GROUP LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $228,328 | FY2020 |
| VA26117P0723 | ZANE AND ASSOCIATES, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $219,947 | FY2017 |
| VA26116P1935 | ZANE AND ASSOCIATES, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $187,513 | FY2016 |
| VA26115C0071 | ZANE AND ASSOCIATES, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $353,571 | FY2015 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA26112J2420_3600_VA26112D0078_3600 · retrieved 2026-09-26.