Description
IGF::OT::IGF REQUEST FOR EQUITABLE ADJUSTMENT SETTLEMENT.
Base award description: COMPLETE GUT AND RENOVATION OF BUILDING 1A: SEISMIC CORRECTIONS
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-09-26+$6,332,500= $6,332,500
- Mod P000012013-03-20+$18,469= $6,350,969
- Mod P000022013-04-12+$17,886= $6,368,855
- Mod P000032013-07-29+$65,874= $6,434,729
- Mod P000042013-09-04+$49,524= $6,484,253
- Mod P000052013-10-21+$66,915= $6,551,168
- Mod P000062013-11-01+$74,048= $6,625,216
- Mod P000072013-11-01+$21,551= $6,646,767
- Mod P000082014-01-14+$25,423= $6,672,190
- Mod P000092014-02-20+$35,514= $6,707,704
- Mod P000102014-02-26+$80,734= $6,788,438
- Mod P000112014-06-18+$16,814= $6,805,252
- Mod P000122015-01-08+$18,772= $6,824,024
- Mod P000132016-08-11+$145,410= $6,969,434
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-09-26 | +$6,332,500 | $6,332,500 | COMPLETE GUT AND RENOVATION OF BUILDING 1A: SEISMIC CORRECTIONS |
| Mod P00001· CHANGE ORDER | 2013-03-20 | +$18,469 | $6,350,969 | IGF::OT::IGF CHANGE ORDER FOR ASBESTOS ABATEMENT AND FIRE-PROOFING IN OLD MECHANICAL AND ELECTRICAL SPACE |
| Mod P00002· CHANGE ORDER | 2013-04-12 | +$17,886 | $6,368,855 | IGF::OT::IGF CHANG ORDER FOR ASBESTOS PIPE INSULATION ABATEMENT ON 1ST FLOOR OF BUILDING 1A; PROVIDE ADDITIONA… |
| Mod P00003· CHANGE ORDER | 2013-07-29 | +$65,874 | $6,434,729 | IGF::OT::IGF SEISMIC 1A CONSTRUCTION |
| Mod P00004· CHANGE ORDER | 2013-09-04 | +$49,524 | $6,484,253 | IGF::OT::IGF SEISMIC 1A CONSTRUCTION |
| Mod P00005· CHANGE ORDER | 2013-10-21 | +$66,915 | $6,551,168 | IGF::OT::IGF BLDG 1A SEISMIC |
| Mod P00006· CHANGE ORDER | 2013-11-01 | +$74,048 | $6,625,216 | IGF::OT::IGF BLDG. 1A SEISMIC |
| Mod P00007· CHANGE ORDER | 2013-11-01 | +$21,551 | $6,646,767 | IGF::OT::IGF BLDG. A SEISMIC |
| Mod P00008· CHANGE ORDER | 2014-01-14 | +$25,423 | $6,672,190 | IGF::OT::IGF BLDG. 1A |
| Mod P00009· CHANGE ORDER | 2014-02-20 | +$35,514 | $6,707,704 | IGF::OT::IGF BLDG. 1A |
| Mod P00010· CHANGE ORDER | 2014-02-26 | +$80,734 | $6,788,438 | IGF::OT::IGF BLDG. 1A SEISMIC |
| Mod P00011· CHANGE ORDER | 2014-06-18 | +$16,814 | $6,805,252 | IGF::OT::IGF BLDG. 1A SEISMIC |
| Mod P00012· CHANGE ORDER | 2015-01-08 | +$18,772 | $6,824,024 | IGF::OT::IGF BLDG. 1A SEISMIC |
| Mod P00013· CLOSE OUT | 2016-08-11 | +$145,410 | $6,969,434 | IGF::OT::IGF REQUEST FOR EQUITABLE ADJUSTMENT SETTLEMENT. |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI SCM2PEG3V1C9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26021P0264 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $191,322 | FY2021 |
| 36C26021P0263 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $154,434 | FY2021 |
| 36C26021N0139 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $1,551,890 | FY2021 |
| 36C26021N0119 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $587,926 | FY2021 |
| 36C26020N0639 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $72,058 | FY2020 |
| 36C26120N0687 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $2,000 | FY2020 |
Other recipients under Z1DA from 261-NETWORK CONTRACT OFFICE 21 (36C261) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26126C0064 | AMOROSO OVERWATCH LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $8,897,000 | FY2026 |
| 36C26126P1121 | SACRAMENTO COMPUTER POWER, INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $217,673 | FY2026 |
| 36C26126C0067 | V. LOPEZ JR. & SONS GENERAL ENGINEERING CONTRACTORS, INC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $2,404,795 | FY2026 |
| 36C26126C0066 | BEXAR-ADVANCED SOLUTIONS GROUP, LLC | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $3,214,131 | FY2026 |
| 36C26126C0063 | MOONLITE CONSTRUCTION | 261-NETWORK CONTRACT OFFICE 21 (36C261) | $113,041 | FY2026 |