IGF::OT::IGF NO COST TIME EXTENSION MODIFICATION
Base award description: IGF::OT::IGF CANTEEN RENOVATION RELOCATION: BID BUILD CONSTRUCTION PROJECT
Modification chain · 14 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-07-02+$3,395,000= $3,395,000
- Mod P000012012-08-23+$17,653= $3,412,653
- Mod P000022012-09-14+$58,285= $3,470,938
- Mod P000032012-11-14+$76,430= $3,547,368
- Mod P000042012-11-26+$64,407= $3,611,775
- Mod P000052012-12-03+$95,201= $3,706,976
- Mod P000062013-01-14+$80,418= $3,787,394
- Mod P000072013-01-28+$42,288= $3,829,682
- Mod P000082013-03-21+$93,629= $3,923,311
- Mod P000092013-04-12+$96,331= $4,019,642
- Mod P000102013-05-14+$50,841= $4,070,483
- Mod P000112013-06-27+$6,039= $4,076,522
- Mod P000122013-07-19+$0= $4,076,522
- Mod P000132013-11-18+$0= $4,076,522
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-07-02 | +$3,395,000 | $3,395,000 | IGF::OT::IGF CANTEEN RENOVATION RELOCATION: BID BUILD CONSTRUCTION PROJECT |
| Mod P00001· CHANGE ORDER | 2012-08-23 | +$17,653 | $3,412,653 | IGF::OT::IGF CANTEEN RENOVATION RELOCATION: CHANGE ORDER #1: |
| Mod P00002· CHANGE ORDER | 2012-09-14 | +$58,285 | $3,470,938 | IGF::OT::IGF CANTEEN RENOVATION RELOCATION: CHANGE ORDERS 2, 3&4 |
| Mod P00003· CHANGE ORDER | 2012-11-14 | +$76,430 | $3,547,368 | IGF::OT::IGF CANTEEN RENOVATION RELOCATION: MODIFICATION P00003 |
| Mod P00004· CHANGE ORDER | 2012-11-26 | +$64,407 | $3,611,775 | IGF::OT::IGF CANTEEN RENOVATION RELOCATION: FURRING MODIFICATION |
| Mod P00005· CHANGE ORDER | 2012-12-03 | +$95,201 | $3,706,976 | IGF::OT::IGF CHANGES AS A RESULT OF DESIGN ERRORS OR OMISSIONS. ROUTING OF PIPES AND CONDUITS. |
| Mod P00006· CHANGE ORDER | 2013-01-14 | +$80,418 | $3,787,394 | IGF::OT::IGF CHANGES RESULTING FROM DESIGN ERRORS AND OMISSIONS. CAT 6&MAU ELECTRICAL. |
| Mod P00007· CHANGE ORDER | 2013-01-28 | +$42,288 | $3,829,682 | IGF::OT::IGF CHANGES RESULTING FROM DESIGN ERRORS AND OMISSIONS. CHANGE FROM EMERGENCY POWER TO NORMAL POWER |
| Mod P00008· CHANGE ORDER | 2013-03-21 | +$93,629 | $3,923,311 | IGF::OT::IGF CHANGES RESULTING FROM DESIGN ERRORS AND OMISSIONS. EXTRA PIPE FOR HOT WATER HEATER, RELOCATE DIS… |
| Mod P00009· CHANGE ORDER | 2013-04-12 | +$96,331 | $4,019,642 | IGF::OT::IGF CHANGES RESULTING FROM DESIGN ERRORS AND OMISSIONS. RELOCATE GREASE INTERCEPTOR, REPLACE HC UNIT… |
| Mod P00010· CHANGE ORDER | 2013-05-14 | +$50,841 | $4,070,483 | IGF::OT::IGF CHANGES RESULTING FROM DESIGN ERRORS AND OMISSIONS. REMAINING GREASE EXHAUST AND BATTERY EXHAUST |
| Mod P00011· CHANGE ORDER | 2013-06-27 | +$6,039 | $4,076,522 | IGF::OT::IGF CHANGES RESULTING FROM ELECTRICAL DESIGN ERRORS AND OMISSIONS |
| Mod P00012· CHANGE ORDER | 2013-07-19 | +$0 | $4,076,522 | IGF::OT::IGF NO COST TIME EXTENSION MODIFICATION |
| Mod P00013· CHANGE ORDER | 2013-11-18 | +$0 | $4,076,522 | IGF::OT::IGF NO COST TIME EXTENSION MODIFICATION |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI YQKLNFR9N289)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26117J3073 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $5,000 | FY2017 |
| VA26014J0501 | 260-NETWORK CONTRACT OFFICE 20 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $10,000 | FY2014 |
| VA26014J0500 | 260-NETWORK CONTRACT OFFICE 20 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $10,000 | FY2014 |
| VA26014J0499 | 260-NETWORK CONTRACT OFFICE 20 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $10,000 | FY2014 |
| VA101F13C0069 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $4,487,309 | FY2013 |
| VA26013J1579 | 260-NETWORK CONTRACT OFFICE 20 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $1,189,723 | FY2013 |
Other recipients under Z1DZ from 261-NETWORK CONTRACT OFFICE 21 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA26115J3148 | PATRIOT CONSTRUCTION INC | 261-NETWORK CONTRACT OFFICE 21 | $23,243 | FY2015 |
| VA26115J1849 | HAWK CONTRACTING GROUP LLC | 261-NETWORK CONTRACT OFFICE 21 | $60,753 | FY2015 |
| VA26115J1651 | TALION CONSTRUCTION, LLC | 261-NETWORK CONTRACT OFFICE 21 | $41,890 | FY2015 |
| VA26115J0932 | K.O.O. CONSTRUCTION, INC. | 261-NETWORK CONTRACT OFFICE 21 | $677,430 | FY2015 |
| VA26114J3185 | PATRIOT CONSTRUCTION INC | 261-NETWORK CONTRACT OFFICE 21 | $204,660 | FY2014 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA26112C0151_3600_-NONE-_-NONE- · retrieved 2026-09-26.