Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-11-24+$6,664,000= $6,664,000
- Mod 12011-04-19+$0= $6,664,000
- Mod 32011-05-09+$14,098= $6,678,098
- Mod 22011-06-13+$39,697= $6,717,795
- Mod 42011-09-23+$12,483= $6,730,278
- Mod P000052011-11-08+$56,008= $6,786,286
- Mod P000072011-12-14+$0= $6,786,286
- Mod P000062012-01-10+$217,629= $7,003,915
- Mod P000082012-03-23+$25,008= $7,028,923
- Mod P000092012-07-09+$22,869= $7,051,792
- Mod P000122012-11-21+$0= $7,051,792
- Mod P000102012-11-28+$147,898= $7,199,690
- Mod P000112012-11-29+$9,692= $7,209,382
- Mod P000132012-12-20+$1,938= $7,211,320
- Mod P000142013-03-25+$27,677= $7,238,997
- Mod P000152013-06-12+$55,534= $7,294,531
- Mod P000162013-11-15+$1,110,100= $8,404,631
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-11-24 | +$6,664,000 | $6,664,000 | CONSTRUCTION OF A NEW THERAPY POOL AND POLYTRAUMA CENTER AT THE VA PUGET SOUND HEALTHCARE SYSTEM, SEATTLE WA |
| Mod 1· CHANGE ORDER | 2011-04-19 | +$0 | $6,664,000 | CONSTRUCTION OF A NEW THERAPY POOL AND POLYTRAUMA CENTER AT THE VA PUGET SOUND HEALTHCARE SYSTEM, SEATTLE WA |
| Mod 3· CHANGE ORDER | 2011-05-09 | +$14,098 | $6,678,098 | CONSTRUCTION OF A NEW THERAPY POOL AND POLYTRAUMA CENTER AT THE VA PUGET SOUND HEALTHCARE SYSTEM, SEATTLE WA |
| Mod 2· CHANGE ORDER | 2011-06-13 | +$39,697 | $6,717,795 | CONSTRUCTION OF A NEW THERAPY POOL AND POLYTRAUMA CENTER AT THE VA PUGET SOUND HEALTHCARE SYSTEM, SEATTLE WA |
| Mod 4· CHANGE ORDER | 2011-09-23 | +$12,483 | $6,730,278 | BILATURAL MODIFICATION TO INCORPORATE 2 CHANGE ORDERS. THE WORK OF BOTH CHANGE ORDERS HAS BEEN DETERMINED TO… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-11-08 | +$56,008 | $6,786,286 | BILATURAL MODIFICATION TO INCORPORATE 5 CHANGE ORDERS. THE WORK OF THESE CHANGE ORDERS HAVE BEEN DETERMINED T… |
| Mod P00007· CHANGE ORDER | 2011-12-14 | +$0 | $6,786,286 | UNILATERAL MODIFICATION ISSUE CHANGE ORDERS 77, 78 AND 79 |
| Mod P00006· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-01-10 | +$217,629 | $7,003,915 | BILATURAL MODIFICATION TO RELOCATE WATER LINE AND OTHER UTILITIES |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-03-23 | +$25,008 | $7,028,923 | BILATURAL MODIFICATION TO RELOCATE WATER LINE AND OTHER UTILITIES |
| Mod P00009· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-09 | +$22,869 | $7,051,792 | BILATURAL MODIFICATION TO RELOCATE WATER LINE AND OTHER UTILITIES |
| Mod P00012· CHANGE ORDER | 2012-11-21 | +$0 | $7,051,792 | BILATURAL MODIFICATION FOR CO#S 42,64,109,110,114,124,127 |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-28 | +$147,898 | $7,199,690 | BILATURAL MODIFICATION DEFINITIZING CO#23 UNSUITABLE SOILS |
| Mod P00011· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-11-29 | +$9,692 | $7,209,382 | BILATURAL MODIFICATION FOR CO#S 42,64,109,110,114,124,127 |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-20 | +$1,938 | $7,211,320 | BILATURAL MODIFICATION FOR CO#103 |
| Mod P00014· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-25 | +$27,677 | $7,238,997 | BILATURAL MODIFICATION FOR CO#46,68,75,76,83,85,87,90&106 |
| Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-06-12 | +$55,534 | $7,294,531 | BILATURAL MODIFICATION FOR CO#45,59,80,93,96,98,99,102,107,111,113,116,117,118,119,122,123, 132 |
| Mod P00016· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-11-15 | +$1,110,100 | $8,404,631 | MODIFICATION P00016 - REA SETTLEMENT |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI K765UKMU2U42)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA260C0856 | 260-NETWORK CONTRACT OFFICE 20 · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $2,498,100 | FY2010 |
Other recipients under Y149 from 260-NETWORK CONTRACT OFFICE 20 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA692C11630 | KOLA, INC. | 260-NETWORK CONTRACT OFFICE 20 | $42,910 | FY2011 |
| VA668C15059 | DWG & ASSOCIATES, INC. | 260-NETWORK CONTRACT OFFICE 20 | $1,992,181 | FY2011 |
| VA531C15112 | DWG & ASSOCIATES, INC. | 260-NETWORK CONTRACT OFFICE 20 | $819,872 | FY2011 |
| VA663Z10008 | INTERFACE TECHNOLOGIES NORTHWEST, INC. | 260-NETWORK CONTRACT OFFICE 20 | $547 | FY2011 |
| VA692C11609 | KEVCON, INC | 260-NETWORK CONTRACT OFFICE 20 | $189,000 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA260C0895_3600_-NONE-_-NONE- · retrieved 2026-09-26.