Description
DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC
First action · last action
2009-06-19 · 2012-07-12
Transactions
24
First transaction's obligation
$3,424,241
Base + all options value (sum of deltas)
$3,706,381
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
NO SET ASIDE USED.
Offers received
5
SDVOSB flag on record
No
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION
Modification chain · 24 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2009-06-19+$3,424,241= $3,424,241
- Mod 12009-11-25-$4,643= $3,419,598
- Mod 22009-12-18+$20,000= $3,439,598
- Mod 32010-01-13+$2,482= $3,442,080
- Mod 42010-01-22+$10,923= $3,453,003
- Mod 52010-02-03+$9,500= $3,462,503
- Mod 62010-02-09+$4,810= $3,467,313
- Mod 72010-02-19+$8,579= $3,475,892
- Mod 82010-04-16+$2,500= $3,478,392
- Mod 92010-04-28+$96,579= $3,574,971
- Mod 102010-05-12+$1,546= $3,576,516
- Mod 112010-05-19-$10,908= $3,565,608
- Mod 122010-05-20+$0= $3,565,608
- Mod 132010-06-28+$0= $3,565,608
- Mod 142010-08-06+$4,200= $3,569,808
- Mod 152010-08-13+$2,364= $3,572,171
- Mod 162010-09-27+$14,859= $3,587,030
- Mod 172010-09-27+$17,965= $3,604,995
- Mod 182010-09-28+$4,848= $3,609,843
- Mod 192010-10-22+$8,778= $3,618,621
- Mod 202010-10-22+$23,075= $3,641,696
- Mod 212010-11-30+$0= $3,641,696
- Mod 222011-03-11+$33,605= $3,675,301
- Mod 232012-07-12+$31,079= $3,706,381
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2009-06-19 | +$3,424,241 | $3,424,241 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-25 | −$4,643 | $3,419,598 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 2· CHANGE ORDER | 2009-12-18 | +$20,000 | $3,439,598 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-13 | +$2,482 | $3,442,080 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-22 | +$10,923 | $3,453,003 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 5· CHANGE ORDER | 2010-02-03 | +$9,500 | $3,462,503 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 6· CHANGE ORDER | 2010-02-09 | +$4,810 | $3,467,313 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-02-19 | +$8,579 | $3,475,892 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 8· CHANGE ORDER | 2010-04-16 | +$2,500 | $3,478,392 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-04-28 | +$96,579 | $3,574,971 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 10· CHANGE ORDER | 2010-05-12 | +$1,546 | $3,576,516 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 11· CHANGE ORDER | 2010-05-19 | −$10,908 | $3,565,608 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 12· CHANGE ORDER | 2010-05-20 | +$0 | $3,565,608 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 13· CHANGE ORDER | 2010-06-28 | +$0 | $3,565,608 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 14· CHANGE ORDER | 2010-08-06 | +$4,200 | $3,569,808 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 15· CHANGE ORDER | 2010-08-13 | +$2,364 | $3,572,171 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 16· CHANGE ORDER | 2010-09-27 | +$14,859 | $3,587,030 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 17· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-09-27 | +$17,965 | $3,604,995 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 18· CHANGE ORDER | 2010-09-28 | +$4,848 | $3,609,843 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 19· CHANGE ORDER | 2010-10-22 | +$8,778 | $3,618,621 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 20· CHANGE ORDER | 2010-10-22 | +$23,075 | $3,641,696 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 21· CHANGE ORDER | 2010-11-30 | +$0 | $3,641,696 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 22· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-11 | +$33,605 | $3,675,301 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
| Mod 23· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-07-12 | +$31,079 | $3,706,381 | DEMOLISH AND REPLACE BLD 221 AT VA WHITE CITY SORCC |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI J7DMM4T6DLH7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26015P0154 | 260-NETWORK CONTRACT OFFICE 20 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $77,350 | FY2015 |
| VA26015P0063 | 260-NETWORK CONTRACT OFFICE 20 · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $18,705 | FY2015 |
| VA26013C0066 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $8,748,570 | FY2013 |
| VA26013C0063 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $8,055,027 | FY2013 |
| VA26012C0007 | 260-NETWORK CONTRACT OFFICE 20 · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $9,044,187 | FY2012 |
| VA260C0958 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y141 · CONSTRUCT/HOSPITALS & INFIRMARIES | $7,998,983 | FY2011 |
Other recipients under Y141 from 260-NETWORK CONTRACT OFFICE 20 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA648C12029 | COLAMETTE CONSTRUCTION COMPANY | 260-NETWORK CONTRACT OFFICE 20 | $541,737 | FY2011 |
| VA648C12028 | GLEN/MAR CONSTRUCTION, INC. | 260-NETWORK CONTRACT OFFICE 20 | $419,678 | FY2011 |
| VA531C15107 | JHC FIRE CONTAINMENT SOLUTIONS INC | 260-NETWORK CONTRACT OFFICE 20 | $447,369 | FY2011 |
| VA260C0960 | KEVCON, INC | 260-NETWORK CONTRACT OFFICE 20 | $3,758,694 | FY2011 |
| VA668C15056 | DWG & ASSOCIATES, INC. | 260-NETWORK CONTRACT OFFICE 20 | $137,594 | FY2011 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA260C0628_3600_-NONE-_-NONE- · retrieved 2026-09-26.