Description
MODIFICATION P00029 INCORPORATE FINAL CONTRACT CHANGE AND CORRECTIONS. ISSUE SUPPLEMENTAL AGREEMENT FOR CHANGE 2, 13, 15, 16, 17, 18, 19, 21, 22, 23, 25, AND SUPPLEMENTAL AGREEMENT FOR NEW CHANGES IN COR 24, 33, 46, 60.
Base award description: SEISMIC UPGRADE BUILDING 11
Modification chain · 31 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2008-09-26+$2,592,040= $2,592,040
- Mod 12009-05-27+$80,000= $2,672,040
- Mod 22009-07-23+$8,400= $2,680,440
- Mod 62009-10-01+$0= $2,680,440
- Mod 32009-10-14+$20,611= $2,701,051
- Mod 42009-10-14+$1,463= $2,702,514
- Mod 52009-10-14+$0= $2,702,514
- Mod 72009-11-05+$0= $2,702,514
- Mod 82009-11-17+$20,000= $2,722,514
- Mod 102010-01-20+$43,873= $2,766,387
- Mod 92010-01-20+$10,668= $2,777,055
- Mod 112010-02-10+$8,947= $2,786,002
- Mod 122010-02-19+$7,013= $2,793,014
- Mod 132010-02-19+$15,000= $2,808,014
- Mod 142010-02-19+$13,391= $2,821,405
- Mod 152010-03-01+$8,914= $2,830,319
- Mod 162010-03-05+$28,995= $2,859,314
- Mod 172010-03-18+$15,000= $2,874,314
- Mod 182010-03-24+$5,000= $2,879,314
- Mod 192010-04-02+$23,000= $2,902,314
- Mod 202010-06-09+$9,262= $2,911,576
- Mod 212010-07-01+$10,000= $2,921,576
- Mod 222010-07-09+$5,000= $2,926,576
- Mod 232010-08-12+$50,000= $2,976,576
- Mod 242010-08-18+$5,318= $2,981,894
- Mod 252010-12-13+$2,237= $2,984,131
- Mod 262011-01-12+$10,869= $2,995,000
- Mod 272011-05-25+$5,231= $3,000,230
- Mod 282011-05-25+$9,105= $3,009,335
- Mod P000292014-10-27+$120,728= $3,130,063
- Mod P000302015-03-30+$45,258= $3,175,321
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2008-09-26 | +$2,592,040 | $2,592,040 | SEISMIC UPGRADE BUILDING 11 |
| Mod 1· CHANGE ORDER | 2009-05-27 | +$80,000 | $2,672,040 | SEISMIC UPGRADE BUILDING 11 |
| Mod 2· CHANGE ORDER | 2009-07-23 | +$8,400 | $2,680,440 | SEISMIC UPGRADE BUILDING 11 |
| Mod 6· CHANGE ORDER | 2009-10-01 | +$0 | $2,680,440 | SEISMIC UPGRADE BUILDING 11 |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-10-14 | +$20,611 | $2,701,051 | SEISMIC UPGRADE BUILDING 11 |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-10-14 | +$1,463 | $2,702,514 | SEISMIC UPGRADE BUILDING 11 |
| Mod 5· CHANGE ORDER | 2009-10-14 | +$0 | $2,702,514 | SEISMIC UPGRADE BUILDING 11 |
| Mod 7· CHANGE ORDER | 2009-11-05 | +$0 | $2,702,514 | SEISMIC UPGRADE BUILDING 11 |
| Mod 8· CHANGE ORDER | 2009-11-17 | +$20,000 | $2,722,514 | SEISMIC UPGRADE BUILDING 11 |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-20 | +$43,873 | $2,766,387 | SEISMIC UPGRADE BUILDING 11 |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-01-20 | +$10,668 | $2,777,055 | SEISMIC UPGRADE BUILDING 11 |
| Mod 11· CHANGE ORDER | 2010-02-10 | +$8,947 | $2,786,002 | SEISMIC UPGRADE BUILDING 11 |
| Mod 12· CHANGE ORDER | 2010-02-19 | +$7,013 | $2,793,014 | SEISMIC UPGRADE BUILDING 11 |
| Mod 13· CHANGE ORDER | 2010-02-19 | +$15,000 | $2,808,014 | SEISMIC UPGRADE BUILDING 11 |
| Mod 14· CHANGE ORDER | 2010-02-19 | +$13,391 | $2,821,405 | SEISMIC UPGRADE BUILDING 11 |
| Mod 15· CHANGE ORDER | 2010-03-01 | +$8,914 | $2,830,319 | SEISMIC UPGRADE BUILDING 11 |
| Mod 16· CHANGE ORDER | 2010-03-05 | +$28,995 | $2,859,314 | SEISMIC UPGRADE BUILDING 11 |
| Mod 17· CHANGE ORDER | 2010-03-18 | +$15,000 | $2,874,314 | SEISMIC UPGRADE BUILDING 11 |
| Mod 18· CHANGE ORDER | 2010-03-24 | +$5,000 | $2,879,314 | SEISMIC UPGRADE BUILDING 11 |
| Mod 19· CHANGE ORDER | 2010-04-02 | +$23,000 | $2,902,314 | SEISMIC UPGRADE BUILDING 11 |
| Mod 20· CHANGE ORDER | 2010-06-09 | +$9,262 | $2,911,576 | SEISMIC UPGRADE BUILDING 11 |
| Mod 21· CHANGE ORDER | 2010-07-01 | +$10,000 | $2,921,576 | SEISMIC UPGRADE BUILDING 11 |
| Mod 22· CHANGE ORDER | 2010-07-09 | +$5,000 | $2,926,576 | SEISMIC UPGRADE BUILDING 11 |
| Mod 23· CHANGE ORDER | 2010-08-12 | +$50,000 | $2,976,576 | SEISMIC UPGRADE BUILDING 11 |
| Mod 24· CHANGE ORDER | 2010-08-18 | +$5,318 | $2,981,894 | SEISMIC UPGRADE BUILDING 11 |
| Mod 25· CHANGE ORDER | 2010-12-13 | +$2,237 | $2,984,131 | SEISMIC UPGRADE BUILDING 11 |
| Mod 26· CHANGE ORDER | 2011-01-12 | +$10,869 | $2,995,000 | SEISMIC UPGRADE BUILDING 11 |
| Mod 27· CHANGE ORDER | 2011-05-25 | +$5,231 | $3,000,230 | SEISMIC UPGRADE BUILDING 11 |
| Mod 28· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-25 | +$9,105 | $3,009,335 | 1. THE SCOPE OF WORK ON S2.4 HAS BEEN REVISED PER SUBMITTAL 29 TO REQUIRE ADDITIONAL STRUCTURAL ENHANCEMENT AT… |
| Mod P00029· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2014-10-27 | +$120,728 | $3,130,063 | MODIFICATION P00029 INCORPORATE FINAL CONTRACT CHANGE AND CORRECTIONS. |
| Mod P00030· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2015-03-30 | +$45,258 | $3,175,321 | MODIFICATION P00029 INCORPORATE FINAL CONTRACT CHANGE AND CORRECTIONS. ISSUE SUPPLEMENTAL AGREEMENT FOR CHANGE… |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI SCM2PEG3V1C9)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26021P0264 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $191,322 | FY2021 |
| 36C26021P0263 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $154,434 | FY2021 |
| 36C26021N0139 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $1,551,890 | FY2021 |
| 36C26021N0119 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $587,926 | FY2021 |
| 36C26020N0639 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $72,058 | FY2020 |
| 36C26120N0687 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1JZ · CONSTRUCTION OF MISCELLANEOUS BUILDINGS | $2,000 | FY2020 |
Other recipients under Y141 from 260-NETWORK CONTRACT OFFICE 20 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA668C15056 | DWG & ASSOCIATES, INC. | 260-NETWORK CONTRACT OFFICE 20 | $137,594 | FY2011 |
| VA260C0960 | KEVCON, INC | 260-NETWORK CONTRACT OFFICE 20 | $3,758,694 | FY2011 |
| VA648C12029 | COLAMETTE CONSTRUCTION COMPANY | 260-NETWORK CONTRACT OFFICE 20 | $541,737 | FY2011 |
| VA531C15107 | JHC FIRE CONTAINMENT SOLUTIONS INC | 260-NETWORK CONTRACT OFFICE 20 | $447,369 | FY2011 |
| VA668C15057 | BURTON CONSTRUCTION, INC. | 260-NETWORK CONTRACT OFFICE 20 | $1,305,494 | FY2011 |