Description
EO14042 BOILER PLAN CALIBRATION
Base award description: IGF::OT::IGF BOILER PLAN CALIBRATION
Modification chain · 9 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2017-09-18+$93,600= $93,600
- Mod P000012018-08-16+$93,600= $187,200
- Mod P000022018-09-14+$23,000= $210,200
- Mod P000032018-12-03+$28,408= $238,608
- Mod P000042019-03-14+$24,000= $262,608
- Mod P000052019-08-22+$93,600= $356,208
- Mod P000072020-09-14+$46,800= $403,008
- Mod P000082021-08-27+$60,000= $463,008
- Mod P000102024-03-18-$28,408= $434,600
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2017-09-18 | +$93,600 | $93,600 | IGF::OT::IGF BOILER PLAN CALIBRATION |
| Mod P00001· EXERCISE AN OPTION | 2018-08-16 | +$93,600 | $187,200 | IGF::OT::IGF BOILER PLAN CALIBRATION |
| Mod P00002· FUNDING ONLY ACTION | 2018-09-14 | +$23,000 | $210,200 | IGF::OT::IGF BOILER PLAN CALIBRATION |
| Mod P00003· FUNDING ONLY ACTION | 2018-12-03 | +$28,408 | $238,608 | IGF::OT::IGF BOILER PLAN CALIBRATION |
| Mod P00004· FUNDING ONLY ACTION | 2019-03-14 | +$24,000 | $262,608 | IGF::OT::IGF BOILER PLAN CALIBRATION |
| Mod P00005· EXERCISE AN OPTION | 2019-08-22 | +$93,600 | $356,208 | BOILER PLAN CALIBRATION OPTION YEAR |
| Mod P00007· EXERCISE AN OPTION | 2020-09-14 | +$46,800 | $403,008 | BOILER PLAN CALIBRATION OPTION YEAR AND MODFICATION OF PRICING. |
| Mod P00008· EXERCISE AN OPTION | 2021-08-27 | +$60,000 | $463,008 | BOILER PLAN CALIBRATION OPTION YEAR 4 |
| Mod P00010· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2024-03-18 | −$28,408 | $434,600 | EO14042 BOILER PLAN CALIBRATION |
Related awards · 9
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI K1SPZK4AJCS3)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26025P0734 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $180,000 | FY2025 |
| 36C26025P0164 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $19,950 | FY2025 |
| 36C26024P1012 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · 6115 · GENERATORS AND GENERATOR SETS, ELECTRICAL | $58,000 | FY2024 |
| VA26014P0397 | 260-NETWORK CONTRACT OFFICE 20 · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $34,295 | FY2014 |
Other recipients under J044 from 260-NETWORK CONTRACT OFFICE 20 (36C260) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26024P1230 | COLE INDUSTRIAL INC | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $63,955 | FY2024 |
| 36C26023N0206 | ACCO ENGINEERED SYSTEMS, INC. | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $18,128 | FY2023 |
| 36C26022N0585 | ACCO ENGINEERED SYSTEMS, INC. | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $12,265 | FY2022 |
| 36C26020P0813 | THE PLUMBING TEAM, LLC | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $90,000 | FY2020 |
| 36C26020P0045 | CH MURPHY CLARK ULLMAN INC | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $52,800 | FY2020 |