Description
IGF::OT::IGF PROJECT 663-15-104 UPGRADE ELEVATORS BUILDING 1 MODIFICATION OF THE TASK ORDER
Base award description: IGF::OT::IGF PROJECT 663-15-104 UPGRADE ELEVATORS BUILDING 1 SEATTLE VAMC NEW CONSTRUCTION TASK ORDER
Modification chain · 3 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2017-03-10+$2,560,899= $2,560,899
- Mod P000012018-03-12+$0= $2,560,899
- Mod P000022018-10-11+$134,612= $2,695,511
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2017-03-10 | +$2,560,899 | $2,560,899 | IGF::OT::IGF PROJECT 663-15-104 UPGRADE ELEVATORS BUILDING 1 SEATTLE VAMC NEW CONSTRUCTION TASK ORDER |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-03-12 | +$0 | $2,560,899 | IGF::OT::IGF PROJECT 663-15-104 UPGRADE ELEVATORS BUILDING 1 SEATTLE VAMC NEW CONSTRUCTION TASK ORDER |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2018-10-11 | +$134,612 | $2,695,511 | IGF::OT::IGF PROJECT 663-15-104 UPGRADE ELEVATORS BUILDING 1 MODIFICATION OF THE TASK ORDER |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI ZJ5TDRYAP9P8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C26026C0054 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $2,030,807 | FY2026 |
| 36C26026C0050 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · N063 · INSTALLATION OF EQUIPMENT- ALARM, SIGNAL, AND SECURITY DETECTION SYSTEMS | $1,999,999 | FY2026 |
| 36C26026C0037 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · J045 · MAINT/REPAIR/REBUILD OF EQUIPMENT- PLUMBING, HEATING, AND WASTE DISPOSAL EQUIPMENT | $252,140 | FY2026 |
| 36C26026C0031 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · N041 · INSTALLATION OF EQUIPMENT- REFRIGERATION, AIR CONDITIONING, AND AIR CIRCULATING EQUIPMENT | $2,624,968 | FY2026 |
| 36C26026C0026 | 260-NETWORK CONTRACT OFFICE 20 (36C260) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $699,933 | FY2026 |
| 36C77626C0041 | PCAC (36C776) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $1,143,144 | FY2026 |
Other recipients under Y1DZ from 260-NETWORK CONTRACT OFFICE 20 (36C260) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C26026C0010 | WRIGHT CONSTRUCTION GROUP LLC | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $1,730,374 | FY2026 |
| 36C26025P0832 | DRI, INC. | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $67,500 | FY2025 |
| 36C26025N0271 | ACCO ENGINEERED SYSTEMS, INC. | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $6,659 | FY2025 |
| 36C26024C0031 | ATC-ABSHER 1 JOINT VENTURE | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $13,025,992 | FY2024 |
| 36C26020N0217 | GLEN/MAR CONSTRUCTION, INC. | 260-NETWORK CONTRACT OFFICE 20 (36C260) | $70,798 | FY2020 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA26017J0953_3600_VA26013D0043_3600 · retrieved 2026-09-26.