Description
IGF::OT::IGF SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 663-378 MOD P12 - CHANGE OF ADDRESS
Base award description: IGF::OT::IGF SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 663-378
Modification chain · 13 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2012-03-28+$6,950,000= $6,950,000
- Mod P000012012-12-05+$7,050= $6,957,050
- Mod P000022013-03-07+$75,720= $7,032,770
- Mod P000032013-04-10+$25,587= $7,058,357
- Mod P000042013-07-03+$13,311= $7,071,668
- Mod P000052013-08-27+$42,603= $7,114,271
- Mod P000062013-10-03+$33,798= $7,148,069
- Mod P000072013-10-03+$75,456= $7,223,525
- Mod P000082013-12-04+$70,710= $7,294,235
- Mod P000092014-03-31+$92,460= $7,386,695
- Mod P000102014-03-31+$66,430= $7,453,125
- Mod P000112014-10-01+$29,171= $7,482,296
- Mod P000122015-01-22+$0= $7,482,296
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2012-03-28 | +$6,950,000 | $6,950,000 | IGF::OT::IGF SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 663-378 |
| Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2012-12-05 | +$7,050 | $6,957,050 | IGF::OT::IGF SUPPLEMENTAL AGREEMENT FOR CO#1&CO#2 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 6… |
| Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-03-07 | +$75,720 | $7,032,770 | IGF::OT::IGF SUPPLEMENTAL AGREEMENT FOR CO#3-2,3-3, 4&7 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJEC… |
| Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-04-10 | +$25,587 | $7,058,357 | IGF::OT::IGF SUPPLEMENTAL AGREEMENT FOR CO#3-2,3-3, 4&7 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJEC… |
| Mod P00004· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-07-03 | +$13,311 | $7,071,668 | IGF::OT::IGF SUPPLEMENTAL AGREEMENT FOR CO#3-2,3-3, 4&7 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJEC… |
| Mod P00005· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-08-27 | +$42,603 | $7,114,271 | IGF::OT::IGF SUPPLEMENTAL AGREEMENT FOR CO#3-2,3-3, 4&7 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJEC… |
| Mod P00006· CHANGE ORDER | 2013-10-03 | +$33,798 | $7,148,069 | IGF::OT::IGF SUPPLEMENTAL AGREEMENT FOR CO#3-2,3-3, 4&7 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJEC… |
| Mod P00007· CHANGE ORDER | 2013-10-03 | +$75,456 | $7,223,525 | IGF::OT::IGF SUPPLEMENTAL AGREEMENT FOR CO#17 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 663-37… |
| Mod P00008· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2013-12-04 | +$70,710 | $7,294,235 | IGF::OT::IGF CO#11,23-1,23-3,26,28,29 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 663-378 |
| Mod P00009· CHANGE ORDER | 2014-03-31 | +$92,460 | $7,386,695 | IGF::OT::IGF CO#11,23-1,23-3,26,28,29 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 663-378 |
| Mod P00010· CHANGE ORDER | 2014-03-31 | +$66,430 | $7,453,125 | IGF::OT::IGF CO#11,23-1,23-3,26,28,29 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 663-378 |
| Mod P00011· CHANGE ORDER | 2014-10-01 | +$29,171 | $7,482,296 | IGF::OT::IGF CO#11,23-1,23-3,26,28,29 SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 663-378 |
| Mod P00012· ENTITY ADDRESS CHANGE | 2015-01-22 | +$0 | $7,482,296 | IGF::OT::IGF SEISMICALLY UPGRADE AND RENOVATE BLDG 2, FL 1&2 PROJECT: 663-378 MOD P12 - CHANGE OF ADDRESS |
Related awards · 8
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI YQKLNFR9N289)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA26117J3073 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $5,000 | FY2017 |
| VA26014J0501 | 260-NETWORK CONTRACT OFFICE 20 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $10,000 | FY2014 |
| VA26014J0500 | 260-NETWORK CONTRACT OFFICE 20 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $10,000 | FY2014 |
| VA26014J0499 | 260-NETWORK CONTRACT OFFICE 20 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $10,000 | FY2014 |
| VA101F13C0069 | OFFICE OF CONSTRUCTION & FACILITIES MANAGEMENT · Y1DZ · CONSTRUCTION OF OTHER HOSPITAL BUILDINGS | $4,487,309 | FY2013 |
| VA26013J1579 | 260-NETWORK CONTRACT OFFICE 20 · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $1,189,723 | FY2013 |
Other recipients under Y1DB from 260-NETWORK CONTRACT OFFICE 20 (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA26012J0999 | GLEN/MAR CONSTRUCTION, INC. | 260-NETWORK CONTRACT OFFICE 20 | $3,463,631 | FY2012 |
| VA26012J0635 | SKYTEK LLC | 260-NETWORK CONTRACT OFFICE 20 | $603,970 | FY2012 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA26012C0020_3600_-NONE-_-NONE- · retrieved 2026-09-26.