Description
DESIGN A REPLACEMENT WATER PLANT FILTRATION MEMBRANE PLANT AT THE VA MEDICAL CENTER SHERIDAN, WY
Modification chain · 1 transaction
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-03-25+$0= $0
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base· CHANGE ORDER | 2010-03-25 | +$0 | $0 | DESIGN A REPLACEMENT WATER PLANT FILTRATION MEMBRANE PLANT AT THE VA MEDICAL CENTER SHERIDAN, WY |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under C211 from 666-SHERIDAN (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA666C10339 | ARETE DESIGN GROUP LLC | 666-SHERIDAN | $40,800 | FY2011 |
| VA259P03140002 | ARETE DESIGN GROUP LLC | 666-SHERIDAN | $11,910 | FY2008 |
| VA259P0314001 | ARETE DESIGN GROUP LLC | 666-SHERIDAN | $23,850 | FY2008 |
| VA259P0314 | ARETE DESIGN GROUP LLC | 666-SHERIDAN | $0 | FY2008 |
| VA259P0279 | IB ENGINEERING CORP | 666-SHERIDAN | $50,000 | FY2008 |