Award recordCONTRACT

OTIS ELEVATOR COMPANY

PIID VA25914F3702· VHA· NETWORK CONTRACT OFFICE 19 (36C259)· J099 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MISCELLANEOUS· FY2014· $935,702 net obligations· UEI G7RPMR7GT9P9· CT

Description

MOD #22 DECREASE FY17 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRISON VAMC.

Base award description: ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FORT HARRISON VAMC AND THE SALT LAKE CITY VAMC. IGF::OT::IGF

First action · last action
2014-05-29 · 2024-08-30
Transactions
23
First transaction's obligation
$86,772
Base + all options value (sum of deltas)
$966,180
Extent competed
FULL AND OPEN COMPETITION
Other than full & open authority
—
Set-aside
—
Offers received
3
SDVOSB flag on record
No
Parent IDV
GS06F0081M
NAICS
811310 · COMMERCIAL AND INDUSTRIAL MACHINERY AND EQUIPMENT (EXCEPT AUTOMOTIVE AND ELECTRONIC) REPAIR AND MAINTENANCE

Modification chain · 23 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$1,001,056$0Base award · 2014-05-29 · this action $86,772 · running total $86,772Modification P00001 · 2014-08-29 · this action $37,364 · running total $124,136Modification P00002 · 2014-10-01 · this action $45,540 · running total $169,676Modification P00003 · 2014-10-09 · this action $3,200 · running total $172,876Modification P00004 · 2015-06-01 · this action $190,830 · running total $363,706Modification P00005 · 2015-08-11 · this action $5,952 · running total $369,658Modification P00006 · 2016-05-19 · this action $122,520 · running total $492,178Modification P00008 · 2016-05-23 · this action $68,310 · running total $560,488Modification P00009 · 2017-05-26 · this action $200,580 · running total $761,068Modification P00011 · 2018-03-08 · this action -$17,697 · running total $743,371Modification P00010 · 2018-03-13 · this action -$11,380 · running total $731,991Modification P00012 · 2018-04-13 · this action $200,580 · running total $932,571Modification P00013 · 2019-05-24 · this action $53,845 · running total $986,416Modification P00014 · 2019-06-26 · this action $4,880 · running total $991,296Modification P00015 · 2019-07-30 · this action $9,760 · running total $1,001,056Modification P00016 · 2020-03-24 · this action -$9,750 · running total $991,306Modification P00017 · 2020-08-18 · this action -$12,714 · running total $978,591Modification P00018 · 2020-12-10 · this action -$9,750 · running total $968,841Modification P00019 · 2020-12-10 · this action -$9,014 · running total $959,827Modification P00020 · 2021-02-04 · this action -$9,750 · running total $950,077Modification P00021 · 2021-02-04 · this action -$3,250 · running total $946,827Modification P00022 · 2021-11-18 · this action -$6,250 · running total $940,577Modification P00023 · 2024-08-30 · this action -$4,875 · running total $935,702
  • Base2014-05-29+$86,772= $86,772
  • Mod P000012014-08-29+$37,364= $124,136
  • Mod P000022014-10-01+$45,540= $169,676
  • Mod P000032014-10-09+$3,200= $172,876
  • Mod P000042015-06-01+$190,830= $363,706
  • Mod P000052015-08-11+$5,952= $369,658
  • Mod P000062016-05-19+$122,520= $492,178
  • Mod P000082016-05-23+$68,310= $560,488
  • Mod P000092017-05-26+$200,580= $761,068
  • Mod P000112018-03-08-$17,697= $743,371
  • Mod P000102018-03-13-$11,380= $731,991
  • Mod P000122018-04-13+$200,580= $932,571
  • Mod P000132019-05-24+$53,845= $986,416
  • Mod P000142019-06-26+$4,880= $991,296
  • Mod P000152019-07-30+$9,760= $1,001,056
  • Mod P000162020-03-24-$9,750= $991,306
  • Mod P000172020-08-18-$12,714= $978,591
  • Mod P000182020-12-10-$9,750= $968,841
  • Mod P000192020-12-10-$9,014= $959,827
  • Mod P000202021-02-04-$9,750= $950,077
  • Mod P000212021-02-04-$3,250= $946,827
  • Mod P000222021-11-18-$6,250= $940,577
  • Mod P000232024-08-30-$4,875= $935,702
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2014-05-29+$86,772$86,772ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FORT HARRISON VAMC AND THE SALT LAKE CITY VAMC. IGF…
Mod P00001· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-08-29+$37,364$124,136ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FORT HARRISON VAMC AND THE SALT LAKE CITY VAMC. IGF…
Mod P00002· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-10-01+$45,540$169,676ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FORT HARRISON VAMC AND THE SALT LAKE CITY VAMC. IGF…
Mod P00003· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2014-10-09+$3,200$172,876ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FORT HARRISON VAMC AND THE SALT LAKE CITY VAMC. IGF…
Mod P00004· EXERCISE AN OPTION2015-06-01+$190,830$363,706ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FORT HARRISON VAMC AND THE SALT LAKE CITY VAMC. EXE…
Mod P00005· FUNDING ONLY ACTION2015-08-11+$5,952$369,658IGF::OT::IGF ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FORT HARRISON VAMC AND THE SALT LAKE C…
Mod P00006· EXERCISE AN OPTION2016-05-19+$122,520$492,178IGF::OT::IGF ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE SALT LAKE CITY VAMC OYII
Mod P00008· EXERCISE AN OPTION2016-05-23+$68,310$560,488IGF::OT::IGF ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE MONTANA (FT. HARRISON) VAMC OYII
Mod P00009· EXERCISE AN OPTION2017-05-26+$200,580$761,068IGF::OT::IGF ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE SALT LAKE CITY AND THE FT. HARRISON V…
Mod P00011· FUNDING ONLY ACTION2018-03-08−$17,697$743,371IGF::OT::IGF ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE SALT LAKE CITY AND THE FT. HARRISON V…
Mod P00010· FUNDING ONLY ACTION2018-03-13−$11,380$731,991IGF::OT::IGF MOD #10 TO REDUCE FY15 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR…
Mod P00012· EXERCISE AN OPTION2018-04-13+$200,580$932,571IGF::OT::IGF MOD #12 OPTION YEAR #4. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRISON…
Mod P00013· EXERCISE AN OPTION2019-05-24+$53,845$986,416IGF::OT::IGF MOD #13 EXTEND OF CONTRACT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARR…
Mod P00014· EXERCISE AN OPTION2019-06-26+$4,880$991,296IGF::OT::IGF MOD #14 EXTEND OF CONTRACT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARR…
Mod P00015· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2019-07-30+$9,760$1,001,056MOD #15 EXTEND CONTRACT 2 MONTHS. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRISON VAM…
Mod P00016· FUNDING ONLY ACTION2020-03-24−$9,750$991,306MOD #16 DECREASE FY18 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRIS…
Mod P00017· FUNDING ONLY ACTION2020-08-18−$12,714$978,591MOD #17 DECREASE FY15 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRIS…
Mod P00018· FUNDING ONLY ACTION2020-12-10−$9,750$968,841MOD #18 DECREASE FY17 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRIS…
Mod P00019· FUNDING ONLY ACTION2020-12-10−$9,014$959,827MOD #19 DECREASE FY16 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRIS…
Mod P00020· FUNDING ONLY ACTION2021-02-04−$9,750$950,077MOD #20 DECREASE FY18 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRIS…
Mod P00021· FUNDING ONLY ACTION2021-02-04−$3,250$946,827MOD #21 DECREASE FY19 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRIS…
Mod P00022· FUNDING ONLY ACTION2021-11-18−$6,250$940,577MOD #22 DECREASE FY17 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRIS…
Mod P00023· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2024-08-30−$4,875$935,702MOD #22 DECREASE FY17 PO FOR CLOSE-OUT. ELEVATOR PREVENTIVE MAINTENANCE AND REPAIR SERVICE FOR THE FT. HARRIS…

Related awards · 11

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI G7RPMR7GT9P9)

AwardOffice · PSC / listingNet obligationsFY
36C25926P0632NETWORK CONTRACT OFFICE 19 (36C259) · J059 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRICAL AND ELECTRONIC EQUIPMENT COMPONENTS$187,250FY2026
36C25926P0497NETWORK CONTRACT OFFICE 19 (36C259) · J059 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ELECTRICAL AND ELECTRONIC EQUIPMENT COMPONENTS$65,750FY2026
36C25925P0974NETWORK CONTRACT OFFICE 19 (36C259) · J035 · MAINT/REPAIR/REBUILD OF EQUIPMENT- SERVICE AND TRADE EQUIPMENT$247,000FY2025
36C25024C0130250-NETWORK CONTRACT OFFICE 10 (36C250) · J065 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MEDICAL, DENTAL, AND VETERINARY EQUIPMENT AND SUPPLIES$21,791FY2024
36C25024C0120250-NETWORK CONTRACT OFFICE 10 (36C250) · J040 · MAINT/REPAIR/REBUILD OF EQUIPMENT- ROPE, CABLE, CHAIN, AND FITTINGS$53,055FY2024
36C25024P0898250-NETWORK CONTRACT OFFICE 10 (36C250) · J039 · MAINT/REPAIR/REBUILD OF EQUIPMENT- MATERIALS HANDLING EQUIPMENT$15,771FY2024

Other recipients under J099 from NETWORK CONTRACT OFFICE 19 (36C259) (most recent first)

AwardRecipientOfficeNet obligationsFY
36C25921C0010BANNING CONTRACTING SERVICES INCNETWORK CONTRACT OFFICE 19 (36C259)$64,776FY2021
36C25920P1012TRILLAMED LLCNETWORK CONTRACT OFFICE 19 (36C259)$129,183FY2020
36C25920P1033D. H. PACE COMPANY, INC.NETWORK CONTRACT OFFICE 19 (36C259)$17,010FY2020
36C25920C0183HURTVET SUBCONTRACTING, INC.NETWORK CONTRACT OFFICE 19 (36C259)$614,930FY2020
36C25920F0386EVOQUA WATER TECHNOLOGIES LLCNETWORK CONTRACT OFFICE 19 (36C259)$95,224FY2020

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25914F3702_3600_GS06F0081M_4730 · retrieved 2026-09-26.