Description
TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS
Modification chain · 12 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-06-28+$612,498= $612,498
- Mod 12010-09-29+$14,341= $626,839
- Mod 22010-12-08+$0= $626,839
- Mod 32010-12-08+$0= $626,839
- Mod 42010-12-08+$0= $626,839
- Mod 52010-12-08+$0= $626,839
- Mod 62010-12-15+$0= $626,839
- Mod 82011-02-15+$0= $626,839
- Mod 72011-02-17+$0= $626,839
- Mod 102011-05-19+$40,000= $666,839
- Mod 92011-05-19+$0= $666,839
- Mod 112011-09-06+$4,039= $670,878
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-06-28 | +$612,498 | $612,498 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 1· CHANGE ORDER | 2010-09-29 | +$14,341 | $626,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 2· CHANGE ORDER | 2010-12-08 | +$0 | $626,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 3· CHANGE ORDER | 2010-12-08 | +$0 | $626,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 4· CHANGE ORDER | 2010-12-08 | +$0 | $626,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 5· CHANGE ORDER | 2010-12-08 | +$0 | $626,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 6· CHANGE ORDER | 2010-12-15 | +$0 | $626,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-15 | +$0 | $626,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 7· CHANGE ORDER | 2011-02-17 | +$0 | $626,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-19 | +$40,000 | $666,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-19 | +$0 | $666,839 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
| Mod 11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-06 | +$4,039 | $670,878 | TAS::36 0158::TAS ARRA - MAIN ENTRY RENOVATION TO INCLUDE ASBESTOS |
Related awards · 5
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other recipients under Z141 from 519-BIG SPRING (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA258RA0395 | AGILE INFRASTRUCTURE SERVICES, L.L.C. | 519-BIG SPRING | $1,071,207 | FY2010 |
| VA258RA0392 | AGILE INFRASTRUCTURE SERVICES, L.L.C. | 519-BIG SPRING | $396,241 | FY2010 |
| VA258C0280 | TAPCO CONSTRUCTION, LLC | 519-BIG SPRING | $14,582 | FY2009 |
| VA258C0278 | TAPCO CONSTRUCTION, LLC | 519-BIG SPRING | $11,800 | FY2009 |
| VA258C0279 | TAPCO CONSTRUCTION, LLC | 519-BIG SPRING | $14,195 | FY2009 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA258RA0386_3600_-NONE-_-NONE- · retrieved 2026-09-26.