Description
RESEARCH EXPANSION 644-226 P00013
Base award description: OT RENOVATION OF RESEARCH EXPANSION LAB
Modification chain · 17 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2010-09-15+$3,648,000= $3,648,000
- Mod 12010-11-12+$234,879= $3,882,879
- Mod 22011-02-15+$51,785= $3,934,664
- Mod 32011-03-31+$37,607= $3,972,271
- Mod 42011-04-04+$82,973= $4,055,244
- Mod 52011-04-05+$57,601= $4,112,845
- Mod 62011-04-08+$98,642= $4,211,487
- Mod 72011-04-08+$94,848= $4,306,335
- Mod CN0012011-05-05+$0= $4,306,335
- Mod 82011-05-16+$430,481= $4,736,816
- Mod CN0022011-05-27+$0= $4,736,816
- Mod 92011-06-06+$31,314= $4,768,130
- Mod CN0032011-06-14+$0= $4,768,130
- Mod 102011-06-26+$69,120= $4,837,250
- Mod 112011-07-27+$79,970= $4,917,220
- Mod 122011-09-02+$9,535= $4,926,755
- Mod P000132011-12-06+$13,027= $4,939,782
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2010-09-15 | +$3,648,000 | $3,648,000 | OT RENOVATION OF RESEARCH EXPANSION LAB |
| Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2010-11-12 | +$234,879 | $3,882,879 | RENOVATION OF RESEARCH EXPANSION LAB ADDED TEMP SPACE AS PART OF IMPACT COSTS. |
| Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-02-15 | +$51,785 | $3,934,664 | RENOVATION OF RESEARCH EXPANSION LAB ADDED UNFORSEEN CONSDITIONS. |
| Mod 3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-03-31 | +$37,607 | $3,972,271 | RENOVATION OF RESEARCH EXPANSION LAB ADDED UNFORSEEN CONSDITIONS. |
| Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-04 | +$82,973 | $4,055,244 | RENOVATION OF RESEARCH EXPANSION LAB ADDED UNFORSEEN CONSDITIONS. |
| Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-05 | +$57,601 | $4,112,845 | RENOVATION OF RESEARCH EXPANSION LAB ADDED UNFORSEEN CONSDITIONS. |
| Mod 6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-08 | +$98,642 | $4,211,487 | RENOVATION OF RESEARCH EXPANSION LAB ADDED UNFORSEEN CONSDITIONS. |
| Mod 7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-04-08 | +$94,848 | $4,306,335 | RENOVATION OF RESEARCH EXPANSION LAB ADDED UNFORSEEN CONSDITIONS. |
| Mod CN001· CHANGE ORDER | 2011-05-05 | +$0 | $4,306,335 | CHANGE NOTICE TO PROVIDE DIRECTION TO PROCEED ON DATA&ELECTRICAL TRENCHING. |
| Mod 8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-05-16 | +$430,481 | $4,736,816 | RENOVATION OF RESEARCH EXPANSION LAB ADDED UNFORSEEN CONSDITIONS. |
| Mod CN002· CHANGE ORDER | 2011-05-27 | +$0 | $4,736,816 | CHANGE NOTICE TO PROVIDE DIRECTION TO PROCEED WITH PURCHASE AND INSTALLATION OF LABORATORY FLUME HOODS. |
| Mod 9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-06 | +$31,314 | $4,768,130 | ADDITIONAL WORK ASSOCIATED WITH DEMOLITION&TRENCHING FOR INSTALLATION OF UNDERGROUND CABLING. |
| Mod CN003· CHANGE ORDER | 2011-06-14 | +$0 | $4,768,130 | CHANGE NOTICE TO PROVIDE DIRECTION TO PROCEED WITH MOLD REMOVLA EFFORTS IN INTERIOR OF BLDG 21. |
| Mod 10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-06-26 | +$69,120 | $4,837,250 | ADDITIONAL WORK ASSOCIATED WITH DEMOLITION&TRENCHING FOR INSTALLATION OF UNDERGROUND CABLING. |
| Mod 11· CHANGE ORDER | 2011-07-27 | +$79,970 | $4,917,220 | TO FORMALIZE CN 0002 AND CN 0003 REPAIRING ROOF DRAIN, ELECRTRICAL BOX, MOLD INVESTIGATION |
| Mod 12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-09-02 | +$9,535 | $4,926,755 | RESEARCH EXPANSION 644-226 |
| Mod P00013· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2011-12-06 | +$13,027 | $4,939,782 | RESEARCH EXPANSION 644-226 P00013 |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI JUHDFA8S7NU8)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA70117C0033 | PCAC NATIONAL ENERGY BUSINESS CENTER (36E776) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $8,092,109 | FY2017 |
| VA26117C0151 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $7,424,575 | FY2017 |
| VA26216J6801 | 258-NETWORK CNTRCT OFF 22G (36C258) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $5,422,806 | FY2016 |
| VA26116J2566 | 261-NETWORK CONTRACT OFFICE 21 (36C261) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS | $2,129,768 | FY2016 |
| VA26216J4441 | 258-NETWORK CNTRCT OFF 22G (36C258) · Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS | $1,176,684 | FY2016 |
| VA26115P1913 | 261-NETWORK CONTRACT OFFICE 21 · J046 · MAINT/REPAIR/REBUILD OF EQUIPMENT- WATER PURIFICATION AND SEWAGE TREATMENT EQUIPMENT | $12,189 | FY2015 |