Award recordCONTRACT

UTILITY CONSTRUCTION COMPANY, INC.

PIID VA258C0118· VHA· 644-PHOENIX· Z249 · MAINT-REP-ALT/OTHER UTILITIES· FY2008· $3,390,689 net obligations· UEI JHEJMWJACNN8· AZ

Description

ELECTRICAL PHASE 2

Base award description: PROJECT N. 644-08-101, ELECTRICAL INFRASTRUCTURE UPGRADE, PHASE 2. P.O. 644-E87099.

First action · last action
2008-05-22 · 2010-04-28
Transactions
9
First transaction's obligation
$3,094,035
Base + all options value (sum of deltas)
$3,390,689
Extent competed
NOT AVAILABLE FOR COMPETITION
Other than full & open authority
AUTHORIZED BY STATUTE
Set-aside
8(A) SOLE SOURCE
Offers received
1
SDVOSB flag on record
No
NAICS
238210 · ELECTRICAL CONTRACTORS AND OTHER WIRING INSTALLATION CONTRACTORS

Modification chain · 9 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$3,390,689$0Base award · 2008-05-22 · this action $3,094,035 · running total $3,094,035Modification 1 · 2009-02-02 · this action -$563 · running total $3,093,472Modification COA · 2009-03-03 · this action $0 · running total $3,093,472Modification 2 · 2009-03-10 · this action $11,252 · running total $3,104,724Modification COB · 2009-07-28 · this action $82,013 · running total $3,186,737Modification COC · 2009-09-15 · this action $152,188 · running total $3,338,925Modification COD · 2009-10-26 · this action $46,297 · running total $3,385,222Modification 4 · 2010-03-05 · this action $0 · running total $3,385,222Modification 5 · 2010-04-28 · this action $5,467 · running total $3,390,689
  • Base2008-05-22+$3,094,035= $3,094,035
  • Mod 12009-02-02-$563= $3,093,472
  • Mod COA2009-03-03+$0= $3,093,472
  • Mod 22009-03-10+$11,252= $3,104,724
  • Mod COB2009-07-28+$82,013= $3,186,737
  • Mod COC2009-09-15+$152,188= $3,338,925
  • Mod COD2009-10-26+$46,297= $3,385,222
  • Mod 42010-03-05+$0= $3,385,222
  • Mod 52010-04-28+$5,467= $3,390,689
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2008-05-22+$3,094,035$3,094,035PROJECT N. 644-08-101, ELECTRICAL INFRASTRUCTURE UPGRADE, PHASE 2. P.O. 644-E87099.
Mod 1· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-02-02−$563$3,093,472PROJECT N. 644-08-101, ELECTRICAL INFRASTRUCTURE UPGRADE, PHASE 2. P.O. 644-E87099.
Mod COA· CHANGE ORDER2009-03-03+$0$3,093,472—
Mod 2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2009-03-10+$11,252$3,104,724PROJECT N. 644-08-101, ELECTRICAL INFRASTRUCTURE UPGRADE, PHASE 2. P.O. 644-E87099.
Mod COB· CHANGE ORDER2009-07-28+$82,013$3,186,737CHANGE ORDER FOR ELECTRICAL INFRASTRUCTURE PHASE 2 PROJECT
Mod COC· CHANGE ORDER2009-09-15+$152,188$3,338,925CHANGE ORDER FOR ELECTRICAL INFRASTRUCTURE PHASE 2 PROJECT
Mod COD· CHANGE ORDER2009-10-26+$46,297$3,385,222CHANGE ORDER FOR ELECTRICAL INFRASTRUCTURE PHASE 2 PROJECT
Mod 4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-03-05+$0$3,385,222PROJECT N. 644-08-101, ELECTRICAL INFRASTRUCTURE UPGRADE, PHASE 2. P.O. 644-E87099.
Mod 5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE2010-04-28+$5,467$3,390,689ELECTRICAL PHASE 2