Description
CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ
Modification chain · 20 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2007-11-21+$0= $0
- Mod SA22007-12-06+$0= $0
- Mod SA32008-07-01+$4,055= $4,055
- Mod SA42008-09-17+$2,749= $6,804
- Mod SA52008-11-15+$31,383= $38,187
- Mod COE2009-02-24+$0= $38,187
- Mod COF2009-02-27+$0= $38,187
- Mod COG2009-03-07+$0= $38,187
- Mod SA62009-04-18+$0= $38,187
- Mod COH2009-05-11+$0= $38,187
- Mod SA72009-06-17+$8,183= $46,370
- Mod SA82009-06-23+$0= $46,370
- Mod SA92009-06-26+$17,429= $63,799
- Mod SA102009-07-16+$5,648= $69,447
- Mod COI2009-08-14+$0= $69,447
- Mod COJ2009-08-14+$0= $69,447
- Mod SA112009-08-31+$0= $69,447
- Mod SA122009-09-18+$22,109= $91,556
- Mod SA132009-10-23+$0= $91,556
- Mod SA142009-11-04+$6,743= $98,299
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2007-11-21 | +$0 | $0 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA2· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2007-12-06 | +$0 | $0 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA3· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2008-07-01 | +$4,055 | $4,055 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA4· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2008-09-17 | +$2,749 | $6,804 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA5· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2008-11-15 | +$31,383 | $38,187 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod COE· CHANGE ORDER | 2009-02-24 | +$0 | $38,187 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod COF· CHANGE ORDER | 2009-02-27 | +$0 | $38,187 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod COG· CHANGE ORDER | 2009-03-07 | +$0 | $38,187 | — |
| Mod SA6· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-04-18 | +$0 | $38,187 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod COH· CHANGE ORDER | 2009-05-11 | +$0 | $38,187 | CORRECT DUCTWORK |
| Mod SA7· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-06-17 | +$8,183 | $46,370 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA8· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-06-23 | +$0 | $46,370 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA9· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-06-26 | +$17,429 | $63,799 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA10· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-07-16 | +$5,648 | $69,447 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod COI· CHANGE ORDER | 2009-08-14 | +$0 | $69,447 | PROVIDE AND INSTALL PATHWAY AND DUCT SMOKE DETECTOR AND PROGRAMING FOR AHU 7 TO SHUT DOWN AND RESET DURING FIR… |
| Mod COJ· CHANGE ORDER | 2009-08-14 | +$0 | $69,447 | PROVIDE AND INSTALL PATHWAY AND DUCT SMOKE DETECTOR AND PROGRAMING FOR AHU 7 TO SHUT DOWN AND RESET DURING FIR… |
| Mod SA11· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-08-31 | +$0 | $69,447 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA12· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-09-18 | +$22,109 | $91,556 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA13· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-10-23 | +$0 | $91,556 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
| Mod SA14· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2009-11-04 | +$6,743 | $98,299 | CONSTRUCTION CONTRACT FOR AIR HANDLERS PHASE I AT SAVAHCS, TUCSON, AZ |
Related awards · 10
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI NE7LHV5QC1N7)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA258C0289 | 756-EL PASO · Z224 · MAINT-REP-ALT/PARKING FACILITIES | $423,111 | FY2009 |
| VA258C0268 | 756-EL PASO · Y224 · CONSTRUCT/PARKING FACILITIES | $452,397 | FY2009 |
| VA258C0238XERIS | 756-EL PASO · S208 · LANDSCAPING/GROUNDSKEEPING SERVICES | $456,299 | FY2009 |
| VA258C0033 | 678-TUCSON · Z141 · MAINT-REP-ALT/HOSPITALS & INFIRMARY | $55,602 | FY2008 |
| VA258C0024 | 678-TUCSON · Z149 · MAINT-REP-ALT/OTHER HOSPITAL BLDGS | -$122,603 | FY2008 |
Other recipients under Z299 from 678-TUCSON (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| VA258C0417 | AFFILIATED WESTERN, INC. | 678-TUCSON | $988,594 | FY2011 |
| V678P00361 | SOUTHWEST HAZARD CONTROL INC | 678-TUCSON | $3,221 | FY2010 |
| V678C00009 | JOHNSON CONTROLS, INC | 678-TUCSON | $124,500 | FY2010 |
| VA258RA0292 | UNITED BUILDERS, LLC | 678-TUCSON | $862,985 | FY2009 |
| V6789P3992 | SOUTHWEST HAZARD CONTROL INC | 678-TUCSON | $8,500 | FY2009 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA258C0034_3600_-NONE-_-NONE- · retrieved 2026-09-26.