CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 16 UNFORESEEN SITE CONDITION WITH INLET ELEVATION
Base award description: CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT IGF::OT::IGF
Modification chain · 18 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2016-08-26+$987,000= $987,000
- Mod P000012016-12-12+$0= $987,000
- Mod P000022016-12-16+$0= $987,000
- Mod P000032017-01-12+$97,888= $1,084,888
- Mod P000042017-01-20+$0= $1,084,888
- Mod P000052017-03-02+$0= $1,084,888
- Mod P000062017-03-08+$46,207= $1,131,095
- Mod P000072017-04-27+$0= $1,131,095
- Mod P000082017-04-28+$0= $1,131,095
- Mod P000092017-05-19+$124,172= $1,255,267
- Mod P000102017-05-24+$47,776= $1,303,043
- Mod P000112017-08-25+$0= $1,303,043
- Mod P000122017-10-03+$2,327= $1,305,370
- Mod P000132017-10-31+$0= $1,305,370
- Mod P000142017-11-13+$0= $1,305,370
- Mod P000152017-11-30+$0= $1,305,370
- Mod P000162017-12-14+$37,924= $1,343,294
- Mod P000192021-04-22-$0= $1,343,294
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2016-08-26 | +$987,000 | $987,000 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT IGF::OT::IGF |
| Mod P00001· CHANGE ORDER | 2016-12-12 | +$0 | $987,000 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 1 IGF::OT::IGF |
| Mod P00002· CHANGE ORDER | 2016-12-16 | +$0 | $987,000 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 2 IGF::OT::IGF |
| Mod P00003· DEFINITIZE CHANGE ORDER | 2017-01-12 | +$97,888 | $1,084,888 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 3 IGF::OT::IGF |
| Mod P00004· CHANGE ORDER | 2017-01-20 | +$0 | $1,084,888 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 4 IGF::OT::IGF |
| Mod P00005· CHANGE ORDER | 2017-03-02 | +$0 | $1,084,888 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 5 IGF::OT::IGF |
| Mod P00006· CHANGE ORDER | 2017-03-08 | +$46,207 | $1,131,095 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 6 IGF::OT::IGF |
| Mod P00007· SUPPLEMENTAL AGREEMENT FOR WORK WITHIN SCOPE | 2017-04-27 | +$0 | $1,131,095 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 7 IGF::OT::IGF |
| Mod P00008· CHANGE ORDER | 2017-04-28 | +$0 | $1,131,095 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 8 IGF::OT::IGF |
| Mod P00009· CHANGE ORDER | 2017-05-19 | +$124,172 | $1,255,267 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 9 IGF::OT::IGF |
| Mod P00010· CHANGE ORDER | 2017-05-24 | +$47,776 | $1,303,043 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 10 IGF::OT::IGF |
| Mod P00011· CHANGE ORDER | 2017-08-25 | +$0 | $1,303,043 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 11 59 DAY PERIOD OF PERFORMANCE EXTENSION IGF::OT::IGF |
| Mod P00012· CHANGE ORDER | 2017-10-03 | +$2,327 | $1,305,370 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 12 UNFORESEEN SITE CONDITION WITH INLET ELEVATION IGF::OT::I… |
| Mod P00013· CHANGE ORDER | 2017-10-31 | +$0 | $1,305,370 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 13 CAPTURE RAIN DELAY DAYS ADD THEM BACK INTO THE CONTRACT I… |
| Mod P00014· CHANGE ORDER | 2017-11-13 | +$0 | $1,305,370 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 14 UNILATERAL MOD FOR INLET REPAIR IGF::OT::IGF |
| Mod P00015· CHANGE ORDER | 2017-11-30 | +$0 | $1,305,370 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 15 UNILATERAL ZERO DOLLAR 59 DAY POP EXTENSION MOD IGF::OT::… |
| Mod P00016· CHANGE ORDER | 2017-12-14 | +$37,924 | $1,343,294 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 16 UNFORESEEN SITE CONDITION WITH INLET ELEVATION IGF::OT::I… |
| Mod P00019· OTHER ADMINISTRATIVE ACTION | 2021-04-22 | −$0 | $1,343,294 | CONSTRUCT TEMPLE VA SOUTH VISITOR PARKING LOT MOD 16 UNFORESEEN SITE CONDITION WITH INLET ELEVATION |
Related awards · 11
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI WB1KNAULH895)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25724C0018 | 257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $2,170,321 | FY2024 |
| 36C25723C0058 | 257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $3,052,249 | FY2023 |
| 36C25723C0017 | 257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2DZ · REPAIR OR ALTERATION OF OTHER HOSPITAL BUILDINGS | $1,594,869 | FY2023 |
| 36C25723P0053 | 257-NETWORK CONTRACT OFFICE 17 (36C257) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $122,260 | FY2023 |
| 36C25723C0001 | 257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2PZ · REPAIR OR ALTERATION OF OTHER NON-BUILDING FACILITIES | $1,341,012 | FY2023 |
| 36C25722P0598 | 257-NETWORK CONTRACT OFFICE 17 (36C257) · Z2NE · REPAIR OR ALTERATION OF WATER SUPPLY FACILITIES | $73,700 | FY2022 |
Other recipients under Y1DZ from 257-NETWORK CONTRACT OFFICE 17 (36C257) (most recent first)
| Award | Recipient | Office | Net obligations | FY |
|---|---|---|---|---|
| 36C25726C0044 | DAX SAFETY & STAFFING SOLUTIONS, LLC | 257-NETWORK CONTRACT OFFICE 17 (36C257) | $3,186,506 | FY2026 |
| 36C25726C0017 | PARADIGM ENGINEERS AND CONSTRUCTORS, PLLC | 257-NETWORK CONTRACT OFFICE 17 (36C257) | $239,571 | FY2026 |
| 36C25726N0104 | BWHIT INFRASTRUCTURE SOLUTIONS LLC | 257-NETWORK CONTRACT OFFICE 17 (36C257) | $883,100 | FY2026 |
| 36C25726C0006 | INTEGRATED MODULAR SOLUTIONS, LLC | 257-NETWORK CONTRACT OFFICE 17 (36C257) | $153,612 | FY2026 |
| 36C25725N0404 | HAMILTON PACIFIC CHAMBERLAIN LLC | 257-NETWORK CONTRACT OFFICE 17 (36C257) | $1,830,355 | FY2025 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25716C0145_3600_-NONE-_-NONE- · retrieved 2026-09-26.