Description
IGF::OT::IGF INCREASE PER REA
Base award description: IGF::OT::IGF CONSTRUCT FIRING RANGE
Modification chain · 12 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2015-06-23+$2,834,039= $2,834,039
- Mod P000012016-03-03+$96,145= $2,930,184
- Mod P000022016-07-21+$0= $2,930,184
- Mod P000032016-09-13+$212,866= $3,143,050
- Mod P000042017-07-07+$4,110= $3,147,160
- Mod P000052017-10-04+$12,406= $3,159,565
- Mod P000062018-04-03+$14,034= $3,173,599
- Mod P000072018-05-16+$16,195= $3,189,794
- Mod P000082018-05-16+$10,855= $3,200,649
- Mod P000092018-07-09+$29,725= $3,230,373
- Mod P000102018-07-24+$15,278= $3,245,652
- Mod P000112019-02-27+$69,654= $3,315,306
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2015-06-23 | +$2,834,039 | $2,834,039 | IGF::OT::IGF CONSTRUCT FIRING RANGE |
| Mod P00001· CHANGE ORDER | 2016-03-03 | +$96,145 | $2,930,184 | IGF::OT::IGF CONSTRUCT FIRING RANGE |
| Mod P00002· OTHER ADMINISTRATIVE ACTION | 2016-07-21 | +$0 | $2,930,184 | IGF::OT::IGF CONSTRUCT FIRING RANGE |
| Mod P00003· CHANGE ORDER | 2016-09-13 | +$212,866 | $3,143,050 | IGF::OT::IGF RELOCATION OF FIBER OPTICS. |
| Mod P00004· CHANGE ORDER | 2017-07-07 | +$4,110 | $3,147,160 | IGF::OT::IGF RELOCATION OF FIBER OPTICS. |
| Mod P00005· CHANGE ORDER | 2017-10-04 | +$12,406 | $3,159,565 | IGF::OT::IGF MODIFICATION 7,11,AND 12 |
| Mod P00006· CHANGE ORDER | 2018-04-03 | +$14,034 | $3,173,599 | IGF::OT::IGF MODIFICATION FOR MEZZANINE AND MINI SPLIT |
| Mod P00007· OTHER ADMINISTRATIVE ACTION | 2018-05-16 | +$16,195 | $3,189,794 | IGF::OT::IGF MODIFICATION FOR MEZZANINE AND MINI SPLIT |
| Mod P00008· OTHER ADMINISTRATIVE ACTION | 2018-05-16 | +$10,855 | $3,200,649 | IGF::OT::IGF MODIFICATION FOR MEZZANINE AND MINI SPLIT |
| Mod P00009· CHANGE ORDER | 2018-07-09 | +$29,725 | $3,230,373 | IGF::OT::IGF MODIFICATION FOR FIRE PROTECTION |
| Mod P00010· CHANGE ORDER | 2018-07-24 | +$15,278 | $3,245,652 | IGF::OT::IGF MODIFICATION FOR LIGHTNING PROTECTION |
| Mod P00011· OTHER ADMINISTRATIVE ACTION | 2019-02-27 | +$69,654 | $3,315,306 | IGF::OT::IGF INCREASE PER REA |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI YN8NXKHT1ME6)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| VA25615C0102 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $3,443,011 | FY2015 |
| VA25614C0163 | 256-NETWORK CONTRACT OFFICE 16 · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $620,316 | FY2014 |
| VA25614C0164 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $1,874,497 | FY2014 |
| VA25614C0125 | 256-NETWORK CONTRACT OFFICE 16 (36C256) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $794,557 | FY2014 |
| VA101V14C0028 | VBA FIELD CONTRACTING · Z1AA · MAINTENANCE OF OFFICE BUILDINGS | $1,575,799 | FY2014 |
| VA101V14P0406 | VBA FIELD CONTRACTING · 7290 · MISCELLANEOUS HOUSEHOLD AND COMMERCIAL FURNISHINGS AND APPLIANCES | $4,252 | FY2014 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25615C0105_3600_-NONE-_-NONE- · retrieved 2026-09-26.