Award recordCONTRACT

BOYKIN CONTRACTING GROUP, INC.

PIID VA25612C0230· VHA· 580-HOUSTON· Z2PC · REPAIR OR ALTERATION OF UNIMPROVED REAL PROPERTY (LAND)· FY2012· $210,544 net obligations· UEI ZYC4YDTGFHW3· SC

Description

MODIFICATION 2: UNFORSEEN SITE CONDITION IN UNDERGROUND ELEVATIONS REQUIRING AN UPGRAGE IN SEWER PIPING SIZE. UTILITIES SITE PREPARATION FOR NEW FISHER HOUSE PROJECT

Base award description: UTILITIES SITE PREPARATION FOR NEW FISHER HOUSE PROJECT

First action · last action
2012-06-06 · 2012-10-09
Transactions
3
First transaction's obligation
$205,900
Base + all options value (sum of deltas)
$210,544
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
4
SDVOSB flag on record
Yes (self-representation)
NAICS
237110 · WATER AND SEWER LINE AND RELATED STRUCTURES CONSTRUCTION

Modification chain · 3 transactions

Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.

$210,544$0Base award · 2012-06-06 · this action $205,900 · running total $205,900Modification P00001 · 2012-08-23 · this action $0 · running total $205,900Modification P00002 · 2012-10-09 · this action $4,644 · running total $210,544
  • Base2012-06-06+$205,900= $205,900
  • Mod P000012012-08-23+$0= $205,900
  • Mod P000022012-10-09+$4,644= $210,544
TransactionAction dateThis action (delta)Running totalDescription on this transaction
Base2012-06-06+$205,900$205,900UTILITIES SITE PREPARATION FOR NEW FISHER HOUSE PROJECT
Mod P00001· CHANGE ORDER2012-08-23+$0$205,900MODIFICATION 1: EXTEND SEVEN CALENDAR DAYS UTILITIES SITE PREPARATION FOR NEW FISHER HOUSE PROJECT
Mod P00002· CHANGE ORDER2012-10-09+$4,644$210,544MODIFICATION 2: UNFORSEEN SITE CONDITION IN UNDERGROUND ELEVATIONS REQUIRING AN UPGRAGE IN SEWER PIPING SIZE.…

Related awards · 6

Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.

Other VA awards to the same recipient (UEI ZYC4YDTGFHW3)

AwardOffice · PSC / listingNet obligationsFY
VA24616J1348246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$0FY2016
VA25616J1106598-NORTH LITTLE ROCK(00598) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$142,232FY2016
VA24616J1227246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$417,884FY2016
VA24616P1180246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$7,183FY2016
VA24616J1223246-NETWORK CONTRACTING OFFICE 6 (36C246) · Z1DZ · MAINTENANCE OF OTHER HOSPITAL BUILDINGS$332,490FY2016
VA25616J0837598-NORTH LITTLE ROCK(00598) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES$118,901FY2016

Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25612C0230_3600_-NONE-_-NONE- · retrieved 2026-09-26.