Description
CONSTRUCTION OF MENTAL HEALTH BUILDING
First action · last action
2011-12-20 · 2014-10-15
Transactions
8
First transaction's obligation
$7,864,900
Base + all options value (sum of deltas)
$15,745,124
Extent competed
FULL AND OPEN COMPETITION AFTER EXCLUSION OF SOURCES
Other than full & open authority
—
Set-aside
SERVICE DISABLED VETERAN OWNED SMALL BUSINESS SET-ASIDE
Offers received
3
SDVOSB flag on record
Yes (self-representation)
NAICS
236220 · COMMERCIAL AND INSTITUTIONAL BUILDING CONSTRUCTION
Modification chain · 8 transactions
Each row is one published transaction. This action is the obligation recorded on that transaction — a change amount, as USAspending publishes it. Running total is computed by Glassbox VA as the cumulative sum of those amounts up to and including the row, so the last running total equals the award's net obligations shown above. The cumulative-total columns in the source files are not used: they are not frozen per modification.
- Base2011-12-20+$7,864,900= $7,864,900
- Mod 12012-05-20+$0= $7,864,900
- Mod 22012-06-22+$0= $7,864,900
- Mod P000032013-11-06+$5,341= $7,870,241
- Mod P000042014-05-15+$7,864,900= $15,735,141
- Mod P000052014-05-15+$4,795= $15,739,936
- Mod P000072014-10-14+$0= $15,739,936
- Mod P000062014-10-15+$5,188= $15,745,124
| Transaction | Action date | This action (delta) | Running total | Description on this transaction |
|---|---|---|---|---|
| Base | 2011-12-20 | +$7,864,900 | $7,864,900 | CONSTRUCTION OF MENTAL HEALTH BUILDING |
| Mod 1· CHANGE ORDER | 2012-05-20 | +$0 | $7,864,900 | CONSTRUCTION OF MENTAL HEALTH BUILDING |
| Mod 2· CHANGE ORDER | 2012-06-22 | +$0 | $7,864,900 | CONSTRUCTION OF MENTAL HEALTH BUILDING |
| Mod P00003· CHANGE ORDER | 2013-11-06 | +$5,341 | $7,870,241 | CONSTRUCTION OF MENTAL HEALTH BUILDING |
| Mod P00004· CHANGE ORDER | 2014-05-15 | +$7,864,900 | $15,735,141 | CONSTRUCTION OF MENTAL HEALTH BUILDING |
| Mod P00005· CHANGE ORDER | 2014-05-15 | +$4,795 | $15,739,936 | CONSTRUCTION OF MENTAL HEALTH BUILDING |
| Mod P00007· OTHER ADMINISTRATIVE ACTION | 2014-10-14 | +$0 | $15,739,936 | CONSTRUCTION OF MENTAL HEALTH BUILDING |
| Mod P00006· CHANGE ORDER | 2014-10-15 | +$5,188 | $15,745,124 | CONSTRUCTION OF MENTAL HEALTH BUILDING |
Related awards · 6
Awards are related by an explicit link in the data, stated for each group below — never by text similarity. Values are net obligations.
Other VA awards to the same recipient (UEI UVR8K1KKR675)
| Award | Office · PSC / listing | Net obligations | FY |
|---|---|---|---|
| 36C25920P0836 | NETWORK CONTRACT OFFICE 19 (36C259) · Y1DA · CONSTRUCTION OF HOSPITALS AND INFIRMARIES | $120,573 | FY2020 |
| 36C25919C0298 | NETWORK CONTRACT OFFICE 19 (36C259) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $169,789 | FY2019 |
| 36C25919C0174 | NETWORK CONTRACT OFFICE 19 (36C259) · Z2DA · REPAIR OR ALTERATION OF HOSPITALS AND INFIRMARIES | $3,312,937 | FY2019 |
| 36C25919C0074 | NETWORK CONTRACT OFFICE 19 (36C259) · Z1LA · MAINTENANCE OF AIRPORT SERVICE ROADS | $121,452 | FY2019 |
| 36C25919C0041 | NETWORK CONTRACT OFFICE 19 (36C259) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $76,240 | FY2019 |
| 36C25918C0326 | NETWORK CONTRACT OFFICE 19 (36C259) · Z1DA · MAINTENANCE OF HOSPITALS AND INFIRMARIES | $21,478 | FY2018 |
Cite as: Glassbox VA record view · VA contract (USAspending / FPDS) · CONT_AWD_VA25612C0086_3600_-NONE-_-NONE- · retrieved 2026-09-26.